Circle area is the megawatts
Germany · Marktstammdatenregister · export of 15 October 2026
4,337 MW of batteries are registered as operating in Germany, and 9,326 MW more are registered as planned. A further 3,304 MW registered as planned is held apart as doubtful.
The Marktstammdatenregister is the Bundesnetzagentur’s register of every power unit in Germany, filled in by operators and checked by grid operators. This is every storage unit of a megawatt or more in it: 1,264 batteries, 542 of them operating and 707 registered as planned, and 108 pumped storage units, drawn where the register places them. The planned figure counts 655 of the planned batteries; the other 52 are held apart, for the reasons in the tables below. A planned unit is one its operator chose to register early; the queue of connection requests is published only as totals by the regulator. The Germany page reads the same register as tables.
Showing every storage unit of a megawatt or more. Filter by status, state or grid operator check, or search a unit, an operator or a place.
Every unit in the register, a megawatt and up
Largest first. Click a row to centre the map on the unit. Power is net nominal power; capacity is the installation’s usable capacity where the register has it. The date is commissioning for an operating unit and the operator’s planned date for a planned one. A planned unit held apart from the planned figure says so; click it on the map for the reason.
| Unit | Operator | Place | Status | MW | MWh | Date |
|---|
Held apart from the planned figure, 3,304 MW in 52 units
These units are registered as planned and stay on the map, in the table and in the download, drawn in pale blue. They are left out of the planned figure because each looks doubtful: 3,000 MW registered but not announced by the owner, 7.5 MW that looks like a duplicate entry, 197 MW in a series registered together and never updated after its planned date passed and 100 MW whose planned date passed more than a year ago. A unit is overdue when its planned date passed more than a year before the register export of 15 October 2026.
| Unit | Where | MW | Planned for | Why it is held apart |
|---|---|---|---|---|
| GigaBattery Jänschwalde 2000 | Teichland, Brandenburg | 1,000 | 31 Dec 2028 | registered, not announced |
| GigaBattery Lippendorf 1000 | Neukieritzsch, Sachsen | 1,000 | 31 Dec 2028 | registered, not announced |
| GigaBattery Boxberg 1000 | Boxberg/O.L., Sachsen | 1,000 | 31 Dec 2028 | registered, not announced |
| Batteriespeicher Gersthofen 2 | Gersthofen, Bayern | 7.5 | 1 Nov 2026 | probable duplicate |
| Großbatteriespeicher | Türkheim, Bayern | 30 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Irsingen | Türkheim, Bayern | 25 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Irsingen | Türkheim, Bayern | 20 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Schwenningen | Schwenningen, Bayern | 20 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Illertissen | Auwald, Bayern | 10 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Burgau | Burgau, Bayern | 10 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Illertissen | Auwald, Bayern | 10 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Horgau | Horgau, Bayern | 10 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Höchstädt | Höchstädt a.d. Donau, Bayern | 10 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Bubesheim | Bubesheim, Bayern | 10 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Langerringen | Langerringen, Bayern | 10 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Untereichen | Altenstadt, Bayern | 10 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Heimertingen | Heimertingen, Bayern | 10 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Großbatteriespeicher Nersingen | Nersingen, Bayern | 10 | 31 Dec 2025 | one of a series registered together, never updated, its planned date passed |
| Batterieanlage Werneuchen | Werneuchen, Brandenburg | 10 | 31 Mar 2025 | planned date passed more than a year ago |
| Speicher Stuttgart-Münster | Stuttgart, Baden-Württemberg | 9.7 | 30 Jun 2025 | planned date passed more than a year ago |
