Italy · the system, right now

Italy’s electricity system, right now

What Italy is generating, using and trading, read from Terna every quarter hour, with the batteries drawn inside it, and beneath it each of the seven market zones.

Live  ·  Terna, through the ENTSO-E Transparency Platform

Where the power is coming from, and where it is going

Reading the flows.

Reading the system.

The flow as a table

The batteries, charging and discharging

Reading the fleet.

Reading the fleet.

Terna publishes what the batteries in each zone are doing as one series per zone, every quarter hour, and never a reading per battery while the day is running. The 14 operating sites the public record names, 0.8 GW, are listed with the zone they sit in on the projects page.

The last 24 hours

Reading the day.

Generation by source, stacked, with the borders’ net import as the pale band at the bottom and the load Terna had to meet drawn over it. Beneath it, on the same clock, what the batteries did: above their line they are sending power out, below it they are taking it in.

The day ends at the newest quarter hour every zone has reported in full, which is usually an hour or two behind the clock. Where the top of the stack sits below the load line, the gap is plant that Terna’s generation by type for the country does not cover that quarter hour; the zonal series carry more, and the zones beneath show them.

The cables

Reading the cables.

Physical flow on each border this quarter hour. Imports into Italy to the right, exports to the left, in megawatts. Switzerland, Greece and Montenegro are published by the hour, the others by the quarter hour.

Terna publishes no frequency on the platform, so there is no frequency panel here.

The seven zones

Reading the zones.

Reading.

The zones as a table

The largest batteries, unit by unit

Reading the units.

Reading.

Terna publishes the output of every unit of 100 MW or more one by one, but months after the day (the regulation allows five days; on 3 October 2026 the newest day published was 18 July), so this figure is never live: it shows the newest whole day Terna has published, midnight to midnight Italian time. Only the six batteries Terna types as energy storage appear; the batteries it types as “Other” in its register (Montalto, Pietrafitta, Larino, Rossano, Quartucciu) never do, and on 18 July the six accounted for about 80% of what the country’s storage line sent out. Each row is one battery on the same scale, sending out above its line and taking in below it. The dotted lines mark the unit’s rated power from Terna’s register of units.

Every figure is Terna’s, published on the ENTSO-E Transparency Platform under Regulation (EU) 543/2013: actual load and actual generation per production type by bidding zone every quarter hour, physical flows between zones and across borders, and, months behind, actual generation per unit for units of 100 MW or more. Terna reports a zone’s batteries as a production type of their own, so the fleet needs no estimate here. Terna’s newest quarter hour can arrive part filled, so the page reads the newest quarter hour every zone has reported in full. Italy publishes no live frequency. Nothing on this page is modelled; where a reading is missing the panel says which. The batteries by name