Vitreous LabsEnergy transparency
Poland · running and being built

315 MW of batteries run commercially in Poland, 273 MW more is switched on, and 2.1 GW is being built

315 MWRunning · 13 batteries
273 MWSwitched on · 14 batteries
2,149 MWBeing built · 12 batteries
971 MWFinanced, not started · 20 batteries

59 batteries of 1 MW and more, each with its status on 20 October 2026 and the dated source for it. 2,034 MWh is running or switched on; 8,199 MWh is being built.

No Polish body lists the batteries that are running, and none lists those being built. This register does, one battery at a time: who owns it, where it is, which grid it joins and where, its power and energy, who supplied and built it, its capacity contract, grant, trader and lenders, and every date from the connection agreement to commercial operation. It starts from the storage registers Tauron and Enea keep under the Energy Law and the four connection lists, joins URE’s capacity results unit by unit, and adds what owners, lenders, suppliers and the trade press have published. Every fact carries its link. The whole register as a CSV.

Of the capacity batteries owe from January 2028, 65% is running or being built and 29% has only a building permit behind it; from 2029, 16% is running or being built

A capacity contract is a promise to be available from 1 January of its first delivery year, with penalties for a unit that is not. Each bar is the obligation batteries won for that year, split by the furthest step the battery behind it has visibly reached: running, being built, financed, or a building permit issued to the contract holder and nothing since. For 2029, 7% is financed and not started, 25% has a permit only, and for 51% nothing has been found at all. A four-hour battery takes a year or more to build, and January 2028 is fourteen months away.

Running or switched onBeing builtFinanced, not startedBuilding permit onlyNothing found

From 2027165 MW owed10% nothing foundFrom 20281,734 MW owed29% permit only, 6% nothing foundFrom 20292,480 MW owed25% permit only, 51% nothing foundFrom 2030685 MW owed7% permit only, 87% nothing found
From 2027165 MW owed10% nothing foundFrom 20281,734 MW owed29% permit only, 6% nothing foundFrom 20292,480 MW owed25% permit only, 51% nothing foundFrom 2030685 MW owed7% permit only, 87% nothing found
First delivery yearUnitsObligation, MWRunning or onBeing builtFinancedPermit onlyNothing found
2027516541450016
2028331,7343667650501101
2029782,480193861866321,257
203057685740045592

MW of de-rated capacity obligation, URE’s final results; batteries counted unit by unit as on the capacity page. A unit counts as running, built or financed when the register matches it by its unit code; as permit only when its contract holder is named as investor in a battery building permit in GUNB’s register, matched by company name. A unit can be under way without a public report, so the hatched share is the most it could be, not the least.

The 28 units owing capacity in 2027 or 2028 that are not visibly being built, 619 MW of obligation
FromUnitContract holderObligation, MWFour-hour MWBuilding permit to the holder
2027JRM/777Battery ESS-1 sp. z o.o.9.29.68none found
2027JRM/774PKE Pomorze sp. z o.o.6.657none found
2028JRM/985Grand Solar 23 sp. z o.o131138Brzeziny, 2 April 2026; Brzeziny, 14 July 2026
2028JRM/982G Solar Energy 2 sp. z o.o.8489Klonówiec, 10 July 2026
2028JRM/983Grand Solar 23 sp. z o.o8489Brzeziny, 2 April 2026; Brzeziny, 14 July 2026
2028JRM/967Grand Solar 14 sp. z o.o.6164Ruda Śląska, 13 July 2026
2028JRM/405Encos sp. z o.o.4648Konin, 9 July 2024; Konin, 22 December 2025
2028JRM/1155Claritas Polska Ventures IV sp. z o.o.8.428.86Garwolin, 20 November 2025
2028JRM/1250RENEGIA BULLA sp. z o.o.7.47.79Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/1177FRV PSH 13 sp. z o.o.6.657Wrocław, 14 April 2026
2028JRM/1247RENEGIA BULLA sp. z o.o.6.66.95Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/1274MEWRO sp. z o.o.5.76Wrocław, 8 September 2026
2028JRM/931RENEGIA BULLA sp. z o.o.5.76Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/932RENEGIA BULLA sp. z o.o.5.76Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/1257FRV PSH 1 sp. z o.o.5.615.91Legnica, 29 January 2025; Legnica, 2 April 2026
2028JRM/966NRG 21 sp. z o.o.5.425.7Bąków, 29 October 2024; Strumień, 3 March 2026
2028JRM/1242FRV PSH 15 sp. z o.o.4.915.17Zamość, 30 September 2024; Zamość, 4 March 2026
2028JRM/968NRG 21 sp. z o.o.4.785.04Bąków, 29 October 2024; Strumień, 3 March 2026
2028JRM/922RENEGIA BULLA sp. z o.o.4.54.74Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/1171RENEGIA BULLA sp. z o.o.4.54.74Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/929RENEGIA BULLA sp. z o.o.4.44.63Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/1181NEO ENERGY PROJECT I sp. z o.o.3.84Kędzierzyn-Koźle, 9 May 2025; Kędzierzyn-Koźle, 28 July 2026
2028JRM/951RENEGIA BULLA sp. z o.o.3.84Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/930RENEGIA BULLA sp. z o.o.2.82.95Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/933RENEGIA BULLA sp. z o.o.2.52.63Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/946RENEGIA BULLA sp. z o.o.1.92Skarbimierz-Osiedle, 30 December 2024; Opole, 31 March 2025
2028JRM/1148GREENVOLT POWER TRADING sp. z o.o.95100none found
2028JRM/1190FRV PSH 11 sp. z o.o.6.316.64none found

The two owing from 1 January 2027, Battery ESS-1 and PKE Pomorze, are the ones to check first: their delivery year starts in ten weeks, and no permit in either name has been found.

If every owner’s date holds, Poland will have about 2.0 GW of batteries by the end of 2027 and 3.5 GW by the end of 2028

Each battery by the year its owner or the press says it will start commercial operation, split by its status today. A date said by an owner is a plan; several here have slipped already, and the ones only financed are the least certain. A date given as the turn of two years is counted in the later one.

Running or switched onBeing builtFinanced, not started

Now588 MW · 27Turośń Kościelna, EłkRest of 2026154 MW · 2Jedwabno, Puławy20271,234 MW · 12Siedlce, Żarnowiec20281,530 MW · 13Gryfino, DzięgielewoNo date given202 MW · 5Zwartowo III PV and battery, CLIP logistics centre near Poznań
Now588 MW · 27Turośń Kościelna, EłkRest of 2026154 MW · 2Jedwabno, Puławy20271,234 MW · 12Siedlce, Żarnowiec20281,530 MW · 13Gryfino, DzięgielewoNo date given202 MW · 5Zwartowo III PV and battery, CLIP logistics centre near Poznań

MW of battery power, and the number of batteries, by the year in each row’s commercial operation column, as worded in the table below. The two largest batteries in each year are named.

Where they are

One circle per battery, sized by its power, at the land parcel of its building permit in GUNB’s register. 19 of 59 placed; the rest have no permit found in their owner’s name, or one whose land GUGiK could not place.

Siedlce, 600 MWDzięgielewo, 300 MWŻarnowiec, 262 MWTurośń Kościelna, 200 MWMieczysławów, 200 MWJedwabno, 150 MWKamionka, 100 MWLwówek Śląski, 80 MWZawiercie, 10 MWŁozienica, 9 MWCLIP logistics centre near Poznań, 8 MWPrzeworsk, 8 MWWrześnia, 5 MWTauron Przewóz, 4 MWCieszanowice, 3 MWBytnica, 3 MWKunice, 2 MWBydgoszcz tram-company, 1 MWGliwice, 1 MWBALTIC SEACZECHIASLOVAKIAUKRAINEBELARUSLITHUANIARUSSIAWarsawKrakówŁódźWrocławPoznańGdańskSzczecinBydgoszcz
running or switched onbeing builtfinanced, not startedTransmission lines, 220 kV and up, OpenStreetMap

Every battery, with everything found

Open a battery for all forty facts and the link for each. “Not found” means searched for and not published anywhere this register could read.

BatteryOwnerPlaceMWMWhStatusCommercial operationCapacity contract
Turośń KościelnaGreenvolt PowerTurośń Kościelna, podlaskie200800RunningJul 2026JRM/1146 from 2028
Stary GrodkówEDF power solutionsSkoroszyce, opolskie50120RunningMay 2026JRM/885 from 2028
Nowe Czarnowo IEnergix GroupGryfino, zachodniopomorskie2456Running·JRM/1630 from 2029
ŁozienicaNGENGoleniów, zachodniopomorskie9.419Running3 Apr 2026·
Bystra hybridEnergapomorskie627RunningApr 2021JRM/747 from 2027
Garbce tractionPGE Energetyka Kolejowadolnośląskie5.51.2Running2021·
HerbyR.PowerHerby, śląskie510Runningfrom 28 Jul 2026JRM/1253 from 2029
Tauron PrzewózTauron Polska EnergiaKraków, małopolskie416RunningFeb 2026JRM/1404 from 2029
Tauron DąbieTauron Polska EnergiaKraków, małopolskie416RunningFeb 2026JRM/1405 from 2029
CieszanowiceTauronKamiennik (from the permit’s parcel)3.330.77Running2022·
RzepedźPGEpodkarpackie2.14.2RunningDec 2020·
CzernikowoEnergaCzernikowo, kujawsko-pomorskie12RunningSep 2022·
Nehrybka hybridR.Powerpodkarpackie12Running··
EłkGreenvolt PowerEłk, warmińsko-mazurskie200800Switched onexpected Q4 2026JRM/1157 from 2028
Nowe Czarnowo IIEnergix GroupGryfino, zachodniopomorskie2571Switched on··
Zawiercienot foundZawiercie, śląskie9.8220Switched on·JRM/1153 from 2028
Tauron ProszówekTauron Polska EnergiaGrębocice, dolnośląskie9.520Switched onplanned Q3 2026JRM/2150
Tauron Kuźnia RaciborskaTauron Polska EnergiaKuźnia Raciborska, śląskie6.928Switched onplanned Q3 2026JRM/1428 from 2029
Stawiszyn hybrid PV and batteryTK Powerwielkopolskie5.04·Switched on··
WrześniaR.PowerWrześnia, wielkopolskie5.015.01Switched on··
BytnicaWB EnergyBytnica, lubuskie3.08·Switched on··
OpoleRenegiaOpole, opolskie2.044.07Switched on··
KuniceSolar TechnicsKunice, dolnośląskie2.034.06Switched on··
Bydgoszcz tram-companyMiejskie Zakłady Komunikacyjne w BydgoszczyBydgoszcz, kujawsko-pomorskie1.24.18Switched on··
Goczałkowice-ZdrójJAK Szkło ŻogałaGoczałkowice-Zdrój, śląskie12Switched on··
GliwiceŚląskie Centrum Logistyki S.A.Gliwice, śląskie12.12Switched on··
Ceków hybrid PV and batteryDomagała Nieruchomościwielkopolskie1·Switched on··
SiedlceGreenvolt PowerZbuczyn (from the permit’s parcel), mazowieckie6002,400Being builttargeted end-2027JRM/1154 from 2028
DzięgielewoR.PowerStara Biała (from the permit’s parcel), mazowieckie3001,200Being builtturn of 2027/2028JRM/2407 from 2030
ŻarnowiecPGE Polska Grupa EnergetycznaKrokowa (Kartoszyno, from PSE row name; confirm), pomorskie262981Being builtplanned Q2 2027JRM/602 from 2029
Gdańsk IIR.PowerGdańsk, pomorskie2501,000Being builtturn of 2027/2028JRM/1513 from 2029
MieczysławówNorthland PowerŚlesin (from the permit’s parcel), wielkopolskie200800Being built2028JRM/1150 from 2028
JedwabnoR.PowerLubicz, kujawsko-pomorskie150300Being builtgrid connection planned Dec 2026JRM/1255 from 2029
TrzebiniaDRI; Actis to acquire on completionTrzebinia (name) or Chrzanów (Columbus 2024 article): see disagreements, małopolskie133622Being builtplanned early 2027JRM/730 from 2027
KamionkaNorthland Powerwielkopolskie100400Being built2028JRM/1149 from 2028
Lwówek ŚląskiGreen Capital S.A. and Prime Capital AG, joint ventureLwówek Śląski, dolnośląskie80320Being builtplanned Q3 2027JRM/1133 from 2029
Osiek JasielskiOX2Osiek Jasielski, podkarpackie50120Being built2027JRM/758 from 2027
BydgoszczTavionBydgoszcz, kujawsko-pomorskie2040Being builtgrid connection expected 2027·
PuławyRelyAssetsPuławy, lubelskie416Being builtplanned Sept 2026·
GryfinoPGE Polska Grupa EnergetycznaGryfino, zachodniopomorskie400800Financed, not startedplanned end-2028JRM/1165 from 2029
Zwartowo III PV and batteryRespect EnergyChoczewo (Zwartowo village; confirm), pomorskie184·Financed, not started··
Tauron LaryszówTauron Polska Energiaśląskie84358Financed, not startedplanned Q4 2028JRM/1413 from 2029
Tauron hybrid OgrodzieniecTauron Polska EnergiaOgrodzieniec, śląskie55237Financed, not startedplanned Q3 2028·
Tauron BałkówTauron Polska Energiaświętokrzyskie54242Financed, not startedplanned Q3 2027·
Tauron Dąbrowa ŚrodkowaTauron Polska Energiadolnośląskie45192Financed, not startedplanned Q2 2028·
Tauron TwardogóraTauron Polska EnergiaTwardogóra, dolnośląskie42179Financed, not startedplanned Q4 2028·
Tauron hybrid Stare Bogaczowice ITauron Polska EnergiaStare Bogaczowice, dolnośląskie30134Financed, not startedplanned Q3 2028·
Tauron BytomTauron Polska EnergiaBytom, śląskie1877Financed, not startedplanned Q4 2028JRM/1415 from 2029
TrześńNot confirmedpodkarpackie1665Financed, not startedplanned Q1 2027·
CLIP logistics centre near PoznańGrupa CLIPSwarzędz (from the permit’s parcel), wielkopolskie820Financed, not started··
PrzeworskLC EnergiaPrzeworsk, podkarpackie816Financed, not startedplanned turn of Q1/Q2 2027·
Tauron Radlna TarnowiecTauron Polska Energiamałopolskie6·Financed, not startedplanned Q2 2027JRM/1398 from 2029
WarzyceBESS-Grouppodkarpackie510Financed, not started··
NiegłowiceBESS-Grouppodkarpackie510Financed, not started··
Krotoszyn PV-coupledNot confirmedKrotoszyn, wielkopolskie525Financed, not startedplanned Q1 2027·
Tauron BaranowiceTauron Polska Energiaśląskie3.9·Financed, not startedplanned Q4 2028·
Tauron PilchowiceTauron Polska Energiadolnośląskie2·Financed, not startedplanned Q2 2028JRM/1403 from 2029
LubońTavionLuboń, wielkopolskie··Financed, not startedgrid connection expected 2027·
Third Tavion parkTavion···Financed, not started··