| Speicher Lübbenau AK 1 | Lübbenau/Spreewald, Brandenburg | 6.7 | 1 Oct 2024 | planned date passed more than a year ago |
| Batterie | Elsterheide, Sachsen | 6.7 | 31 Mar 2024 | planned date passed more than a year ago |
| Bereich Nord Speicher | Malchow, Mecklenburg-Vorpommern | 6.5 | 1 Sep 2025 | planned date passed more than a year ago |
| Bereich Süd Speicher | Malchow, Mecklenburg-Vorpommern | 5.2 | 1 Sep 2025 | planned date passed more than a year ago |
| PV-Park Fuchsgrube Speicher | Ellzee, Bayern | 3.7 | 30 Jun 2025 | planned date passed more than a year ago |
| Speicher BAB60 | Wilsecker, Rheinland-Pfalz | 3.5 | 31 Mar 2023 | planned date passed more than a year ago |
| Speicher Waidhaus | Waidhaus, Bayern | 3.4 | 11 Apr 2023 | planned date passed more than a year ago |
| Balder A09 - BSK | Tützpatz, Mecklenburg-Vorpommern | 3.4 | 2 Jan 2023 | planned date passed more than a year ago |
| 20128 SP Hans-Seidel-Schacht Speicher | Eisleben, Sachsen-Anhalt | 3.3 | 30 Nov 2021 | planned date passed more than a year ago |
| Speichersystem Innovation US2 | Untersiemau, Bayern | 2.9 | 30 Sep 2021 | planned date passed more than a year ago |
| Batteriespeicher Waldmattensee | Lahr/Schwarzwald, Baden-Württemberg | 2.5 | 1 Sep 2025 | planned date passed more than a year ago |
| Speicher Test | Nürnberg, Bayern | 2.5 | 1 Jul 2022 | planned date passed more than a year ago |
| Solarpark Leer | Leer (Ostfriesland), Niedersachsen | 2.4 | 1 Aug 2025 | planned date passed more than a year ago |
| 067-Treuenbrietzen-Speicher | Treuenbrietzen, Brandenburg | 2.2 | 31 Oct 2024 | planned date passed more than a year ago |
| Speicher Krücklham | Gars a. Inn, Bayern | 2.0 | 31 Jan 2022 | planned date passed more than a year ago |
| Batteriespeicher Solarpark Nutteln | Nutteln, Schleswig-Holstein | 2.0 | 3 Mar 2025 | planned date passed more than a year ago |
| Speicher 1 der Freiflächenanlage Deponie Edesheim | Edesheim, Rheinland-Pfalz | 1.9 | 1 Jun 2025 | planned date passed more than a year ago |
| Batteriespeicher | Wetter (Ruhr), Nordrhein-Westfalen | 1.9 | 4 Apr 2022 | planned date passed more than a year ago |
| Bereich Rest Speicher | Malchow, Mecklenburg-Vorpommern | 1.6 | 1 Sep 2025 | planned date passed more than a year ago |
| HMM-2022-005-1 Langhagen-Speicher | Lalendorf, Mecklenburg-Vorpommern | 1.5 | 31 Oct 2024 | planned date passed more than a year ago |
| BESS Uphusen | Achim, Niedersachsen | 1.5 | 31 Jul 2025 | planned date passed more than a year ago |
| ABO Batterie Heimertingen | Heimertingen, Bayern | 1.5 | 31 Mar 2024 | planned date passed more than a year ago |
| Speicher 3,3 MW Ottenbüttel | Ottenbüttel, Schleswig-Holstein | 1.5 | 31 Oct 2022 | planned date passed more than a year ago |
| 20343 SP Wimmelburg_Speicher | Hergisdorf, Sachsen-Anhalt | 1.4 | 30 Sep 2021 | planned date passed more than a year ago |
| Anlage 3750 Batterie | Herbstein, Hessen | 1.2 | 31 Mar 2025 | planned date passed more than a year ago |
| Batteriespeicher PV- Anlage Hasselwerder | Hamburg, Hamburg | 1.2 | 31 Jan 2023 | planned date passed more than a year ago |
| BSS Saarwellingen | Saarwellingen, Saarland | 1.2 | 15 Jul 2025 | planned date passed more than a year ago |
| HMM-2022-036 Zurow-Speicher | Zurow, Mecklenburg-Vorpommern | 1.1 | 31 Oct 2024 | planned date passed more than a year ago |
| PV-Batterie-Vogelherd | Ölbronn-Dürrn, Baden-Württemberg | 1.0 | 1 Sep 2025 | planned date passed more than a year ago |
| Evciler | Krefeld, Nordrhein-Westfalen | 1.0 | 1 Sep 2025 | planned date passed more than a year ago |
| Testfeld KT | Kitzingen, Bayern | 1.0 | 1 Oct 2019 | planned date passed more than a year ago |
| HLB2 | Heilbronn, Baden-Württemberg | 1.0 | 1 Feb 2024 | planned date passed more than a year ago |
Decided by hand, 25 units, with the evidence
Each of these was checked by hand against the register and the owners’ own announcements on 11 October 2026, and the series again on 16 October 2026. A capacity entered in MWh is shown corrected and an impossible date is left blank; the register’s own values stay in the download.
