Vitreous LabsEnergy transparency
The lead · register read 29 September 2026

Great Britain has 55 GW of batteries waiting on paper for every gigawatt that runs.

NESO’s connection register holds 426 GW of storage projects. The balancing mechanism register holds 7.8 GW of batteries that trade. This year’s reform gave every permitted megawatt to projects that were already protected, so the useful question is which of the 426 GW will never be built, and at which substation the capacity comes back.

One dot is one gigawatt. A hollow dot is a request on paper. A solid dot is a battery that runs.

Every dot is a gigawatt in the connection register; the solid ones are the batteries that trade today.

Great Britain 426 GW waiting on paper7.8 GW running
Waiting to connectRunning, measured from settlement

NESO connection register read 29 September 2026; running fleet from Elexon’s balancing mechanism register, 29 September 2026.

Open the Development Atlas

One market today, read the same way everywhere

The same method in each country: the connection register, the operating fleet and what the fleet is paid, all from published files, rebuilt on every refresh.

Great Britain

Registers read twice a week since August 2026
7.8 GWrunning, on 206 sites, each with its own page
426 GWin the connection queue, 266 GW of it traced to 76 named developers
Zeropermitted battery capacity left in all nineteen zones after the reform
£53/kW/yrwhat 141 batteries were actually paid in the year to 27 September

Italy

First read October 2026

Terna publishes the requests to connect to the Italian transmission grid every month, by municipality. On 8 September 2026 Italy signed the law that hands capacity to the projects that hold a permit and orders the applicants published by name. We are reading the register now and will publish once two monthly reads agree with Terna’s own totals.

Development Atlas, comingFleet, later

Three products

The register is free because it traces to published files. The work we add sits behind a key.

The Fleet

Every operating battery: what it earns, who owns it, who trades it, and what it is doing right now, measured from settlement rather than modelled.

FreeGreat Britain

The Development Atlas

The connection queue on a map: what is contracted, what is likely to fail, where capacity comes back, and what changed since the last read. Who is really behind each project is the part we resolve ourselves.

FreeKeyGreat Britain

The Forecast

Tomorrow’s price, published each morning before the auction, and the long term view drawn from every public report so a page never shows nothing.

FreeGreat Britain

How it is kept honest

Every number traces to a published file or is labelled as inference. The three marks below appear on every map and every page.

MeasuredRead directly from a published register, settlement file or filing, with the date it was read.
InferredWorked out by us, for instance a coordinate derived from a substation name. Drawn differently and explained in the popup.
Not publishedLeft blank. Where the data does not exist in any published file, we say so instead of estimating.

How every number is worked out  ·  What you may do with each layer

The Friday ledger

Every Friday, every change in the queue since the last read: new requests, withdrawals, dates that moved, capacity that came back. One email, no commentary you did not ask for.

Confirm by email, unsubscribe from any issue. We store the address and nothing else.

Sign up for the ledger

The ledger covers Great Britain today.