Running

Turośń Kościelna BESS · Running · 200 MW

Who

Owner
Greenvolt Power (Greenvolt Group, owned by KKR)
Project company
Magazyn EE Turośń Kościelna sp. z o.o. (KRS/NIP not found); capacity contract held by GREENVOLT POWER ADVISORY sp. z o.o., NIP 5214026608
Developer
Greenvolt Power
Also called
MEE Turośń Kościelna (PSE queue and capacity-market unit name); Magazyn Energii Elektrycznej Turośń Kościelna

Where

Gmina
Turośń Kościelna
Powiat
białostocki
Voivodeship
podlaskie
Coordinates
53.03204, 23.04435 (the land parcel of building permit ST-PD-BI/WNIOSEK/4642/2023 in GUNB’s register, placed by GUGiK)
Grid operator
PSE (transmission; 110 kV side of the Narew substation)
Connection, kV
110
Connection point
Narew (PSE)

What

Power, MW
200
Energy, MWh
800
Hours at full power
4.00
Kind
standalone, front-of-meter, transmission-connected
Cells, integrator and builder
BYD Energy Storage, 196 LFP enclosures; 49 container transformer stations; general contractor P&Q

Money

Capacity unit
JRM/1146
Capacity obligation, MW
170
Contract years
17
First delivery year
2028
Four-hour equivalent, MW
178.9
Other capacity contracts
2027 additional (quarterly) auctions: 180.5 MW in each of Q1-Q4 2027
Grant
€43.25m (189,283,710 zł). NFOŚiGW Modernisation Fund storage call (FM): grant recommended on the ranking list of 10 Dec 2025 (total cost 495,973,317 zł); signing of the agreement not confirmed in sources read
Trader, optimiser or toll
Statkraft 10-year tolling agreement for Turośń and Ełk (400 MW), announced 29 Sep 2026; Entrix optimisation deal (exclusive, Sept 2025) continues through Entrix cooperation with Statkraft
Financing
UniCredit: €153m bridge facility plus €65m guarantee line, shared with Ełk (Aug 2026). EBRD project 55427: up to €60m senior loan for Turośń and Ełk, approval date 17 Jun 2026 (signing not confirmed). IFC project 50763: up to €75m own account plus €80m parallel loans, pending approval as of Dec 2025

When

Connection agreement signed
2021-11-03
Connection date in the agreement
2026-07-30
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2026-07 (inaugurated 2026-07-30)

Evidence

Why this status
Inaugurated 30 Jul 2026 (Greenvolt press release; energy-storage.news 31 Jul 2026). Energy-storage.news (24 Sep and 5 Oct 2026) says it entered commercial operation in July 2026.
Its row in the connection lists
PSE art. 7 ust. 8l list (31 Aug 2026): "MEE Turośń Kościelna", applicant Magazyn EE Turośń Kościelna sp. z o.o., Narew 110 kV, 294 MW (charge 294 MW), agreement 2021-11-03, start of delivery 2026-07-30. Matched by name and project company.
How the contract was matched
By unit name "MEE Turośń Kościelna" in URE final list, 2028 main auction.
Where sources disagree
PSE queue row is for 294 MW against 200 MW built. The PSE list of 31 Aug 2026 still shows the agreement in force, not "connected", although its delivery start date (30 Jul 2026) has passed. IFC had planned construction completion for June 2026.
Still missing
Coordinates (OSM or Geoportal parcel search). KRS and NIP of the project company (KRS search by name). Energisation date and PSE balancing qualification date (Greenvolt or PSE). Construction start date (Greenvolt press archive). Whether the NFOŚiGW grant agreement was signed (NFOŚiGW list of signed agreements). Whether the EBRD and IFC loans were signed (EBRD PSD status, IFC disclosure page).

Sources. status (energy-storage.news); cod (energy-storage.news); cm (power.greenvolt.com); financing (gramwzielone.pl); toll (energy-storage.news); ebrd (ebrd.com); powiat (disclosures.ifc.org); grant (gov.pl); queue (pse.pl); cm (ure.gov.pl); cm q2027 (ure.gov.pl); substation (gramwzielone.pl); site (wyszukiwarka.gunb.gov.pl)

Stary Grodków BESS · Running · 50 MW

Who

Owner
EDF power solutions (EDF group)
Project company
ME Stary Grodków sp. z o.o., KRS 0000959915, NIP 5223220959 (Tauron register); capacity contract supplier in URE list: Respect Energy S.A., NIP 8762459238
Developer
EDF power solutions Polska
Also called
Magazyn Energii Stary Grodków (capacity-market unit name); "Stare Grodkowo" in the 20 Oct 2026 Respect Energy article

Where

Gmina
Skoroszyce
Powiat
nyski
Voivodeship
opolskie
Coordinates
not found
Grid operator
Tauron Dystrybucja
Connection, kV
110
Connection point
GPZ Grodków (Tauron queue code GDK3)

What

Power, MW
50
Energy, MWh
120
Hours at full power
2.40
Kind
standalone, front-of-meter, 110 kV distribution
Cells, integrator and builder
Sungrow: 24 PowerTitan 2.0 units and 12 MVS5140 medium-voltage stations; EPC not named

Money

Capacity unit
JRM/885
Capacity obligation, MW
22.56
Contract years
17
First delivery year
2028
Four-hour equivalent, MW
23.7
Other capacity contracts
2027 additional auctions: 23.906 MW in Q1 and Q4 2027
Grant
not found
Trader, optimiser or toll
Respect Energy: commercial balancing, auxiliary supply, balancing service provider, day-ahead/intraday/balancing optimisation and capacity-market compliance (agreement reported 20 Oct 2026; length not stated)
Financing
not found

When

Connection agreement signed
2023-11-24
Connection date in the agreement
2026-05-13
Building started
2025-06 (construction announced 4 Jun 2025)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2026-05 (register: storage activity from 2026-05-13)

Evidence

Why this status
Gramwzielone 20 May 2026: the plant has started operating. Tauron register gives storage activity from 13 May 2026; Tauron queue shows the object connected.
Its row in the connection lists
Tauron queue (30 Jun 2026): station GDK3, 110 kV, storage 50 MW out / 50 MW in, 60.2 MW, status "connected", agreement 2023-11-24, start 2026-05-13. Matched by station code, size and register date (applicant is anonymised as "Osoba prawna").
How the contract was matched
By unit name "Magazyn Energii Stary Grodków" in URE 2028 main list.
Where sources disagree
Size: 50 MW / 120 MWh (EDF, gramwzielone, register 120.36 MWh) vs 50 MW / 100 MWh and two-hour duration (gramwzielone 20 Oct 2026). Register installed power 60.192 MW with 50 MW discharge; ESS News says 60 MW installed, 50 MW grid connection. The URE list names Respect Energy, not an EDF company, as capacity supplier.
Still missing
Coordinates. EPC contractor (EDF or Sungrow press). Energisation date (planned Oct-Nov 2025 per June 2025 article; actual not found). Financing (EDF balance sheet assumed, not confirmed). PSE balancing qualification (Respect Energy). Which MWh figure is right: 100 or 120 (ask EDF; register says 120.36).

Sources. status (gramwzielone.pl); register (tauron-dystrybucja.pl); queue (tauron-dystrybucja.pl); equipment (ess-news.com); construction (gramwzielone.pl); optimiser (gramwzielone.pl); completion (energy-storage.news); cm (ure.gov.pl); cm q2027 (ure.gov.pl)

Nowe Czarnowo I BESS · Running · 24 MW

Who

Owner
Energix Group (Energix Polska)
Project company
Capacity contract holder: ENERGIX POLSKA sp. z o.o. BESS NOWE CZARNOWO I MANAGEMENT sp. j., NIP 5273070108
Developer
Energix Polska
Also called
ME Nowe Czarnowo I S059 (capacity-market unit); EP PL BESS Nowe Czarnowo I

Where

Gmina
Gryfino
Powiat
gryfiński
Voivodeship
zachodniopomorskie
Coordinates
not found
Grid operator
Not stated (near PSE Krajnik substation; connection costs to PSE grid mentioned by Axpo)
Connection, kV
not found
Connection point
near Krajnik (PSE)

What

Power, MW
24
Energy, MWh
56
Hours at full power
2.33
Kind
standalone, front-of-meter, co-located with Energix wind and PV at Krajnik
Cells, integrator and builder
System integrator Diotech (Estonia); SMA and LG Energy Solution technology; Energix built it

Money

Capacity unit
JRM/1630
Capacity obligation, MW
8.52
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
13.9
Other capacity contracts
2026 additional auctions: 13.359 MW in Q1 and Q4 2026; 2027 additional: 13.205 MW in Q1 2027
Grant
None (Nowe Czarnowo II grant application not recommended)
Trader, optimiser or toll
Axpo Polska: full optimisation, wholesale and balancing integration, capacity obligation; profit share (length not stated)
Financing
Santander Bank Polska (announced June 2025, per energy-storage.news)

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
2025-10 (commissioning began late Oct 2025)
Qualified for PSE’s balancing
2026-09 (PSE confirmed qualification and start of balancing services; gramwzielone 9 Sep 2026)
Commercial operation
not found

Evidence

Why this status
Gramwzielone 12 Jan 2026: operating, first URE storage concession. Gramwzielone 9 Sep 2026: first Polish battery to complete PSE qualification and provide balancing services.
Its row in the connection lists
No row found in the PSE list of 31 Aug 2026 or the distribution queues by name; probably connected through Energix wind-farm infrastructure (unconfirmed).
How the contract was matched
By unit name "ME Nowe Czarnowo I S059" and supplier name (URE 2029 main list).
Where sources disagree
24 MW / 56 MWh (Energix, Axpo, gramwzielone) vs 28 MW (Modo, Apr 2026).
Still missing
Connection voltage, substation and grid operator (Energix; PSE register of storage does not list it). Project company KRS. Exact commissioning/COD date and URE concession date (URE concession register). Coordinates. Axpo contract length.

Sources. status (gramwzielone.pl); commissioning (gramwzielone.pl); concession (gramwzielone.pl); integrator (baltictimes.com); optimiser (axpo.com); financing (energy-storage.news); cm (ure.gov.pl); cm q2026 (ure.gov.pl); cm q2027 (ure.gov.pl); grant not recommended (gov.pl)

Łozienica BESS (Project Vistula) · Running · 9.4 MW

Who

Owner
NGEN (NGEN Energetske rešitve d.o.o., Slovenia)
Project company
NGEN 1 sp. z o.o., KRS 0001127239, NIP 7011222707
Developer
NGEN
Also called
Vistula; "Łozienica E32" in NFOŚiGW application

Where

Gmina
Goleniów
Powiat
goleniowski
Voivodeship
zachodniopomorskie
Coordinates
53.52753, 14.79663 (the land parcel of building permit ST-ZP-GO/WNIOSEK/2339/2025 in GUNB’s register, placed by GUGiK)
Grid operator
Enea Operator
Connection, kV
15
Connection point
GPZ Łozienica, ZKP-SN Łozienica 6 no. 782892

What

Power, MW
9.4
Energy, MWh
18.8
Hours at full power
2.00
Kind
standalone, front-of-meter, medium voltage
Cells, integrator and builder
Tesla, five Megapack 2XL (LFP); EPC not named

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
NFOŚiGW FM application not recommended
Trader, optimiser or toll
Merchant; NGEN in-house trading (day-ahead and intraday arbitrage first, balancing later)
Financing
EBRD project 55451: up to €70m for five NGEN BESS incl. two in Poland, approved May 2026 (not stated that Łozienica is one of them)

When

Connection agreement signed
2024-07-11
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2026-04-03 (Modo: commissioned 3 Apr 2026); register: storage activity from 2026-02-10

Evidence

Why this status
Gramwzielone 8 Apr 2026 and Balkan Green Energy News 3 Apr 2026: commissioned; Enea register entry 24 Mar 2026.
Its row in the connection lists
Enea queue: no. 25821/2023, NGEN 1 sp. z o.o., Łozienica SN field, agreement 2024-07-11 (MW parsed as 0.221, which looks like a parsing error). Matched by applicant name.
How the contract was matched
not found
Where sources disagree
9.4 MW / 18.8 MWh (NGEN, press) vs 9.636 MW / 19.272 MWh (Enea register). Modo counts 9.4 MW.
Still missing
Coordinates. EPC. Whether it is in the EBRD-financed portfolio (EBRD PSD 55451 or NGEN). Balancing qualification date (NGEN/PSE). Check the Enea queue PDF row for the true MW.