| Unit | Where | MW | Flag | Evidence |
|---|---|---|---|---|
| GigaBattery Jänschwalde 2000 | Teichland, Brandenburg | 1,000 | registered, not announced | GigaBattery Jänschwalde 2000, LEAG Clean Power, registered 22 May 2026 at 1,000 MW and 4,000 MWh with the planned date 31 December 2028, at the same point as Jänschwalde 1000. LEAG names two GigaBattery projects on its own page and in the press, Jänschwalde 1000 (1,000 MW, 4,000 MWh) and Boxberg 400 (400 MW, 1,600 MWh); no announcement of this one was found (https://www.leag.de/en/gigawattfactory/batteriespeicher/gigabatteries/, checked 11 October 2026). |
| GigaBattery Lippendorf 1000 | Neukieritzsch, Sachsen | 1,000 | registered, not announced | GigaBattery Lippendorf 1000, LEAG Clean Power, registered 22 May 2026 at 1,000 MW and 4,000 MWh with the planned date 31 December 2028. LEAG names two GigaBattery projects on its own page and in the press, Jänschwalde 1000 (1,000 MW, 4,000 MWh) and Boxberg 400 (400 MW, 1,600 MWh); no announcement of this one was found (https://www.leag.de/en/gigawattfactory/batteriespeicher/gigabatteries/, checked 11 October 2026). |
| GigaBattery Boxberg 1000 | Boxberg/O.L., Sachsen | 1,000 | registered, not announced | GigaBattery Boxberg 1000, LEAG Clean Power, registered 22 May 2026 at 1,000 MW and 4,000 MWh with the planned date 31 December 2028, beside Boxberg 400 and the 100 MW Big Battery Oberlausitz. LEAG names two GigaBattery projects on its own page and in the press, Jänschwalde 1000 (1,000 MW, 4,000 MWh) and Boxberg 400 (400 MW, 1,600 MWh); no announcement of this one was found (https://www.leag.de/en/gigawattfactory/batteriespeicher/gigabatteries/, checked 11 October 2026). |
| Batteriespeicher Gersthofen 2 | Gersthofen, Bayern | 7.5 | probable duplicate | Batteriespeicher Gersthofen 2, registered as planned by Bayernwerk Natur on 21 July 2026 at 7.5 MW. The same name and power appear as an operating unit of LEW Natur, SEE995288152438, commissioned 2 July 2026, about 130 m away. LEW and Bayernwerk Natur build such plants together, as at Meitingen in 2023 (https://www.bayern-innovativ.de/en/emagazine/detail/en/page/lew-and-bayernwerk-natur-with-new-large-scale-storage-facility). The operating entry is counted. |
| Großbatteriespeicher | Türkheim, Bayern | 30 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Irsingen | Türkheim, Bayern | 25 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Irsingen | Türkheim, Bayern | 20 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Schwenningen | Schwenningen, Bayern | 20 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Illertissen | Auwald, Bayern | 10 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Burgau | Burgau, Bayern | 10 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Illertissen | Auwald, Bayern | 10 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Horgau | Horgau, Bayern | 10 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Höchstädt | Höchstädt a.d. Donau, Bayern | 10 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Bubesheim | Bubesheim, Bayern | 10 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Langerringen | Langerringen, Bayern | 10 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Untereichen | Altenstadt, Bayern | 10 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Heimertingen | Heimertingen, Bayern | 10 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Großbatteriespeicher Nersingen | Nersingen, Bayern | 10 | stale series | One of 14 planned units, 