Vitreous LabsEnergy transparency

Ernesettle

19 MW, about 19 MWh (1 hour, from the capacity market de-rating class) in West Devon and Cornwall. Everything on this page is read from published data for the 364 days to 22 September 2026, or is labelled as an estimate.

What it is

Registered power19 MW response and reserve auction registration
Storage duration1.0 hours capacity market de-rating class
Charging zoneWest Devon and Cornwall
PostcodePL5 2TS
Balancing mechanism unitV__LCEND005 a virtual unit registered by the company that trades it; its balancing actions are not yet counted on this site

Who owns it and who trades it

Traded byCentrica Business Solutions UK Optimisation Limitedauction results, unchecked
Owned byIRE 001 LIMITED
Owner established fromcapacity market registered holder
UltimatelyRGREEN INVEST (Arlington Energy developed) confirmed source

How we know. Both project companies are controlled by Infragreen 4 RE UK Limited, the UK holding company for RGREEN INVEST's InfraGreen IV fund. ARL 001 was controlled by Arlington Energy Limited until March 2021, and RGREEN and Arlington each announced the four plant investment in December 2021.

Market registers name the party that sells into the market, which for a battery is usually an optimiser under contract rather than the owner. This unit is registered only in the response and reserve auctions, so the seller is the participant NESO's auction results name, and Elexon's register carries no entry to check it against. How we tell them apart

What it earned

Line364 days to 22 September 2026
Balancing mechanismnot yet counted
Response and reserve auctions auction implied£250k
Capacity market£59k
Three lines together£309k

Balancing is offer revenue and does not net off the cost of the power. The response and reserve figure is the value implied by the published auction results, award quantity times clearing price times the length of the delivery window, and not a settled payment. Capacity market income is at the price the agreement cleared at, before inflation uprating, so it is a floor. Method

Outside the balancing mechanism, estimated from metered peers

Elexon publishes no metered output for this battery. Its balancing registration, V__LCEND005, is a virtual unit registered by the company that trades it, and this site reads no meter for it, so nothing can be derived for it. What can be said is what its peers did: 15 units of about 1 hour in England and Wales, metered, earned between £-0.22 and £26.99 per kilowatt a year with the balancing legs and the position outside the balancing mechanism together, £5.99 at the median. Applied to this unit's 19 MW that is £114k, in a range of −£4k to £513k. An estimate from other batteries, never this one's figure. Method

Where it stands

All three measured lineswhole fleet, £/kW/yr34th percentile199 units

Percentiles, so 90 means better than nine in ten of the cohort named beside it, on that measure alone, over the same 364 days. Rates are pounds per kilowatt per year, annualised over the days the unit has been on the system, the same figures the performance league ranks on. A high position in the taken-in table is not a fault: a constraint asset is paid to charge, and charging is its job.

The nearest comparables

The five nearest in size in England and Wales, and this battery among them, ranked by what each was paid for every kilowatt it holds over the 364 days to the same date. They run for about the same length of time. Same market, same rules, same weather.

BatteryMWHoursMeasured, per kW
Gses 1 (GSET-04)181h£42.9/kW/yr
Gses 1 (GSET-05)181h£39.8/kW/yr
Gerrards Cross BESS201h£36.3/kW/yr
Gses 1 (GSET-03)181h£31.7/kW/yr
Fareham Reserve181h£29.5/kW/yr
Ernesettlethis battery191h£16.3/kW/yr

See it on the map

Open the operating map here

Every figure on this page traces to a published file. If something here is wrong about your asset, the methods section says how to tell us.