Sources. register (operator.enea.pl); equipment (gramwzielone.pl); commissioned (balkangreenenergynews.com); ebrd (ebrd.com); ebrd approved (gramwzielone.pl); modo date (modoenergy.com); queue (operator.enea.pl); grant not recommended (gov.pl); site (wyszukiwarka.gunb.gov.pl)

Bystra hybrid BESS (Energa) · Running · 6 MW

Who

Owner
Energa (Orlen group)
Project company
Energa OZE (formerly Energa Wytwarzanie); capacity contract holder ENERGA WYTWARZANIE S.A., NIP 5932372895
Developer
Energa with PSE and Hitachi (NEDO)
Also called
Magazyn energii Bystra; Polish-Japanese NEDO project; capacity unit JRM/747

Where

Gmina
not found
Powiat
not found
Voivodeship
pomorskie
Coordinates
not found
Grid operator
Energa-Operator (assumed; at the Bystra wind farm)
Connection, kV
not found
Connection point
Bystra wind farm, near Pruszcz Gdański

What

Power, MW
6
Energy, MWh
27
Hours at full power
4.50
Kind
co-located with a wind farm (hybrid)
Cells, integrator and builder
Hybrid: 1 MW lithium-ion (0.47 MWh) and 5 MW lead-acid (26.9 MWh); Japanese partners (Hitachi per Forsal); building contractor PBI Niewczas

Money

Capacity unit
JRM/747
Capacity obligation, MW
3.79
Contract years
7
First delivery year
2027
Four-hour equivalent, MW
4.0
Other capacity contracts
2026 additional auction: 3.834 MW in Q4 2026
Grant
NEDO (Japan) co-funded pilot; amount not found
Trader, optimiser or toll
Energa
Financing
Energa / NEDO

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
2018-11 (building contract signed)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2021-04 (handed over for operation early April 2021)

Evidence

Why this status
Forsal/WysokieNapiecie 6 Aug 2021: handed over for operation in early April 2021 after tests. Holds a Q4 2026 capacity contract as an existing unit.
Its row in the connection lists
Not matched.
How the contract was matched
Gramwzielone 22 Dec 2022 says Energa's 2027 capacity unit is the hybrid store next to the Bystra wind farm; JRM/747 is Energa Wytwarzanie's only storage unit in that auction.
Where sources disagree
Gramwzielone (Dec 2022) said it would be connected to the national system after the pilot phase, so its grid status in 2021-2022 is unclear.
Still missing
Gmina and powiat (Bystra village, likely gmina Pruszcz Gdański: confirm). Connection voltage and point (Energa-Operator register, not captured). Current operating status (Energa).

Sources. status (forsal.pl); cm (gramwzielone.pl); construction (gramwzielone.pl); cm (ure.gov.pl); cm q2026 (ure.gov.pl)

Garbce traction BESS (PKP Energetyka) · Running · 5.5 MW

Who

Owner
PGE Energetyka Kolejowa (formerly PKP Energetyka)
Project company
PKP Energetyka S.A. (now PGE Energetyka Kolejowa S.A.)
Developer
PKP Energetyka with University of Zielona Góra, My-Soft, Impact Clean Power Technology, Elester-PKP
Also called
Mobi-Trak; traction energy storage at Garbce traction substation

Where

Gmina
not found
Powiat
not found
Voivodeship
dolnośląskie
Coordinates
not found
Grid operator
PKP Energetyka (railway traction network)
Connection, kV
3 (DC traction, assumed)
Connection point
Garbce traction substation, about 50 km from Wrocław

What

Power, MW
5.5
Energy, MWh
1.2
Hours at full power
0.22
Kind
traction (railway DC network), not public AC grid
Cells, integrator and builder
Four containers, 4,240 Li-ion cells; My-Soft (Mobi-Trak), Impact Clean Power Technology, DC/DC converter

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
EU co-funding 45% of €4.4m (Railway Gazette)
Trader, optimiser or toll
Railway traction supply
Financing
EU grant plus PKP Energetyka

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2021 (official opening reported 6 Jul 2021)

Evidence

Why this status
Railway Gazette 6 Jul 2021: built, with photo of the official opening.
Its row in the connection lists
Not applicable.
How the contract was matched
not found
Where sources disagree
Energy: 1.2 MWh usable (Railway Gazette) vs 1.88 MWh total / 1.5 MWh usable (gramwzielone 15 Jun 2021). Power 5.5 MW (Railway Gazette) vs 5 MW (Railtech).
Still missing
Whether it counts as grid-scale for Vitreous (traction DC). Gmina. Current status (PGE Energetyka Kolejowa).

Sources. status (railwaygazette.com); mwh (gramwzielone.pl); mw (railtech.com)

Herby BESS · Running · 5 MW

Who

Owner
R.Power
Project company
Elektrownia PV 130 sp. z o.o., KRS 0001114935, NIP 5214076606
Developer
R.Power
Also called
Magazyn energii Herby (capacity-market unit); Magazyn Herby BESS

Where

Gmina
Herby
Powiat
lubliniecki
Voivodeship
śląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja
Connection, kV
15
Connection point
15 kV cable to client station CZZ35264, connected at cable joint ZK-SN CZZ30612 (register)

What

Power, MW
5
Energy, MWh
10
Hours at full power
2.00
Kind
standalone, front-of-meter, medium voltage
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1253
Capacity obligation, MW
1.532
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
2.5
Other capacity contracts
T-1 2027 supplementary auction (Sept 2026): R.Power won 75.994 MW for Jedwabno and Herby together (split not published)
Grant
€0.35m (1,545,700.37 zł). NFOŚiGW FM: grant 1,545,700.37 zł plus loan 1,631,862.98 zł recommended (ranking 10 Dec 2025)
Trader, optimiser or toll
Entrix optimisation and trading on all relevant markets (term not stated)
Financing
NFOŚiGW grant and loan (recommended); R.Power group funds

When

Connection agreement signed
2024-08-14 (inferred Tauron match)
Connection date in the agreement
not found
Building started
2025-Q4
Switched on
not found
Qualified for PSE’s balancing
qualification in progress (Oct 2026)
Commercial operation
register: storage activity from 2026-07-28; operating per 20 Oct 2026 article

Evidence

Why this status
Gramwzielone 20 Oct 2026: connected to the grid and started operating; balancing qualification in progress. Tauron register entry 10 Jul 2026.
Its row in the connection lists
Possible Tauron queue row: station HER3, SN, storage 5 MW out / 5 MW in, agreement 2024-08-14 (inferred from station code and size; applicant anonymised).
How the contract was matched
By unit name "Magazyn energii Herby" and NIP 5214076606 (same as register owner).
Where sources disagree
Register: 5.04 MW / 10.03 MWh vs 5 MW / 10 MWh. Register start date (28 Jul) is after first-entry date (10 Jul).
Still missing
Supplier and EPC (R.Power). Exact COD. Confirm Tauron queue row. Coordinates.

Sources. status (gramwzielone.pl); register (tauron-dystrybucja.pl); cm (ure.gov.pl); grant (gov.pl); queue (tauron-dystrybucja.pl); t1 2027 (biznesradar.pl)

Tauron BESS Przewóz (Kraków) · Running · 4 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON Ekoenergia sp. z o.o., KRS 0000195546, NIP 6112502075 (register owner); capacity contract holder TAURON BME4 sp. z o.o., NIP 6343042745
Developer
Tauron (in-house)
Also called
BME Przewóz; ME Przewóz (capacity-market unit); register site "ST krp33900 Rybitwy"

Where

Gmina
Kraków
Powiat
Kraków
Voivodeship
małopolskie
Coordinates
50.04111, 20.09744 (the land parcel of building permit ST-MA-KR/WNIOSEK/14947/2025 in GUNB’s register, placed by GUGiK)
Grid operator
Tauron Dystrybucja
Connection, kV
not found
Connection point
ST krp33900 Rybitwy

What

Power, MW
4
Energy, MWh
16
Hours at full power
4.00
Kind
standalone, front-of-meter, on Tauron hydro-plant land
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1404
Capacity obligation, MW
2.452
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
4.0
Other capacity contracts
Tauron won 14.155 MW of storage obligation in the T-1 2027 supplementary auction (units not named)
Grant
NFOŚiGW FM application not recommended (gramwzielone, parkiet)
Trader, optimiser or toll
Tauron group
Financing
Tauron balance sheet (assumed; not stated)

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2026-02 (handed over Feb 2026); register: storage activity from 2025-11-07

Evidence

Why this status
Tauron H1 2026 report via gramwzielone 24 Sep 2026: Dąbie and Przewóz operating, handed over in February 2026. Tauron register entry 13 Nov 2025.
Its row in the connection lists
Not matched (Tauron queue is anonymised; no row with this size found by station code).
How the contract was matched
By unit name "ME Przewóz" and Tauron SPV; 2.452 / 0.613 = 4.0 MW four-hour equivalent, matching 4 MW / 16 MWh.
Where sources disagree
Register: 4.41 MW installed / 4.0 MW discharge / 17.556 MWh, vs 4 MW / 16 MWh in Tauron statements. Register owner is TAURON Ekoenergia, capacity contract holder TAURON BME4. Register lists the site as Rybitwy; Tauron calls it Przewóz (adjacent Kraków districts); matched by Tauron press saying both Kraków units sit on hydro-plant land. Building permit for "BESS Przewóz" (GUNB ST-MA-KR/WNIOSEK/14947/2025) names TAURON BME4 sp. z o.o. as investor; the register lists the battery under TAURON Ekoenergia.
Still missing
Connection voltage (register point only). Equipment supplier and EPC (Tauron tender notices). Coordinates. Confirm Rybitwy = Przewóz with Tauron.

Sources. register (tauron-dystrybucja.pl); status (gramwzielone.pl); mwh (gramwzielone.pl); cm (ure.gov.pl); no grant (parkiet.com); site (wyszukiwarka.gunb.gov.pl)

Tauron BESS Dąbie (Kraków) · Running · 4 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON Ekoenergia sp. z o.o., KRS 0000195546, NIP 6112502075 (register owner); capacity contract holder TAURON BME4 sp. z o.o., NIP 6343042745
Developer
Tauron (in-house)
Also called
BME Dąbie; ME Dąbie (capacity-market unit); register site "ST krp3695 Dąbie"

Where

Gmina
Kraków
Powiat
Kraków
Voivodeship
małopolskie
Coordinates
not found
Grid operator
Tauron Dystrybucja
Connection, kV
not found
Connection point
ST krp3695 Dąbie

What

Power, MW
4
Energy, MWh
16
Hours at full power
4.00
Kind
standalone, front-of-meter, on Tauron hydro-plant land
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1405
Capacity obligation, MW
2.452
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
4.0
Other capacity contracts
Tauron T-1 2027 supplementary auction storage obligation 14.155 MW (units not named)
Grant
NFOŚiGW FM application not recommended
Trader, optimiser or toll
Tauron group
Financing
Tauron balance sheet (assumed; not stated)

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2026-02 (handed over Feb 2026); register: storage activity from 2025-11-25

Evidence

Why this status
Tauron H1 2026 report via gramwzielone 24 Sep 2026: operating, handed over Feb 2026. Tauron register entry 27 Nov 2025.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
By unit name "ME Dąbie" and Tauron SPV; four-hour equivalent 4.0 MW.
Where sources disagree
Register: 4.41 MW installed / 4.0 MW discharge / 17.556 MWh vs 4 MW / 16 MWh (Tauron).
Still missing
Connection voltage. Supplier/EPC. Coordinates.

Sources. register (tauron-dystrybucja.pl); status (gramwzielone.pl); mwh (gramwzielone.pl); cm (ure.gov.pl)

Cieszanowice BESS (Tauron Dystrybucja) · Running · 3.33 MW

Who

Owner
Tauron
Project company
TAURON Dystrybucja S.A.
Developer
Tauron Dystrybucja
Also called
Szklary 159A storage; POIiŚ demonstration project

Where

Gmina
Kamiennik (from the permit’s parcel)
Powiat
nyski
Voivodeship
not found
Coordinates
50.58149, 17.17687 (the land parcel of building permit ST-OP-NY/WNIOSEK/8715/2021 in GUNB’s register, placed by GUGiK)
Grid operator
Tauron Dystrybucja
Connection, kV
15
Connection point
110/15 kV station Cieszanowice, 15 kV switchgear field 13 (48-256 Szklary 159A)

What

Power, MW
3.33
Energy, MWh
0.774
Hours at full power
0.23
Kind
DSO grid asset
Cells, integrator and builder
Lithium-titanate batteries; supplier not named

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
€1.79m (7,851,880.81 zł). EU POIiŚ 2014-2020 (measure 1.4): 7,851,880.81 zł, 82.83% of eligible costs, agreement 13 Jun 2018
Trader, optimiser or toll
DSO grid asset (Tauron says it meets the fully-integrated-network-element test)
Financing
EU grant plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2022 (year built or commissioned)

Evidence

Why this status
URE Informacja 6/2026 (30 Jan 2026) lists it as an existing storage facility subject to consultation, built/commissioned 2022; charge and discharge 2,000 kW.
Its row in the connection lists
Not applicable.
How the contract was matched
not found
Where sources disagree
Installed 3,330 kW but maximum charge/discharge 2,000 kW. Gramwzielone (11 Feb 2026) misprinted it as 33 MW.
Still missing
Gmina/powiat for Szklary (48-256 is the Głuchołazy/Nysa area, Opolskie: confirm). Supplier. Outcome of URE consultation (URE BIP).

Sources. all (ure.gov.pl); site (wyszukiwarka.gunb.gov.pl)

Rzepedź BESS (PGE) · Running · 2.1 MW

Who

Owner
PGE
Project company
PGE Dystrybucja / PGE Polska Grupa Energetyczna (project run jointly)
Developer
PGE
Also called
Magazyn energii Rzepedź

Where

Gmina
not found
Powiat
not found
Voivodeship
podkarpackie
Coordinates
not found
Grid operator
PGE Dystrybucja
Connection, kV
not found
Connection point
not found

What

Power, MW
2.1
Energy, MWh
4.2
Hours at full power
2.00
Kind
DSO grid asset
Cells, integrator and builder
Tesla Powerpack; contractor Griffin Group Energy

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
Grid support (DSO asset)
Financing
PGE

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2020-12 (launch reported 9 Dec 2020)

Evidence

Why this status
Gramwzielone and Forsal, 9 Dec 2020: PGE launched the storage. No later report of closure found.
Its row in the connection lists
PGE Dystrybucja queue and register not captured.
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Gmina (Rzepedź is in gmina Komańcza, powiat sanocki: confirm). Connection voltage. Whether still operating and whether URE treats it as a fully integrated grid element (PGE Dystrybucja register; URE decisions of 2023 on three PGE Dystrybucja units).

