Erskine BESS

30 MW in South West Scotlands. Everything on this page is read from published data for the 364 days to 19 August 2026, or is labelled as an estimate.

What it is

Registered power30 MW balancing mechanism registration
Storage duration2.0 hours capacity market de-rating class
Charging zoneSouth West Scotlands
Connection siteRenfrewshire
PostcodePA7 5NT
Balancing mechanism unitE_ERSKB-1

Who owns it and who trades it

Traded byEDF Energy Customers Limitedruns several sites
Owned byCARE POWER (ERSKINE) LIMITED
Owner established fromcapacity market registered holder

Market registers name the party that sells into the market, which for a battery is usually an optimiser under contract rather than the owner. How we tell them apart

What it earned

Line364 days to 19 August 2026
Balancing mechanism£12k
Response and reserve auctions auction implied£71k
Capacity market£307k
Three lines together£391k

Balancing is offer revenue and does not net off the cost of the power. The response and reserve figure is the value implied by the published auction results, award quantity times clearing price times the length of the delivery window, and not a settled payment. Capacity market income is at the price the agreement cleared at, before inflation uprating, so it is a floor. Method

What it might have earned trading, estimated

At our middle assumption£691k
Across the range£532k to £851k
Energy cycled in the year21,827 MWh

This one is a model, not a measurement. Nobody publishes what any site traded. It is never added to the measured lines. How it is worked out and what is wrong with it

See it on the map

Open the operating map here

Every figure on this page traces to a published file. If something here is wrong about your asset, the methods section says how to tell us.