196.6 MW together, that Hermann Braig Entsorgungsfachbetrieb registered between 11 and 24 February 2025, each at its own site in Bavarian Swabia (Altenstadt, Auwald twice, Bubesheim, Burgau, Heimertingen, Horgau, Höchstädt, Langerringen, Nersingen, Schwenningen and Türkheim three times), all on LEW Verteilnetz at the high to medium voltage level and sized in steps of 10.08 MW with two hours of storage. Every one carries the planned date 31 December 2025 and none has been updated since it was registered. A fifteenth, Lauben, was moved to 31 December 2027 on 4 August 2026 and is counted. Held apart until the operator updates the series. Read from the daily register table of 15 October 2026; first described as probable duplicates on 11 October 2026, a label corrected on 16 October 2026 because the sites are separate. |
| Batteriespeicher Saarlouis-Lisdorf | Saarlouis, Saarland | 5.0 | capacity entered in MWh | Batteriespeicher Saarlouis-Lisdorf, 5.04 MW, registered with a usable capacity of 9.556 kWh, under a minute of its power. Read as 9.556 MWh it runs 1.9 hours, like its peers. Shown as 9.6 MWh; the register value stays in the download. |
| Strs | Trossingen, Baden-Württemberg | 3.0 | capacity entered in MWh | Strs, 3.0 MW, registered with a usable capacity of 8 kWh, under a minute of its power. Read as 8 MWh it runs 2.7 hours. Shown as 8 MWh; the register value stays in the download. |
| Stromspeicher 1 | Hengersberg, Bayern | 2.5 | capacity entered in MWh | Stromspeicher 1, 2.5 MW, registered with a usable capacity of 5.796 kWh, under a minute of its power. Read as 5.796 MWh it runs 2.3 hours. Shown as 5.8 MWh; the register value stays in the download. |
| ABR955057773547 | Hohenstein-Ernstthal, Sachsen | 2.5 | capacity entered in MWh | A 2.5 MW unit named with its operator number, ABR955057773547, registered with a usable capacity of 5 kWh, under a minute of its power. Read as 5 MWh it runs 2 hours. Shown as 5 MWh; the register value stays in the download. |
| Big Battery Lausitz | , Brandenburg | 66 | MaStR and owner disagree | Big Battery Lausitz, Lausitz Energie Kraftwerke (LEAG), registered at 66 MW and 52.6 MWh. It was reported at 50 MW when it was built (pv magazine, https://www.pv-magazine.de/?p=16237); the MWh agree and the MW do not. Counted at the register’s 66 MW. The register gives it no coordinates or municipality. |
| Batteriespeicher Cremzow | Randowtal, Brandenburg | 2.8 | MaStR and owner disagree | Batteriespeicher Cremzow, Enel Green Power, registered at 2.8 MW net power against 22 MW gross, with 34.6 MWh. Its builders announced it as a 22 MW battery (pv magazine, 20 May 2019, https://www.pv-magazine.com/2019/05/20/enertrag-enel-and-leclanche-commission-22-mw-storage-project-in-germany/). Counted at the register’s 2.8 MW, the power the operator declared for the grid. |
| Speicher | Bokholt-Hanredder, Schleswig-Holstein | 1.0 | impossible date | A 1 MW battery named Speicher, shut down for good, registered with the commissioning date 1 May 1923, which cannot be right for a battery of this size. The date is left blank on the pages; the register value stays in the download. |
Checks on the register’s entries, 25 flagged
The register is filled in by operators and checked by grid operators, and these are the entries that look odd when read mechanically. Nothing is dropped: a unit flagged here stays in every count above, and this table says why a reader should treat it with care. The check is where the work on this register starts.