Sources. mw (gramwzielone.pl); forsal (forsal.pl)

Czernikowo BESS (Energa-Operator) · Running · 1 MW

Who

Owner
Energa (Orlen group)
Project company
Energa-Operator S.A.
Developer
Energa-Operator
Also called
Magazyn energii w Czernikowie; RS Czernikowo

Where

Gmina
Czernikowo
Powiat
toruński
Voivodeship
kujawsko-pomorskie
Coordinates
not found
Grid operator
Energa-Operator
Connection, kV
15
Connection point
RS Czernikowo (next to a 3.77 MW PV farm on 15 kV)

What

Power, MW
1
Energy, MWh
2
Hours at full power
2.00
Kind
DSO grid asset
Cells, integrator and builder
Lithium-ion; supplier not named

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
EU POIiŚ 2014-2020 Smart Grid project (85% co-financing of the wider project; storage share not given)
Trader, optimiser or toll
DSO grid asset; URE decision of 19 Dec 2025 recognised it as a fully integrated network element
Financing
EU grant plus Energa-Operator

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
2020-07 (construction start announced)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2022-09 (launch reported 30 Sep 2022)

Evidence

Why this status
Gramwzielone 30 Sep 2022: launched. URE Informacja 6/2026: URE decision of 19 Dec 2025 lets Energa-Operator keep and run it.
Its row in the connection lists
Not applicable.
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Supplier. Connection voltage of the storage itself (PV is 15 kV). Gmina inferred from place name: confirm.

Sources. mw (gramwzielone.pl); construction (money.pl); ure (ure.gov.pl)

Nehrybka hybrid BESS (R.Power) · Running · 1 MW

Who

Owner
R.Power
Project company
not found
Developer
R.Power
Also called
not found

Where

Gmina
not found
Powiat
przemyski
Voivodeship
podkarpackie
Coordinates
not found
Grid operator
PGE Dystrybucja (assumed: Podkarpacie)
Connection, kV
not found
Connection point
not found

What

Power, MW
1
Energy, MWh
2
Hours at full power
2.00
Kind
co-located with a PV farm (hybrid)
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
None (operating without public support)
Trader, optimiser or toll
Photon Energy: optimisation, balancing responsible party and balancing services (Aug 2025)
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Gramwzielone 18 Mar 2026: operating commercially, providing system services and arbitrage.
Its row in the connection lists
PGE Dystrybucja queue not captured.
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Project company, gmina, connection, COD (R.Power). Powiat inferred ("near Przemyśl"): confirm.

Sources. mw (gramwzielone.pl); optimiser (energy-storage.news)

Switched on

Ełk BESS (Nowa Wieś Ełcka) · Switched on · 200 MW

Who

Owner
Greenvolt Power (Greenvolt Group, owned by KKR)
Project company
Magazyn EE Ełk sp. z o.o. (KRS/NIP not found); capacity contract held by GREENVOLT POWER ADVISORY sp. z o.o., NIP 5214026608
Developer
Greenvolt Power
Also called
MEE Ełk (PSE queue and capacity-market unit); BESS Ełk; Nowa Wieś Ełcka

Where

Gmina
Ełk
Powiat
ełcki
Voivodeship
warmińsko-mazurskie
Coordinates
not found
Grid operator
PSE
Connection, kV
220 (temporary, via a 0.7 km line to an existing 220 kV line); planned 400 kV at Ełk Bis
Connection point
temporary tap on existing 220 kV line; later PSE Ełk Bis

What

Power, MW
200
Energy, MWh
800
Hours at full power
4.00
Kind
standalone, front-of-meter, transmission-connected
Cells, integrator and builder
BYD Energy Storage, 196 MC Cube-T units; general contractor P&Q

Money

Capacity unit
JRM/1157
Capacity obligation, MW
170
Contract years
17
First delivery year
2028
Four-hour equivalent, MW
178.9
Other capacity contracts
2027 additional auctions: 180.5 MW in each of Q1-Q4 2027
Grant
at most about €48.89m (214,000,000 zł). KPO "Systemy magazynowania energii" grant: Żarnowiec and Ełk together 691 m zł; Żarnowiec alone "over 477 m zł", so Ełk is at most about 214 m zł (derived by subtraction, not published)
Trader, optimiser or toll
Statkraft 10-year tolling agreement (with Turośń), announced 29 Sep 2026; Entrix optimisation (Sept 2025)
Financing
UniCredit €153m bridge plus €65m guarantee line (with Turośń, Aug 2026); EBRD project 55427 up to €60m (approval date 17 Jun 2026, signing not confirmed); IFC project 50763 (pending approval Dec 2025)

When

Connection agreement signed
2022-02-01
Connection date in the agreement
2030-02-28
Building started
2025-05 (road and substation works May-Sep 2025 per EBRD schedule)
Switched on
2026-06-16 (voltage applied; module energisation began)
Qualified for PSE’s balancing
not found
Commercial operation
expected Q4 2026

Evidence

Why this status
PSE chief executive, 16 Jun 2026 (gramwzielone 19 Jun 2026): voltage applied, energisation of modules begun. Energy-storage.news 5 Oct 2026: commercial operation targeted Q4 2026, not yet operational.
Its row in the connection lists
PSE list: "MEE Ełk", applicant Magazyn EE Ełk sp. z o.o., Ełk Bis 400 kV, 294 MW, agreement 2022-02-01, start of delivery 2030-02-28. Matched by name and company. The row is for the permanent 400 kV connection; the plant runs on a temporary 220 kV connection.
How the contract was matched
By unit name "MEE Ełk" (URE 2028 main list).
Where sources disagree
EBRD NTS: 200.6 MW and 842 MWh grid-side vs 200 MW / 800 MWh. EBRD planned commissioning for Sept 2026, IFC for April 2026. PSE queue gives 294 MW and 2030 for the permanent connection.
Still missing
Exact KPO grant for Ełk (NFOŚiGW KPO agreement list). KRS/NIP of SPV. Coordinates. Balancing qualification. COD (Greenvolt, expected Q4 2026).

Sources. energised (gramwzielone.pl); cod (energy-storage.news); ebrd nts (ebrd.com); ebrd psd (ebrd.com); ifc (disclosures.ifc.org); financing (gramwzielone.pl); kpo total (gramwzielone.pl); kpo zarnowiec (gramwzielone.pl); queue (pse.pl); cm (ure.gov.pl); cm q2027 (ure.gov.pl)

Nowe Czarnowo II BESS · Switched on · 25 MW

Who

Owner
Energix Group (Energix Polska)
Project company
not found
Developer
Energix Polska
Also called
Nowe Czarnowo 2

Where

Gmina
Gryfino
Powiat
gryfiński
Voivodeship
zachodniopomorskie
Coordinates
not found
Grid operator
not found
Connection, kV
not found
Connection point
near Krajnik (inferred from site name; unconfirmed)

What

Power, MW
25
Energy, MWh
71
Hours at full power
2.84
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
NFOŚiGW FM application (63,757,188 zł cost) not recommended
Trader, optimiser or toll
Axpo and Energix partners in qualification (gramwzielone 9 Sep 2026)
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
in PSE qualification (Sept 2026)
Commercial operation
not found

Evidence

Why this status
Gramwzielone 9 Sep 2026: Nowe Czarnowo II has entered PSE qualification, which requires an energised unit. Energix site: expected 2026.
Its row in the connection lists
No queue row found by name.
How the contract was matched
No capacity contract found.
Where sources disagree
25 MW / 71 MWh (gramwzielone) vs 52 MWh (Energix website, no MW).
Still missing
Owner company, connection point and voltage, energisation date, COD (Energix or Axpo). Which MWh figure is right. Coordinates.

Sources. status (gramwzielone.pl); energix (new.energix-group.com); grant (gov.pl)

Zawiercie BESS (BESS CM2) · Switched on · 9.82 MW

Who

Owner
not found
Project company
BESS CM2 sp. z o.o., KRS 0001053117, NIP 5223267719
Developer
not found
Also called
Magazyn Energii Zawiercie 1 (capacity-market unit)

Where

Gmina
Zawiercie
Powiat
zawierciański
Voivodeship
śląskie
Coordinates
50.49909, 19.42438 (the land parcel of building permit ST-SL-ZE/WNIOSEK/21396/2024 in GUNB’s register, placed by GUGiK)
Grid operator
Tauron Dystrybucja
Connection, kV
15
Connection point
GPZ Argentyna, 15 kV switchgear, field 14

What

Power, MW
9.823
Energy, MWh
19.6
Hours at full power
2.00
Kind
standalone, front-of-meter, medium voltage
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1153
Capacity obligation, MW
3.705
Contract years
17
First delivery year
2028
Four-hour equivalent, MW
3.9
Other capacity contracts
2027 additional auctions: 3.705 MW in Q1 and Q4 2027
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
2024-01-29 (inferred Tauron match)
Connection date in the agreement
not found
Building started
not found
Switched on
2026-09 (register entry 2026-09-03; start date blank)
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Tauron register entry 3 Sep 2026 (connected storage). No press report of operation.
Its row in the connection lists
Tauron queue: station ARG3, SN, storage 8.1 MW, agreement 2024-01-29 (inferred: station code ARG = Argentyna and 8.1 MW matches the register discharge 8.07 MW).
How the contract was matched
By NIP 5223267719 (same in register and URE list) and unit name.
Where sources disagree
Register: 9.823 MW installed, 8.07 MW discharge, 19.6 MWh.
Still missing
Owner group (KRS extract for BESS CM2 sp. z o.o.). Supplier, financing, optimiser, COD. Coordinates.

Sources. register (tauron-dystrybucja.pl); cm (ure.gov.pl); cm q2027 (ure.gov.pl); queue (tauron-dystrybucja.pl); site (wyszukiwarka.gunb.gov.pl)

Tauron BESS Proszówek · Switched on · 9.5 MW

Who

Owner
Tauron Polska Energia
Project company
FF Park PV sp. z o.o., KRS 0000838530, NIP 9252131338 (register owner, Tauron group PV-farm company)
Developer
Tauron (in-house)
Also called
BME Proszówek; register owner FF Park PV sp. z o.o. at Kalinówka

Where

Gmina
Grębocice
Powiat
polkowicki
Voivodeship
dolnośląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja
Connection, kV
110
Connection point
110 kV line field no. 9, 110/20/6 kV station Kalinówka

What

Power, MW
9.5
Energy, MWh
20.06
Hours at full power
2.11
Kind
co-located with Tauron PV farm Proszówek
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
Same NIP holds JRM/2150 (FF PARK PV 1, 7.364 MW, 2030, 17 yrs), but its four-hour equivalent (55 MW) does not fit this battery; probably another unit (Proszówek II, 47 MW?)
Grant
not found
Trader, optimiser or toll
Tauron group
Financing
Tauron; capex 12.4 m zł (H1 2026 report)

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
2026-07 (register: storage activity from 2026-07-09)
Qualified for PSE’s balancing
not found
Commercial operation
planned Q3 2026

Evidence

Why this status
Tauron register entry 26 Jun 2026, activity from 9 Jul 2026. Tauron H1 2026 report: 96% complete, completion Q3 2026.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
No confirmed match; see cm_other.
Where sources disagree
8 MW / 16 MWh (Tauron, Dec 2025) vs 9.5 MW (Tauron H1 2026) vs 10 MW installed / 8 MW discharge / 20.064 MWh (register). Match of register row "FF Park PV, Grębocice, Kalinówka" to Tauron's "BESS Proszówek (gmina Grębocice, on a PV farm)" is by gmina and timing, not by name.
Still missing
Confirm FF Park PV = Tauron Proszówek (Tauron). Final MW/MWh. COD. Supplier. Coordinates.

Sources. register (tauron-dystrybucja.pl); status (gramwzielone.pl); mw (gramwzielone.pl); cm (ure.gov.pl)

Tauron BESS Kuźnia Raciborska · Switched on · 6.9 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON BME9 sp. z o.o., KRS 0001119369, NIP 6343042685
Developer
Tauron (in-house)
Also called
BME Kuźnia Raciborska; ME Kuźnia Raciborska (capacity-market unit)

Where

Gmina
Kuźnia Raciborska
Powiat
raciborski
Voivodeship
śląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja
Connection, kV
15
Connection point
GPZ Kuźnia Raciborska 110/15 kV, 15 kV field 20 (Tauron code KUR3)

What

Power, MW
6.9
Energy, MWh
28
Hours at full power
4.06
Kind
standalone, front-of-meter, medium voltage
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1428
Capacity obligation, MW
3.978
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
6.5
Other capacity contracts
Tauron T-1 2027 storage obligation 14.155 MW (units not named)
Grant
€1.82m (7,968,064.60 zł). NFOŚiGW FM grant 7,968,064.60 zł (cost 22,955,000 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant plus Tauron; capex 15.3 m zł (H1 2026 report)

When

Connection agreement signed
2024-12-13
Connection date in the agreement
2026-06-26
Building started
not found
Switched on
2026-06 (register: storage activity from 2026-06-26)
Qualified for PSE’s balancing
not found
Commercial operation
planned Q3 2026

Evidence

Why this status
Tauron register entry 11 Jun 2026, activity from 26 Jun 2026; Tauron queue shows it connected. Tauron H1 2026 report (gramwzielone 24 Sep 2026): 96% complete, completion Q3 2026. COD not reported.
Its row in the connection lists
Tauron queue: station KUR3, SN, storage 9 MW out / 6.9 MW in, status "connected", agreement 2024-12-13, start 2026-06-26. Matched by station code, MW and date.
How the contract was matched
By unit name "ME Kuźnia Raciborska" and NIP 6343042685 (same as register owner).
Where sources disagree
Register: 7.5 MW installed / 6.9 MW discharge / 30.096 MWh; Tauron Dec 2025: 6.9 MW / 28 MWh; NFOŚiGW grant release (energyglobal): 6.9 MW / 30 MWh.
Still missing
COD (Tauron Q3 2026 report). Supplier/EPC (Tauron tenders). Coordinates.

