Vitreous LabsEnergy transparency

Octopus Energy Trading Limited

Sells into the markets for 8 units at 8 sites, 298 MW together, over the 364 days to 28 August 2026. Everything here is measured from published settlement and auction results; wholesale trading is invisible for every optimiser, not just this one.

The book

Balancing mechanism, paid to discharge£1.1m
Balancing mechanism, paid out to charge−£2.0m
Response and reserve auctions£663k
Capacity market£2.1m
Income across the book, per kilowatt£13.00/kW/yr fleet 33.63
Median unit, all three lines£12.45/kW/yr
Hours at full power, sent out62 h/yr
Hours at full power, taken in398 h/yr

What the book is made of

Performance follows portfolio shape as much as skill: a Scottish, long duration book does a different job from an English one hour book, so the mix belongs beside the money, not in a footnote.

Duration, by megawatt

about 1 hour 42 MW · about 1.5 hours 40 MW · 2 hours and up 190 MW · not published 26 MW

Region, by megawatt

Scotland 142 MW · England and Wales 156 MW

Every unit it sells for

UnitMWBalancingStanding readyCM£/kW/yr
WEST DIDSBURY
North Midlands and North Wales
45£24k£535k12.45
AR0006-BLOX
Mid Wales and The Midlands
42£741k£167k£98k24.19
Coupar Battery Storage
Eastern Grampian and Tayside
41£90k£108k£291k11.88
Shilton Lane BESS
South West Scotlands
40£195k£43k5.96
Stairfoot
North Midlands and North Wales
40£75k£251k8.19
Arbroath Battery Storage
Eastern Grampian and Tayside
34£97k£94k£297k14.20
WBRD-01
South Lancashire, Yorkshire and Humber
29£20k£595k21.28
BYBRB-1
Eastern Grampian and Tayside
26£134k5.15

Attribution. A unit belongs to whoever the market registers as its seller today, so a book that changed hands mid year credits the whole year to the current seller. We have recorded optimiser switches since 27 August 2026 and the record deepens from here. Corporate families are not joined: a platform selling through several registered entities appears as several rows on the optimiser list.

All optimisers