| Unit | Where | MW | What looks odd |
|---|---|---|---|
| GigaBattery Jänschwalde 1000 | Teichland, Brandenburg | 1,000 | same operator, municipality and power as GigaBattery Jänschwalde 2000, perhaps one plant registered twice |
| Battery Park Höxter 2 | Höxter, Nordrhein-Westfalen | 65 | same operator, municipality and power as Battery Park Höxter 1, perhaps one plant registered twice |
| Großbatteriespeicher Illertissen | Auwald, Bayern | 10 | same operator, municipality and power as Großbatteriespeicher Illertissen, perhaps one plant registered twice |
| BESS Herzebrock-Clarholz green flexibility | Herzebrock-Clarholz, Nordrhein-Westfalen | 10 | usable capacity is 15 hours of its power, over twelve hours |
| Speicher Krumpa West | Braunsbedra, Sachsen-Anhalt | 7 | same operator, municipality and power as Speicher Krumpa Ost, perhaps one plant registered twice |
| BESS Dummerstorf Energiewende 2 | Roggentin, Mecklenburg-Vorpommern | 7 | same operator, municipality and power as BESS Dummerstorf Energiewende 3, perhaps one plant registered twice |
| BESS 2 (HK16) | Lichtenau, Nordrhein-Westfalen | 5 | same operator, municipality and power as BESS 1 (HK05), perhaps one plant registered twice |
| W2_Powergrid_2 | Friedrichshafen, Baden-Württemberg | 4 | same operator, municipality and power as W2_Powergrid_1, perhaps one plant registered twice |
| BESS Warendorf green flexibility | Warendorf, Nordrhein-Westfalen | 3 | usable capacity is 15 hours of its power, over twelve hours |
| BESS Hagen i. Bremischen green flexibility | Hagen im Bremischen, Niedersachsen | 3 | usable capacity is 15 hours of its power, over twelve hours |
| BESS Esterwegen green flexibility | Esterwegen, Niedersachsen | 3 | usable capacity is 15 hours of its power, over twelve hours |
| BESS Lindern green flexibility | Lindern (Oldenburg), Niedersachsen | 3 | usable capacity is 15 hours of its power, over twelve hours |
| BESS Melle - Dratum | Melle, Niedersachsen | 3 | same operator, municipality and power as BESS Melle - Bennien, perhaps one plant registered twice |
| BESS Melle - Krukum | Melle, Niedersachsen | 3 | same operator, municipality and power as BESS Melle - Bennien, perhaps one plant registered twice |
| Batteriespeicher Cremzow | Randowtal, Brandenburg | 3 | usable capacity is 12 hours of its power, over twelve hours |
| BTC_PFL P11 | Salzbergen, Niedersachsen | 2 | usable capacity is 0.00 hours of its power, under a quarter of an hour |
| Solar-Speicher-Kraftwerk Gutengermendorf II | Löwenberger Land, Brandenburg | 2 | same operator, municipality and power as Solar-Speicher-Kraftwerk Gutengermendorf I, perhaps one plant registered twice |
| BTC_PFL P12 | Salzbergen, Niedersachsen | 2 | usable capacity is 0.00 hours of its power, under a quarter of an hour |
| Batteriespeicher | Senden, Nordrhein-Westfalen | 2 | same operator, municipality and power as Batteriespeicher 2, perhaps one plant registered twice |
| Batteriespeicher 2,5MWh Kötterhof 4 Halle 14/15 | Steinfeld (Oldenburg), Niedersachsen | 1 | same operator, municipality and power as Batteriespeicher 2,5MWh Rienshof 7 Halle1/2, perhaps one plant registered twice |
| BTC_PFL P09 | Salzbergen, Niedersachsen | 1 | usable capacity is 0.00 hours of its power, under a quarter of an hour |
| BTC_PFL P08 | Salzbergen, Niedersachsen | 1 | usable capacity is 0.00 hours of its power, under a quarter of an hour |
| BTC_PFL P05 | Salzbergen, Niedersachsen | 1 | usable capacity is 0.00 hours of its power, under a quarter of an hour |
| BTC_PFL P10 | Salzbergen, Niedersachsen | 1 | usable capacity is 0.00 hours of its power, under a quarter of an hour |
| Speicher | Bokholt-Hanredder, Schleswig-Holstein | 1 | usable capacity is 0.20 hours of its power, under a quarter of an hour |
Source: Marktstammdatenregister, Bundesnetzagentur, full export of 15 October 2026, read by Vitreous for storage units with a net nominal power of 1,000 kW or more; Datenlizenz Deutschland, Namensnennung 2.0. Status, power, capacity, dates and coordinates are as registered, except where a note says a value is shown corrected or left blank; the download keeps the register’s own values beside ours. A natural person among the operators is not named, as the register itself does not name one for small units. The connection queue is not in the register; its totals are the regulator’s own.