Sources. register (tauron-dystrybucja.pl); queue (tauron-dystrybucja.pl); status (gramwzielone.pl); mwh (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); cm (ure.gov.pl)

Stawiszyn hybrid PV+BESS (TK Power) · Switched on · 5.04 MW

Who

Owner
TK Power
Project company
TK Power sp. z o.o. (KRS/NIP not found)
Developer
TK Power
Also called
not found

Where

Gmina
not found
Powiat
not found
Voivodeship
wielkopolskie
Coordinates
not found
Grid operator
Energa-Operator
Connection, kV
SN
Connection point
GPZ Stawiszyn

What

Power, MW
5.04
Energy, MWh
not found
Hours at full power
not found
Kind
hybrid PV (10.507 MW) + storage
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
None found for this site (TK Power holds 14 other NFOŚiGW grants, all for other sites)
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
2025-03-29
Connection date in the agreement
after 30 Jun 2026 (as printed)
Building started
not found
Switched on
by 30 Jun 2026 (queue status "connected")
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Energa-Operator list (data to 30 Jun 2026, published 31 Aug 2026): status "UMOWA O PRZYŁĄCZENIE - obiekt przyłączony" (connected).
Its row in the connection lists
Energa queue P/22/087372: TK Power, GPZ Stawiszyn, SN, MIX, storage 6 MW out / 2.5 MW in, 5.04 MW, PV 10.507 MW, connected. Direct row.
How the contract was matched
not found
Where sources disagree
Storage figures in the row: discharge 6 MW, charge 2.5 MW, "mw" 5.04.
Still missing
Energy capacity, equipment, start of operation (TK Power or Energa-Operator register, not captured). Gmina (Stawiszyn, powiat kaliski: confirm).

Sources. queue (cdn-netpr.pl)

Września BESS (Elektrownia PV 99) · Switched on · 5.01 MW

Who

Owner
R.Power (Elektrownia PV-numbered companies are R.Power SPVs; ownership of PV 99 not confirmed)
Project company
ELEKTROWNIA PV 99 sp. z o.o., KRS 000097272 (as printed, digit missing), NIP 5213969302
Developer
not found
Also called
not found

Where

Gmina
Września
Powiat
wrzesiński
Voivodeship
wielkopolskie
Coordinates
52.32938, 17.61300 (the land parcel of building permit ST-WK-WR/WNIOSEK/3099/2026 in GUNB’s register, placed by GUGiK)
Grid operator
Enea Operator
Connection, kV
SN
Connection point
behind the PV farm meter ("instalacja zalicznikowa")

What

Power, MW
5.0112
Energy, MWh
5.015
Hours at full power
1.00
Kind
co-located with PV (behind the generator meter)
Cells, integrator and builder
LFP (register)

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
register: start date given as 2022-05-23 (probably the PV farm)
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Entered in the operator's art. 43g storage register (first entry 2026-09-17); the register lists connected storage. No report of commercial operation found.
Its row in the connection lists
Not matched.
How the contract was matched
not found
Where sources disagree
One-hour battery (5.0 MW / 5.0 MWh). Register KRS has 9 digits.
Still missing
Owner group (KRS extract). Storage commissioning date. Coordinates.

Sources. register (operator.enea.pl); site (wyszukiwarka.gunb.gov.pl)

Bytnica BESS (WB Energy) · Switched on · 3.08 MW

Who

Owner
WB Energy
Project company
WB Energy sp. z o.o., KRS 0000269806, NIP 9671471843
Developer
not found
Also called
not found

Where

Gmina
Bytnica
Powiat
krośnieński
Voivodeship
lubuskie
Coordinates
52.10709, 15.10771 (the land parcel of building permit ST-LB-KO/WNIOSEK/2987/2026 in GUNB’s register, placed by GUGiK)
Grid operator
Enea Operator
Connection, kV
15
Connection point
15 kV switchgear in 110 kV/MV station Bytnica

What

Power, MW
3.084
Energy, MWh
not found
Hours at full power
not found
Kind
unknown (WB Energy is a wind/PV developer; possibly co-located)
Cells, integrator and builder
LFP (register)

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
register: storage activity from 2026-08-01
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Entered in the operator's art. 43g storage register (first entry 2026-08-13); the register lists connected storage. No report of commercial operation found.
Its row in the connection lists
Not matched.
How the contract was matched
not found
Where sources disagree
Register gives 0.006 MWh, which cannot be right for a 3.084 MW battery; energy left blank.
Still missing
Energy capacity (Enea register correction or WB Energy). Stand-alone or hybrid. Coordinates.

Sources. register (operator.enea.pl); site (wyszukiwarka.gunb.gov.pl)

Opole BESS (Renegia 4) · Switched on · 2.04 MW

Who

Owner
Renegia (Opole developer; group unconfirmed)
Project company
Renegia 4 sp. z o.o., KRS 0000955211, NIP 7543348538
Developer
not found
Also called
not found

Where

Gmina
Opole
Powiat
Opole
Voivodeship
opolskie
Coordinates
not found
Grid operator
Tauron Dystrybucja
Connection, kV
not found
Connection point
ZKSN no. OPC20985

What

Power, MW
2.037
Energy, MWh
4.0736
Hours at full power
2.00
Kind
not found
Cells, integrator and builder
LFP (register)

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
register: storage activity from 2026-09-24
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Entered in the operator's art. 43g storage register (first entry 2026-09-09); the register lists connected storage. No report of commercial operation found.
Its row in the connection lists
Not matched.
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Owner group; link to RENEGIA BULLA capacity units (11 units in Opole region, 2028 contracts, also 2026 quarterly contracts) not established; COD; connection voltage (KRS, Renegia).

Sources. register (tauron-dystrybucja.pl)

Kunice BESS (Solar Technics) · Switched on · 2.03 MW

Who

Owner
Solar Technics
Project company
Solar Technics sp. z o.o., KRS 0000518197, NIP 6912506034
Developer
not found
Also called
not found

Where

Gmina
Kunice
Powiat
legnicki
Voivodeship
dolnośląskie
Coordinates
51.19112, 16.34951 (the land parcel of building permit ST-DL-LE/WNIOSEK/788/2025 in GUNB’s register, placed by GUGiK)
Grid operator
Tauron Dystrybucja
Connection, kV
20
Connection point
20 kV overhead line LGL259

What

Power, MW
2.032
Energy, MWh
4.064
Hours at full power
2.00
Kind
unknown (likely co-located with PV)
Cells, integrator and builder
Li-ion (register)

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
register: storage activity from 2025-08-19
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Entered in the operator's art. 43g storage register (first entry 2025-10-27); the register lists connected storage. No report of commercial operation found.
Its row in the connection lists
Not matched.
How the contract was matched
not found
Where sources disagree
Register discharge power 0.995 MW, below 1 MW; installed 2.032 MW.
Still missing
Whether stand-alone or PV-coupled, supplier, COD, coordinates (Solar Technics). Its NFOŚiGW grant (2,008,227 zł) is for a different site, Piotrówek.

Sources. register (tauron-dystrybucja.pl); site (wyszukiwarka.gunb.gov.pl)

Bydgoszcz tram-company BESS (MZK) · Switched on · 1.2 MW

Who

Owner
Miejskie Zakłady Komunikacyjne w Bydgoszczy (municipal)
Project company
Miejskie Zakłady Komunikacyjne sp. z o.o., KRS 0000111252, NIP 5540314041
Developer
not found
Also called
not found

Where

Gmina
Bydgoszcz
Powiat
bydgoski
Voivodeship
kujawsko-pomorskie
Coordinates
53.10599, 17.98258 (the land parcel of building permit ST-KP-BD/WNIOSEK/10486/2025 in GUNB’s register, placed by GUGiK)
Grid operator
Enea Operator
Connection, kV
SN
Connection point
behind the meter ("instalacja zalicznikowa"); queue: Bydgoszcz Błonie field 20

What

Power, MW
1.2
Energy, MWh
4.18
Hours at full power
3.48
Kind
behind the meter (municipal transport)
Cells, integrator and builder
LFP (register)

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
register: start date given as 2002-05-10 (company date, not storage)
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Entered in the operator's art. 43g storage register (first entry 2026-07-30); the register lists connected storage. No report of commercial operation found.
Its row in the connection lists
Enea queue no. 62884/2024, MZK, Bydgoszcz Błonie field 20 behind the meter, storage 1.2 MW in / 2 MW, agreement 2025-11-27. Matched by applicant name.
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Real start date of storage operation. Supplier.

Sources. register (operator.enea.pl); site (wyszukiwarka.gunb.gov.pl)

Goczałkowice-Zdrój BESS (JAK Szkło Żogała) · Switched on · 1 MW

Who

Owner
JAK Szkło Żogała
Project company
JAK SZKŁO ŻOGAŁA, KRS 0000012797, NIP 6381002475
Developer
not found
Also called
not found

Where

Gmina
Goczałkowice-Zdrój
Powiat
pszczyński
Voivodeship
śląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja
Connection, kV
not found
Connection point
ul. Brzozowa 62, 43-230 Goczałkowice-Zdrój

What

Power, MW
1.001
Energy, MWh
2.002
Hours at full power
2.00
Kind
commercial/industrial, likely behind the meter
Cells, integrator and builder
LFP (register)

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
register: start date blank
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Entered in the operator's art. 43g storage register (first entry 2026-09-15); the register lists connected storage. No report of commercial operation found.
Its row in the connection lists
Not matched.
How the contract was matched
not found
Where sources disagree
Discharge power 0.861 MW.
Still missing
Whether behind the meter. Supplier. Start date.

Sources. register (tauron-dystrybucja.pl)

Gliwice BESS (Śląskie Centrum Logistyki) · Switched on · 1 MW

Who

Owner
Śląskie Centrum Logistyki S.A.
Project company
ŚLĄSKIE CENTRUM LOGISTYKI S.A., KRS 0000047612, NIP 6310000121
Developer
not found
Also called
not found

Where

Gmina
Gliwice
Powiat
gliwicki
Voivodeship
śląskie
Coordinates
50.33118, 18.63020 (the land parcel of building permit ST-SL-GL/WNIOSEK/19141/2024 in GUNB’s register, placed by GUGiK)
Grid operator
Tauron Dystrybucja
Connection, kV
6
Connection point
cable heads of 6 kV supply cable in station G190

What

Power, MW
1
Energy, MWh
2.12
Hours at full power
2.12
Kind
commercial/industrial, likely behind the meter (logistics site)
Cells, integrator and builder
LFP (register)

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
register: storage activity from 2026-09-15
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Entered in the operator's art. 43g storage register (first entry 2026-07-10); the register lists connected storage. No report of commercial operation found.
Its row in the connection lists
Not matched.
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Behind-the-meter or front-of-meter (owner). Supplier. Coordinates.

Sources. register (tauron-dystrybucja.pl); site (wyszukiwarka.gunb.gov.pl)

Ceków hybrid PV+BESS (Domagała Nieruchomości) · Switched on · 1 MW

Who

Owner
Domagała Nieruchomości
Project company
Domagała Nieruchomości sp. z o.o. (KRS/NIP not found)
Developer
not found
Also called
not found

Where

Gmina
not found
Powiat
not found
Voivodeship
wielkopolskie
Coordinates
not found
Grid operator
Energa-Operator
Connection, kV
SN
Connection point
GPZ Ceków

What

Power, MW
1
Energy, MWh
not found
Hours at full power
not found
Kind
hybrid PV (1.029 MW) + storage, probably behind a commercial meter
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
2024-12-19
Connection date in the agreement
after 30 Jun 2026 (as printed)
Building started
not found
Switched on
by 30 Jun 2026 (queue status "connected")
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Energa-Operator list (data to 30 Jun 2026): status "connected".
Its row in the connection lists
Energa queue P/24/084846, GPZ Ceków, SN, MIX, storage 1 MW (charge 1 MW), PV 1.029 MW, connected. Direct row.
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Energy capacity, owner details, start date. Borderline for a grid-scale register at 1 MW.

Sources. queue (cdn-netpr.pl)

Being built

Siedlce BESS (Greenvolt) · Being built · 600 MW

Who

Owner
Greenvolt Power (KKR)
Project company
Magazyn EE Siedlce sp. z o.o. (PSE applicant); capacity contract held by GREENVOLT POWER TRADING sp. z o.o., NIP 5213983839
Developer
Greenvolt Power
Also called
MEE Siedlce (capacity-market unit); MEE Siedlce 1 i 2 (PSE queue)

Where

Gmina
Zbuczyn (from the permit’s parcel)
Powiat
siedlecki
Voivodeship
mazowieckie
Coordinates
52.11017, 22.40890 (the land parcel of building permit ST-MZ-SI/WNIOSEK/31435/2023 in GUNB’s register, placed by GUGiK)
Grid operator
PSE
Connection, kV
400
Connection point
Siedlce Ujrzanów (PSE)

What

Power, MW
600
Energy, MWh
2400
Hours at full power
4.00
Kind
standalone, front-of-meter, transmission-connected
Cells, integrator and builder
BYD Energy Storage (10 MWh 20-ft Haohan containers); EPC P&Q and ONDE; SCADA/EMS contract awarded Sept 2026

Money

Capacity unit
JRM/1154
Capacity obligation, MW
510
Contract years
17
First delivery year
2028
Four-hour equivalent, MW
536.8
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
2022-02-09
Connection date in the agreement
2027-12-30
Building started
2026-09 (start announced 24 Sep 2026)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
targeted end-2027

Evidence

Why this status
Energy-storage.news and energyglobal 24 Sep 2026; gramwzielone 28 Sep 2026: construction has started.
Its row in the connection lists
PSE list: "MEE Siedlce 1 i 2", Magazyn EE Siedlce sp. z o.o., Siedlce Ujrzanów 400 kV, 600 MW, agreement 2022-02-09, start of delivery 2027-12-30. Matched by name.
How the contract was matched
By unit name "MEE Siedlce" (URE 2028 main list).
Where sources disagree
none recorded
Still missing
Gmina/powiat and coordinates (Greenvolt, building permit). Financing. Optimiser/offtake. KRS of SPV.

Sources. status (energy-storage.news); status pl (gramwzielone.pl); supplier (gramwzielone.pl); scada (gramwzielone.pl); queue (pse.pl); cm (ure.gov.pl); site (wyszukiwarka.gunb.gov.pl)

Dzięgielewo BESS (R.Power) · Being built · 300 MW

Who

Owner
R.Power
Project company
Elektrownia PV 96 sp. z o.o., NIP 5213969035
Developer
R.Power
Also called
MEE Dzięgielewo (PSE queue); "Dzięgielewo w miejscowości Dziarnowo" (NFOŚiGW)

Where

Gmina
Stara Biała (from the permit’s parcel)
Powiat
płocki
Voivodeship
mazowieckie
Coordinates
52.64089, 19.67353 (the land parcel of building permit ST-MZ-PL/WNIOSEK/23768/2025 in GUNB’s register, placed by GUGiK)
Grid operator
PSE
Connection, kV
400
Connection point
Płock (PSE)

What

Power, MW
300
Energy, MWh
1200
Hours at full power
4.00
Kind
standalone, front-of-meter, transmission-connected
Cells, integrator and builder
ONDE (contract 117,814,096 zł net: design, procurement, civil and electrical works; construction starts on investor's written instruction); battery supplier not named

Money

Capacity unit
JRM/2407
Capacity obligation, MW
40.17
Contract years
17
First delivery year
2030
Four-hour equivalent, MW
300.0
Other capacity contracts
not found
Grant
€43.05m (188,420,875.61 zł). NFOŚiGW FM: grant 188,420,875.61 zł plus loan 198,924,097.75 zł recommended (cost 542,698,800 zł)
Trader, optimiser or toll
Axpo 10-year optimisation agreement with a floor (May 2026)
Financing
Green bonds and state grants (ESS News)

When

Connection agreement signed
2026-07-22
Connection date in the agreement
2030-03-31
Building started
2026-07 (contract signed 15 Jul 2026; start reported 23-28 Jul 2026)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
turn of 2027/2028 (ONDE: handover in 2027)

Evidence

Why this status
ESS News 23 Jul 2026 and gramwzielone 28 Jul 2026 report construction starting. ONDE (15 Jul 2026): works begin only on the investor's written instruction, so physical start is not separately confirmed.
Its row in the connection lists
PSE list: "MEE Dzięgielewo", Elektrownia PV 96 sp. z o.o., Płock 400 kV, 300 MW, agreement 2026-07-22, start of delivery 2030-03-31. Matched by company.
How the contract was matched
By NIP 5213969035 (2030 main auction; unit names not published in that list).
Where sources disagree
Capacity delivery from 2029 (gramwzielone, ESS News) vs 2030 main auction in URE list. PSE connection date 2030 vs COD 2027/28.
Still missing
Gmina (Dziarnowo is a village in mazowieckie; confirm gmina). Confirm physical start. Battery supplier. Coordinates.

Sources. status (ess-news.com); status pl (gramwzielone.pl); epc (biznesradar.pl); optimiser (energy-storage.news); optimiser 10yr (energy-storage.news); grant (gov.pl); queue (pse.pl); cm (ure.gov.pl); site (wyszukiwarka.gunb.gov.pl)

Żarnowiec BESS (PGE) · Being built · 262 MW

Who

Owner
PGE Polska Grupa Energetyczna
Project company
PGE Inwest 14 sp. z o.o. (PSE applicant and KPO beneficiary; KRS/NIP not found); capacity contract held by PGE Polska Grupa Energetyczna S.A., NIP 5260250541
Developer
PGE Energia Odnawialna
Also called
BMEE Żarnowiec; MEE Żarnowiec (capacity-market unit); MEE Kartoszyno (PSE queue)

Where

Gmina
Krokowa (Kartoszyno, from PSE row name; confirm)
Powiat
pucki
Voivodeship
pomorskie
Coordinates
54.74428, 18.09528 (the land parcel of building permit ST-PM-PU/WNIOSEK/5043/2025 in GUNB’s register, placed by GUGiK)
Grid operator
PSE
Connection, kV
400
Connection point
Żarnowiec (PSE); 30/400 kV transformer

What

Power, MW
262
Energy, MWh
981
Hours at full power
3.74
Kind
standalone, front-of-meter, transmission-connected (next to Żarnowiec pumped storage)
Cells, integrator and builder
LG Energy Solution Wrocław: general contractor and DC-Link containers (204 planned); 400 kV transformer from South Korea

Money

Capacity unit
JRM/602
Capacity obligation, MW
137.925
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
225.0
Other capacity contracts
not found
Grant
over €108.98m (477,000,000 zł). KPO "Systemy magazynowania energii" grant "over 477 m zł" (NFOŚiGW, Dec 2025); FM application (470.7 m zł requested) rejected
Trader, optimiser or toll
PGE group
Financing
KPO grant plus PGE; budget about 1.3 bn zł (H1 2026) / contract 1.555 bn zł gross

When

Connection agreement signed
2023-11-15
Connection date in the agreement
2028-06-30
Building started
2025-09-19
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q2 2027

Evidence

Why this status
PGE H1 2026 report (gramwzielone 23 Sep 2026): about 85% complete; all units and HV transformer works finished Aug 2026; COD Q2 2027.
Its row in the connection lists
PSE list: "MEE Kartoszyno", PGE Inwest 14, Żarnowiec 400 kV, 263.2 MW (charge 269.4), agreement 2023-11-15, start of delivery 2028-06-30. Matched by company (KPO beneficiary PGE Inwest 14) and size.
How the contract was matched
By unit name "MEE Żarnowiec" and supplier PGE (URE 2029 main list); 137.925 / 0.613 = 225 MW = 900 MWh / 4.
Where sources disagree
Energy: 981 MWh (contract, KPO) vs about 1,020 MWh nominal (H1 2026 report) vs 900 MWh (2024 tender). Power 262 vs 263 MW. Cost 1.555 bn zł gross (contract) vs about 1.3 bn zł (H1 2026 budget).
Still missing
Exact KPO grant amount (NFOŚiGW agreement). Gmina and coordinates (PGE, Geoportal). KRS/NIP of PGE Inwest 14.

Sources. status (gramwzielone.pl); construction start (biznesradar.pl); equipment (gramwzielone.pl); grant (gramwzielone.pl); kpo beneficiary (gramwzielone.pl); queue (pse.pl); cm (ure.gov.pl); fm rejected (gov.pl); site (wyszukiwarka.gunb.gov.pl)

Gdańsk II BESS (R.Power) · Being built · 250 MW

Who

Owner
R.Power
Project company
Elektrownia PV 61 sp. z o.o., NIP 5213892278
Developer
R.Power
Also called
Magazyn energii Gdańsk II (capacity-market unit); MEE Gdańsk 2 (PSE queue)

Where

Gmina
Gdańsk
Powiat
Gdańsk
Voivodeship
pomorskie
Coordinates
not found
Grid operator
PSE
Connection, kV
110
Connection point
Gdańsk Błonia (PSE)

What

Power, MW
250
Energy, MWh
1000
Hours at full power
4.00
Kind
standalone, front-of-meter, 110 kV at a PSE substation
Cells, integrator and builder
ESIX (EPC or balance-of-plant: a reader comment calls these BoP contracts); battery supplier not named

Money

Capacity unit
JRM/1513
Capacity obligation, MW
153.25
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
250.0
Other capacity contracts
not found
Grant
€35.32m (154,570,037.41 zł). NFOŚiGW FM: grant 154,570,037.41 zł plus loan 163,186,298.40 zł recommended (cost 445,200,000 zł)
Trader, optimiser or toll
not found
Financing
Green bonds and state grants (ESS News); R.Power recapitalisation €250m

When

Connection agreement signed
2025-03-18
Connection date in the agreement
2032-06-30
Building started
2026-07 (contracts signed; start reported 23-28 Jul 2026)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
turn of 2027/2028

Evidence

Why this status
ESS News 23 Jul 2026 ("moves into construction") and gramwzielone 28 Jul 2026 ("construction starts"). Physical works not separately confirmed.
Its row in the connection lists
PSE list: "MEE Gdańsk 2", Elektrownia PV 61 sp. z o.o., Gdańsk Błonia 110 kV, 250 MW, agreement 2025-03-18, start of delivery 2032-06-30. Matched by company.
How the contract was matched
By NIP 5213892278 and unit name.
Where sources disagree
PSE agreed connection date 30 Jun 2032 is years after the planned COD (2027/28); a capacity obligation starts 2029.
Still missing
Confirm physical construction start and that the PSE connection date was brought forward (PSE list, R.Power). Battery supplier. Exact site and coordinates. Whether NFOŚiGW agreements were signed (R.Power says 499.1 m zł received in total).

Sources. status (ess-news.com); status pl (gramwzielone.pl); epc (energy-storage.news); grant (gov.pl); r power grants total (gramwzielone.pl); queue (pse.pl); cm (ure.gov.pl)

Mieczysławów BESS (Northland Power) · Being built · 200 MW

Who

Owner
Northland Power (bought from Greenvolt, Nov 2025)
Project company
Magazyn EE Mieczysławów sp. z o.o. (PSE applicant, NFOŚiGW beneficiary); capacity contract held by GREENVOLT POWER TRADING sp. z o.o., NIP 5213983839
Developer
Greenvolt Power (to pre-construction)
Also called
MEE Mieczysławów

Where

Gmina
Ślesin (from the permit’s parcel)
Powiat
koniński
Voivodeship
wielkopolskie
Coordinates
52.33062, 18.24447 (the land parcel of building permit ST-WK-KN/WNIOSEK/9879/2025 in GUNB’s register, placed by GUGiK)
Grid operator
PSE
Connection, kV
220
Connection point
Pątnów (PSE)

What

Power, MW
200
Energy, MWh
800
Hours at full power
4.00
Kind
standalone, front-of-meter, transmission-connected
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1150
Capacity obligation, MW
170
Contract years
17
First delivery year
2028
Four-hour equivalent, MW
178.9
Other capacity contracts
not found
Grant
€40.99m (179,413,200 zł). NFOŚiGW FM grant 179,413,200 zł (cost 520,021,625 zł); Northland/PKO: grants for both projects about 280 m zł
Trader, optimiser or toll
not found
Financing
About 500 m zł for Mieczysławów and Kamionka: PKO Bank Polski, Bank Pekao (agent), BGK and Export Development Canada; financial close announced 30 Sep 2026; total cost of both about 1 bn zł

When

Connection agreement signed
2022-02-01
Connection date in the agreement
2027-05-30
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2028 (early 2028 per ESN; mid-2028 per gramwzielone)

Evidence

Why this status
PKO BP 8 Oct 2026 and gramwzielone 1 Oct 2026: both projects already under construction.
Its row in the connection lists
PSE list: "MEE Mieczysławów", Magazyn EE Mieczysławów sp. z o.o., Pątnów 220 kV, 200 MW, agreement 2022-02-01, start of delivery 2027-05-30. Matched by name.
How the contract was matched
By unit name "MEE Mieczysławów".
Where sources disagree
COD: early 2028 (energy-storage.news 2 Oct 2026) vs mid-2028 (gramwzielone 1 Oct 2026, which gives Kamionka early 2028). Energy-storage.news says grants of about 1 bn zł; PKO and gramwzielone say about 280 m zł, which matches the ranking list (282.0 m zł).
Still missing
Gmina and coordinates. Equipment supplier and EPC (Northland). Construction start date. Which COD is right.

Sources. status (pkobp.pl); cod pl (gramwzielone.pl); cod en (energy-storage.news); acquisition (energy-storage.news); grant (gov.pl); queue (pse.pl); cm (ure.gov.pl); site (wyszukiwarka.gunb.gov.pl)

Jedwabno BESS (R.Power) · Being built · 150 MW

Who

Owner
R.Power
Project company
Magazyn Energii Jedwabno sp. z o.o., NIP 5214076492 (earlier Elektrownia PV 76 sp. z o.o. held the URE concession promise)
Developer
R.Power
Also called
Magazyn Energii Jedwabno (capacity-market unit)

Where

Gmina
Lubicz
Powiat
toruński
Voivodeship
kujawsko-pomorskie
Coordinates
53.05883, 18.77490 (the land parcel of building permit ST-KP-TO/WNIOSEK/5961/2025 in GUNB’s register, placed by GUGiK)
Grid operator
Energa-Operator
Connection, kV
110
Connection point
SE Toruń Elana

What

Power, MW
150
Energy, MWh
300
Hours at full power
2.00
Kind
standalone, front-of-meter, 110 kV
Cells, integrator and builder
EPC Nomad Electric (R.Power group) with ESIX; 64 battery containers, 32 MV transformer stations; battery supplier not named

Money

Capacity unit
JRM/1255
Capacity obligation, MW
45.975
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
75.0
Other capacity contracts
T-1 2027 supplementary auction: R.Power won 75.994 MW for Jedwabno and Herby together
Grant
NFOŚiGW FM grant and loan applications not recommended
Trader, optimiser or toll
Axpo long-term optimisation (signed Jan or Feb 2026 per R.Power/energyglobal; ESS News says May)
Financing
Project finance about 270 m zł (€64m), Siemens Bank (Siemens Financial Services) and Erste Group, June 2026

When

Connection agreement signed
2024-10-14
Connection date in the agreement
after 30 Jun 2026 (as printed)
Building started
2026-02 (energyglobal; ESS News says ground broken in March)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
grid connection planned Dec 2026

Evidence

Why this status
Energyglobal 8 Oct 2026 and gramwzielone 8 Oct 2026: all 64 containers delivered and installed; grid connection planned for December 2026.
Its row in the connection lists
Energa queue P/23/006183: Magazyn Energii Jedwabno sp. z o.o., SE Toruń Elana, 110 kV, 150 MW, agreement 2024-10-14; second row P/25/041776 (31.44 MW, agreement 2026-04-27). Matched by applicant name.
How the contract was matched
By unit name and NIP 5214076492.
Where sources disagree
Construction start Feb 2026 (energyglobal) vs March 2026 (ESS News). Axpo deal Jan 2026 (energyglobal) vs Feb 2026 (gramwzielone) vs May 2026 (ESS News).
Still missing
Battery supplier (R.Power). Coordinates. Second Energa row (31.44 MW) purpose.

Sources. status (energyglobal.com); containers (gramwzielone.pl); financing (gramwzielone.pl); gmina (gramwzielone.pl); voivodeship (gramwzielone.pl); epc (ess-news.com); queue (cdn-netpr.pl); cm (ure.gov.pl); grant not recommended (gov.pl); site (wyszukiwarka.gunb.gov.pl)

Trzebinia BESS (DRI / DTEK, to Actis) · Being built · 133 MW

Who

Owner
DRI (DTEK Renewables International, DTEK group); Actis to acquire on completion (announced 6 Oct 2026)
Project company
Fotowoltaika HIG XVIII sp. z o.o., NIP 5213943455 (capacity contract and PSE applicant)
Developer
Columbus Energy (to RtB), then DRI
Also called
MEE Trzebinia (PSE queue); BESS Trzebinia

Where

Gmina
Trzebinia (name) or Chrzanów (Columbus 2024 article): see disagreements
Powiat
chrzanowski
Voivodeship
małopolskie
Coordinates
not found
Grid operator
PSE
Connection, kV
220
Connection point
Siersza (PSE)

What

Power, MW
133
Energy, MWh
622
Hours at full power
4.68
Kind
standalone, front-of-meter, transmission-connected
Cells, integrator and builder
Fluence Smartstack; EPC Electrum

Money

Capacity unit
JRM/730
Capacity obligation, MW
123.852
Contract years
17
First delivery year
2027
Four-hour equivalent, MW
130.4
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
Entrix optimisation and trading (June 2026)
Financing
About 470 m zł non-recourse project finance: Erste Bank Polska (coordinator, agent), PKO Bank Polski, UniCredit; KUKE guarantee under the ITE programme (June 2026)

When

Connection agreement signed
2024-07-03
Connection date in the agreement
2027-01-30
Building started
2026 (start announced by June 2026)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned early 2027

Evidence

Why this status
Gramwzielone 10 and 22 Jun 2026: construction under way; commissioning planned early 2027. Energy-storage.news 8 Oct 2026: Actis deal completes once operational.
Its row in the connection lists
PSE list: "MEE Trzebinia", Fotowoltaika HIG XVIII sp. z o.o., Siersza 220 kV, 132.264 MW, agreement 2024-07-03, start of delivery 2027-01-30. Matched by company.
How the contract was matched
By NIP 5213943455 (Fotowoltaika HIG XVIII), 2027 main auction; Columbus and DRI statements tie this SPV to the project.
Where sources disagree
Energy: 532 MWh (Columbus 2024) vs 622 MWh (Fluence, DRI) vs 623 MWh (Actis). Power 133 vs 132 MW. Gmina: Columbus 2024 article said gmina Chrzanów; project name and PSE substation (Siersza) point to Trzebinia.
Still missing
Gmina and coordinates (building permit, Geoportal). Construction start date. Energisation date (due before 2027 capacity obligation).

Sources. status (gramwzielone.pl); status (gramwzielone.pl); mwh (ir.fluenceenergy.com); optimiser (gramwzielone.pl); actis (energy-storage.news); columbus sale (gramwzielone.pl); queue (pse.pl); cm (ure.gov.pl)

Kamionka BESS (Northland Power) · Being built · 100 MW

Who

Owner
Northland Power (bought from Greenvolt, Nov 2025)
Project company
Magazyn EE Kamionka sp. z o.o. (PSE applicant, NFOŚiGW beneficiary); capacity contract held by GREENVOLT POWER TRADING sp. z o.o., NIP 5213983839
Developer
Greenvolt Power (to pre-construction)
Also called
MEE Kamionka; "Turek 1 etap 1" (PSE queue)

Where

Gmina
not found
Powiat
turecki
Voivodeship
wielkopolskie
Coordinates
52.00873, 18.53751 (the land parcel of building permit ST-WK-TU/WNIOSEK/7680/2023 in GUNB’s register, placed by GUGiK)
Grid operator
PSE
Connection, kV
110
Connection point
Adamów (PSE)

What

Power, MW
100
Energy, MWh
400
Hours at full power
4.00
Kind
standalone, front-of-meter, transmission-connected
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1149
Capacity obligation, MW
85
Contract years
17
First delivery year
2028
Four-hour equivalent, MW
89.5
Other capacity contracts
not found
Grant
€23.45m (102,619,500 zł). NFOŚiGW FM grant 102,619,500 zł (cost 304,040,263 zł)
Trader, optimiser or toll
not found
Financing
Shared about 500 m zł loan with Mieczysławów (PKO BP, Pekao, BGK, EDC), announced 30 Sep 2026

When

Connection agreement signed
2022-03-15
Connection date in the agreement
2026-12-26
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2028 (mid-2028 per ESN; early 2028 per gramwzielone)

Evidence

Why this status
PKO BP 8 Oct 2026 and gramwzielone 1 Oct 2026: under construction.
Its row in the connection lists
PSE list: "MEE Kamionka (Turek 1 etap 1)", Magazyn EE Kamionka sp. z o.o., Adamów 110 kV, 100 MW, agreement 2022-03-15, start of delivery 2026-12-26. Matched by name.
How the contract was matched
By unit name "MEE Kamionka".
Where sources disagree
COD differs between sources (see Mieczysławów). PSE agreed delivery date 26 Dec 2026 vs COD 2028.
Still missing
Gmina and coordinates. Supplier and EPC. Construction start.

Sources. status (pkobp.pl); cod pl (gramwzielone.pl); cod en (energy-storage.news); grant (gov.pl); queue (pse.pl); cm (ure.gov.pl); site (wyszukiwarka.gunb.gov.pl)

Lwówek Śląski BESS (Green Capital) · Being built · 80 MW

Who

Owner
Green Capital S.A. and Prime Capital AG (50% of this project), joint venture
Project company
Słoneczko V sp. z o.o., NIP 8911632269
Developer
Green Capital
Also called
Płóczki Górne (NFOŚiGW); possibly "ME Rząsiny" (capacity-market unit)

Where

Gmina
Lwówek Śląski
Powiat
lwówecki
Voivodeship
dolnośląskie
Coordinates
51.06535, 15.53949 (the land parcel of building permit ST-DL-LS/WNIOSEK/3988/2025 in GUNB’s register, placed by GUGiK)
Grid operator
Tauron Dystrybucja
Connection, kV
110
Connection point
possibly Tauron station LWO4 (inferred)

What

Power, MW
80
Energy, MWh
320
Hours at full power
4.00
Kind
standalone, front-of-meter, 110 kV
Cells, integrator and builder
Electrum full-wrap EPC (design, technology supply, civil, HV, grid integration, EMS/SCADA, 5-year O&M); battery supplier not named

Money

Capacity unit
JRM/1133
Capacity obligation, MW
48.794
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
79.6
Other capacity contracts
not found
Grant
€22.12m (96,810,090.73 zł). NFOŚiGW FM grant 96,810,090.73 zł recommended (cost 228,139,400 zł; "80 MW and 320 MWh in Płóczki Górne")
Trader, optimiser or toll
not found
Financing
Prime Capital equity (50%); NFOŚiGW grant

When

Connection agreement signed
2023-12-06 (inferred Tauron match)
Connection date in the agreement
not found
Building started
2026-Q2 (planned)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q3 2027

Evidence

Why this status
Gramwzielone 20 May 2026: Green Capital has 80 MW of storage under construction (this is its only 80 MW project). Construction was scheduled to start in Q2 2026 (gramwzielone 20 Apr 2026).
Its row in the connection lists
Possible Tauron queue row: station LWO4, 110 kV, storage 80 MW, agreement 2023-12-06 (inferred from station code and size).
How the contract was matched
By company Słoneczko V (same as grant beneficiary) and size: 48.794 / 0.613 = 79.6 MW four-hour equivalent. Unit name "ME Rząsiny" differs from Płóczki Górne; check both villages are the site.
Where sources disagree
A reader comment claims the site is in a flood zone and faces local opposition (unverified).
Still missing
Dated confirmation that works began (Green Capital). Confirm ME Rząsiny = this project. Connection point. Coordinates.

Sources. status (gramwzielone.pl); cod (gramwzielone.pl); epc en (energy-storage.news); grant (gov.pl); cm (ure.gov.pl); queue (tauron-dystrybucja.pl); site (wyszukiwarka.gunb.gov.pl)

Osiek Jasielski BESS (OX2) · Being built · 50 MW

Who

Owner
OX2
Project company
OX2 Green sp. z o.o., NIP 5252813797 (capacity contract holder)
Developer
OX2
Also called
Osiek BESS; OX2's first Polish battery

Where

Gmina
Osiek Jasielski
Powiat
jasielski
Voivodeship
podkarpackie
Coordinates
not found
Grid operator
PGE Dystrybucja (Rzeszów branch)
Connection, kV
110
Connection point
not found

What

Power, MW
50
Energy, MWh
120
Hours at full power
2.40
Kind
standalone, front-of-meter, 110 kV
Cells, integrator and builder
Fluence Smartstack; OX2 usually keeps EPC in-house

Money

Capacity unit
JRM/758
Capacity obligation, MW
21.09
Contract years
17
First delivery year
2027
Four-hour equivalent, MW
22.2
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
Long-term project financing from NORD/LB and CaixaBank (also covers OX2's Lion PV farm), June 2026

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
2024 (works on both sides of the connection point, July 2024); investment decision 1 Jun 2026
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
2027 ("next year", June 2026); earlier target mid-2026

Evidence

Why this status
Energy-storage.news 4 Jun 2026: FID taken and construction under way. OX2 press release 1 Jun 2026: investment decision.
Its row in the connection lists
PGE Dystrybucja queue not captured.
How the contract was matched
By supplier OX2 Green sp. z o.o. and press: OX2's only 2027-auction unit, "21 MW portion" of the battery.
Where sources disagree
Energy: 100 MWh (gramwzielone 2024) vs 120 MWh (OX2 2026). "Construction underway" in July 2024 vs investment decision announced June 2026.
Still missing
Connection substation (PGE Dystrybucja queue, not captured). Project-company KRS. Coordinates. Energisation before the 2027 capacity obligation.

Sources. status (energy-storage.news); financing (ox2.com); supplier (gramwzielone.pl); 2024 (gramwzielone.pl); cm (ure.gov.pl)

Bydgoszcz BESS (Tavion) · Being built · 20 MW

Who

Owner
Tavion (Sweden)
Project company
not found
Developer
Tavion
Also called
Tavion's first Polish battery park

Where

Gmina
Bydgoszcz
Powiat
Bydgoszcz
Voivodeship
kujawsko-pomorskie
Coordinates
not found
Grid operator
Enea Operator
Connection, kV
not found
Connection point
not found

What

Power, MW
20
Energy, MWh
40
Hours at full power
2.00
Kind
standalone, front-of-meter
Cells, integrator and builder
HyperStrong (BESS integration); Esix Polska (part of works); Ayesa (engineer)

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
Tavion equity (€34m round led by Leitmotif and Oberon Capital) plus debt raised Sept 2026 (€50m total incl. €16m credit line)

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
2026-10 (reported started 13 Oct 2026)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
grid connection expected 2027

Evidence

Why this status
Gramwzielone 13 Oct 2026: construction has started.
Its row in the connection lists
Possible Enea queue rows: ALFAMA sp. z o.o., Bydgoszcz Południe SN, 2 x 9.415 MW, agreement 2025-11-04 (unconfirmed; matched only by city and size).
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Project company and site (Tavion). Connection point (Enea queue match). Coordinates.

Sources. status (gramwzielone.pl); financing (gramwzielone.pl); queue (operator.enea.pl)

Puławy BESS (RelyAssets) · Being built · 4 MW

Who

Owner
RelyAssets (Spain)
Project company
not found
Developer
RelyAssets
Also called
not found

Where

Gmina
Puławy
Powiat
puławski
Voivodeship
lubelskie
Coordinates
not found
Grid operator
PGE Dystrybucja (assumed: Lublin region)
Connection, kV
not found
Connection point
not found

What

Power, MW
4
Energy, MWh
16
Hours at full power
4.00
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
A RelyAssets company won about 4 MW in the T-1 2027 supplementary auction (WysokieNapiecie/Modo via earlier research; unit not named)
Grant
not found
Trader, optimiser or toll
Entrix: optimisation and commercialisation (ancillary services, day-ahead, intraday)
Financing
RelyAssets raised over €2.3m for the project

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
by June 2026
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Sept 2026 (not confirmed)

Evidence

Why this status
Gramwzielone 22 Jun 2026: being built, commissioning planned for September 2026. No later report found.
Its row in the connection lists
PGE Dystrybucja queue not captured.
How the contract was matched
Unconfirmed (T-1 2027 list not read).
Where sources disagree
none recorded
Still missing
Whether it was energised in Sept 2026 (RelyAssets/Entrix). Project company. T-1 2027 capacity contract (URE final T-1 list). Coordinates.

Sources. status (gramwzielone.pl); entrix (gramwzielone.pl)

Financed, not started

Gryfino BESS (PGE) · Financed, not started · 400 MW

Who

Owner
PGE Polska Grupa Energetyczna
Project company
PGE Inwest 22 sp. z o.o. (PSE applicant, FM applicant); capacity contract held by PGE Polska Grupa Energetyczna S.A., NIP 5260250541
Developer
PGE Energia Odnawialna
Also called
Magazyn Energii Gryfino; ME Gryfino (capacity-market unit); site at Nowe Czarnowo

Where

Gmina
Gryfino
Powiat
gryfiński
Voivodeship
zachodniopomorskie
Coordinates
not found
Grid operator
PSE
Connection, kV
400
Connection point
Krajnik (PSE)

What

Power, MW
400
Energy, MWh
800
Hours at full power
2.00
Kind
standalone, front-of-meter, transmission-connected (two-hour)
Cells, integrator and builder
Fluence SmartStack; design-build turnkey contract with SPEC BAU Polska and EL Professional, 1.142 bn zł gross (1.1 bn zł per H1 report); contract engineer Elbis (Apr 2026)

Money

Capacity unit
JRM/1165
Capacity obligation, MW
120.782
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
197.0
Other capacity contracts
not found
Grant
NFOŚiGW FM application (383.3 m zł requested) not recommended
Trader, optimiser or toll
PGE group
Financing
PGE balance sheet (future capex commitments about 940 m zł at 30 Jun 2026)

When

Connection agreement signed
2025-05-26
Connection date in the agreement
2028-11-30
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned end-2028

Evidence

Why this status
PGE H1 2026 report (gramwzielone 23 Sep 2026): EPC contract signed, in design phase, no construction yet.
Its row in the connection lists
PSE list: "MEE Gryfino", PGE Inwest 22, Krajnik 400 kV, 400.069 MW, agreement 2025-05-26, start of delivery 2028-11-30. Matched by name.
How the contract was matched
By unit name "ME Gryfino" and supplier PGE (URE 2029 list).
Where sources disagree
Contract value 1.142 bn zł gross (tender result) vs 1.1 bn zł (H1 report).
Still missing
Construction start date. Coordinates.

Sources. status (gramwzielone.pl); epc (gramwzielone.pl); queue (pse.pl); cm (ure.gov.pl); grant rejected (gov.pl)

Zwartowo III PV + BESS (Respect Energy) · Financed, not started · 184 MW

Who

Owner
Respect Energy
Project company
Respect Energy Solar Zwartowo sp. z o.o.
Developer
Respect Energy
Also called
PV+MEE Zwartowo III (PSE queue; formerly PV Zwartowo / FW Choczewo)

Where

Gmina
Choczewo (Zwartowo village; confirm)
Powiat
wejherowski
Voivodeship
pomorskie
Coordinates
not found
Grid operator
PSE
Connection, kV
110
Connection point
Żarnowiec (PSE)

What

Power, MW
184
Energy, MWh
not found
Hours at full power
not found
Kind
hybrid with 255 MWp PV
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
KPO Fundusz Wsparcia Energetyki preferential financing over 326 m zł via BGK for PV (255 MWp) and BESS together (loan or grant not stated)
Trader, optimiser or toll
Respect Energy group
Financing
BGK/KPO preferential financing agreement over 326 m zł (May 2026)

When

Connection agreement signed
2010-05-05 (as printed in PSE list)
Connection date in the agreement
2030-04-10
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Gramwzielone 27 May 2026: financing agreement signed with BGK; project described in future tense, no construction start. Partial financing only; included because a financing agreement is signed; treat as borderline.
Its row in the connection lists
PSE list: "PV+MEE Zwartowo III (wcześniej PV Zwartowo; FW Choczewo)", Respect Energy Solar Zwartowo sp. z o.o., Żarnowiec 110 kV, MIX 184 MW, start of delivery 2030-04-10. Matched by name and company.
How the contract was matched
not found
Where sources disagree
PSE agreement date 2010-05-05 reflects the original wind-farm agreement.
Still missing
Battery MWh, share of financing for storage, construction schedule (Respect Energy, BGK). Whether this is full financial close.

Sources. financing (gramwzielone.pl); queue (pse.pl)

Tauron BESS Laryszów · Financed, not started · 84 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON BME8 sp. z o.o., NIP 6343042662
Developer
Tauron (in-house)
Also called
BME Laryszów; ME Laryszów (capacity-market unit)

Where

Gmina
not found
Powiat
not found
Voivodeship
śląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
84
Energy, MWh
358
Hours at full power
4.26
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1413
Capacity obligation, MW
49.371
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
80.5
Other capacity contracts
not found
Grant
€24.58m (107,568,872.06 zł). NFOŚiGW FM grant 107,568,872.06 zł (cost 309,830,000 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant (35-45% of cost) plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q4 2028

Evidence

Why this status
NFOŚiGW co-financing secured (energyglobal, 5 Jan 2026) and listed by Tauron among storage investments in execution, "early stage" (H1 2026 report, gramwzielone 24 Sep 2026). No construction reported.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
By unit name and Tauron SPV; four-hour equivalent 80.5 MW.
Where sources disagree
none recorded
Still missing
Site, gmina, connection point and voltage (Tauron, Tauron queue by station code). Construction start. Supplier/EPC (Tauron tenders). Coordinates.

Sources. status (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); mwh (gramwzielone.pl); cm (ure.gov.pl)

Tauron hybrid Ogrodzieniec (BESS part) · Financed, not started · 55 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON Zielona Energia sp. z o.o.
Developer
Tauron (in-house)
Also called
IH Ogrodzieniec; ME Ogrodzieniec

Where

Gmina
Ogrodzieniec
Powiat
not found
Voivodeship
śląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
55
Energy, MWh
237
Hours at full power
4.31
Kind
hybrid with Tauron PV (85 MW PV, 140 MW total)
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
€21.64m (94,734,270 zł). NFOŚiGW FM grant 94,734,270.00 zł (cost 210,525,600 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant (35-45% of cost) plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q3 2028

Evidence

Why this status
NFOŚiGW co-financing secured (energyglobal, 5 Jan 2026) and listed by Tauron among storage investments in execution, "early stage" (H1 2026 report, gramwzielone 24 Sep 2026). No construction reported. Tauron says it took investment decisions on three of its four hybrid installations in H1 2026 without naming them.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Site, gmina, connection point and voltage (Tauron, Tauron queue by station code). Construction start. Supplier/EPC (Tauron tenders). Coordinates.

Sources. status (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); mwh (gramwzielone.pl)

Tauron BESS Bałków · Financed, not started · 54 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON Zielona Energia sp. z o.o.
Developer
Tauron (in-house)
Also called
BME Bałków

Where

Gmina
not found
Powiat
not found
Voivodeship
świętokrzyskie
Coordinates
not found
Grid operator
Tauron Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
54
Energy, MWh
242
Hours at full power
4.48
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
€21.24m (92,947,500 zł). NFOŚiGW FM grant 92,947,500.00 zł (cost 206,555,000 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant (35-45% of cost) plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q3 2027

Evidence

Why this status
NFOŚiGW co-financing secured (energyglobal, 5 Jan 2026) and listed by Tauron among storage investments in execution, "early stage" (H1 2026 report, gramwzielone 24 Sep 2026). No construction reported.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Site, gmina, connection point and voltage (Tauron, Tauron queue by station code). Construction start. Supplier/EPC (Tauron tenders). Coordinates.

Sources. status (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); mwh (gramwzielone.pl)

Tauron BESS Dąbrowa Środkowa · Financed, not started · 45 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON Zielona Energia sp. z o.o.
Developer
Tauron (in-house)
Also called
BME Dąbrowa Środkowa

Where

Gmina
not found
Powiat
not found
Voivodeship
dolnośląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
45
Energy, MWh
192
Hours at full power
4.27
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
€17.70m (77,456,250 zł). NFOŚiGW FM grant 77,456,250.00 zł (cost 172,130,000 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant (35-45% of cost) plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q2 2028

Evidence

Why this status
NFOŚiGW co-financing secured (energyglobal, 5 Jan 2026) and listed by Tauron among storage investments in execution, "early stage" (H1 2026 report, gramwzielone 24 Sep 2026). No construction reported.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Site, gmina, connection point and voltage (Tauron, Tauron queue by station code). Construction start. Supplier/EPC (Tauron tenders). Coordinates.

Sources. status (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); mwh (gramwzielone.pl)

Tauron BESS Twardogóra · Financed, not started · 42 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON Zielona Energia sp. z o.o.
Developer
Tauron (in-house)
Also called
BME Twardogóra

Where

Gmina
Twardogóra
Powiat
not found
Voivodeship
dolnośląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
42
Energy, MWh
179
Hours at full power
4.26
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
€16.52m (72,292,500 zł). NFOŚiGW FM grant 72,292,500.00 zł (cost 160,655,000 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant (35-45% of cost) plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q4 2028

Evidence

Why this status
NFOŚiGW co-financing secured (energyglobal, 5 Jan 2026) and listed by Tauron among storage investments in execution, "early stage" (H1 2026 report, gramwzielone 24 Sep 2026). No construction reported.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Site, gmina, connection point and voltage (Tauron, Tauron queue by station code). Construction start. Supplier/EPC (Tauron tenders). Coordinates.

Sources. status (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); mwh (gramwzielone.pl)

Tauron hybrid Stare Bogaczowice I (BESS part) · Financed, not started · 30 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON Zielona Energia sp. z o.o.
Developer
Tauron (in-house)
Also called
IH Stare Bogaczowice I; ME Stare Bogaczowice I

Where

Gmina
Stare Bogaczowice
Powiat
not found
Voivodeship
dolnośląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
30
Energy, MWh
134
Hours at full power
4.47
Kind
hybrid with Tauron PV (28.5 MW PV, 58.5 MW total)
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
€9.10m (39,840,322.99 zł). NFOŚiGW FM grant 39,840,322.99 zł (cost 114,755,000 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant (35-45% of cost) plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q3 2028

Evidence

Why this status
NFOŚiGW co-financing secured (energyglobal, 5 Jan 2026) and listed by Tauron among storage investments in execution, "early stage" (H1 2026 report, gramwzielone 24 Sep 2026). No construction reported. Tauron says it took investment decisions on three of its four hybrid installations in H1 2026 without naming them.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
not found
Where sources disagree
Tauron also holds capacity unit JRM/1399 "ME Stare Bogaczowice 3" (TAURON BME7, 63.121 MW = 103 MW four-hour equivalent), which fits Stare Bogaczowice II (105 MW, no grant), not this project.
Still missing
Site, gmina, connection point and voltage (Tauron, Tauron queue by station code). Construction start. Supplier/EPC (Tauron tenders). Coordinates.

Sources. status (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); mwh (gramwzielone.pl)

Tauron BESS Bytom · Financed, not started · 18 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON BME9 sp. z o.o., NIP 6343042685
Developer
Tauron (in-house)
Also called
BME Bytom; ME Bytom (capacity-market unit)

Where

Gmina
Bytom
Powiat
not found
Voivodeship
śląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
18
Energy, MWh
77
Hours at full power
4.28
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1415
Capacity obligation, MW
10.702
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
17.5
Other capacity contracts
not found
Grant
€6.69m (29,261,250 zł). NFOŚiGW FM grant 29,261,250.00 zł (cost 65,030,000 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant (35-45% of cost) plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q4 2028

Evidence

Why this status
NFOŚiGW co-financing secured (energyglobal, 5 Jan 2026) and listed by Tauron among storage investments in execution, "early stage" (H1 2026 report, gramwzielone 24 Sep 2026). No construction reported.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
By unit name and Tauron SPV; four-hour equivalent 17.5 MW.
Where sources disagree
none recorded
Still missing
Site, gmina, connection point and voltage (Tauron, Tauron queue by station code). Construction start. Supplier/EPC (Tauron tenders). Coordinates.

Sources. status (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); mwh (gramwzielone.pl); cm (ure.gov.pl)

Trześń BESS (PEI PV 03 / Eko Prime) · Financed, not started · 16 MW

Who

Owner
Not confirmed (grant beneficiary PEI PV 03 sp. z o.o.)
Project company
PEI PV 03 sp. z o.o. (KRS/NIP not found)
Developer
not found
Also called
"Magazyn energii TRZEŚŃ 2-3-4" (NFOŚiGW)

Where

Gmina
not found
Powiat
not found
Voivodeship
podkarpackie
Coordinates
not found
Grid operator
not found
Connection, kV
15
Connection point
not found

What

Power, MW
16.25
Energy, MWh
65
Hours at full power
4.00
Kind
standalone (three blocks)
Cells, integrator and builder
EPC Eko Prime Inwestycje; 13 Linyang 5.015 MWh containers; Kehua converters

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
€3.79m (16,577,671.23 zł). NFOŚiGW FM grant 16,577,671.23 zł recommended (cost 47,952,200 zł)
Trader, optimiser or toll
Arbitrage first, balancing after PSE qualification (plan)
Financing
NFOŚiGW grant

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q1 2027

Evidence

Why this status
Gramwzielone 31 Aug 2026 (sponsored): contracted, equipment already at port, commissioning Q1 2027.
Its row in the connection lists
Not matched (PGE Dystrybucja queue not captured).
How the contract was matched
not found
Where sources disagree
Source is sponsored content. Link between Eko Prime's Trześń contract and PEI PV 03's grant is by place name only.
Still missing
Gmina (several villages are called Trześń), owner, connection, construction start.

Sources. equipment (gramwzielone.pl); grant (gov.pl)

CLIP logistics centre BESS near Poznań (EDP) · Financed, not started · 8 MW

Who

Owner
Grupa CLIP (client; ownership model with EDP not stated)
Project company
NFOŚiGW beneficiaries: CLIP Logistyka sp. z o.o., Clip Ubezpieczenia sp. z o.o., STS Logistic sp. z o.o., MB Poznań sp. z o.o. (link to this EDP project inferred)
Developer
EDP Energia Polska
Also called
Four battery systems for Grupa CLIP

Where

Gmina
Swarzędz (from the permit’s parcel)
Powiat
poznański (assumed)
Voivodeship
wielkopolskie
Coordinates
52.39845, 17.12140 (the land parcel of building permit ST-WK-PO/WNIOSEK/25014/2025 in GUNB’s register, placed by GUGiK)
Grid operator
Enea Operator (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
8
Energy, MWh
20
Hours at full power
2.50
Kind
commercial/industrial, behind the meter (four systems of about 2 MW)
Cells, integrator and builder
EDP Energia Polska builds; supplier not named

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
€1.91m (8,345,757 zł). NFOŚiGW FM grants to four CLIP-group companies, about 2.07-2.09 m zł each, 8,345,757 zł together (container BESS with transformer stations, wielkopolskie); link to this project inferred
Trader, optimiser or toll
Own use with about 8 MW of rooftop PV
Financing
NFOŚiGW grants (inferred) plus client/EDP

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Gramwzielone 23 Jul 2026: EDP will build four systems (8 MW / 20 MWh) for CLIP; energy-storage.news 24 Jul 2026 says EDP is deploying them.
Its row in the connection lists
Not matched.
How the contract was matched
not found
Where sources disagree
Four systems of about 2 MW each; only the total is above 1 MW per site if each is 2 MW (not stated).
Still missing
Per-system size, site, whether grants are these systems, construction start (EDP or CLIP).

Sources. status (gramwzielone.pl); edp en (energy-storage.news); grant (gov.pl); site (wyszukiwarka.gunb.gov.pl)

Przeworsk BESS (LC Energia) · Financed, not started · 8 MW

Who

Owner
LC Energia (joint venture of Low Carbon, Evercon and InCommodities)
Project company
Not confirmed (LC ENERGIA 19 sp. z o.o. applied for a grant for ME Wylewa)
Developer
Evercon
Also called
Possibly "Magazyn Energii ME Wylewa", gmina Przeworsk (LC Energia 19 grant application, not funded)

Where

Gmina
Przeworsk
Powiat
przeworski
Voivodeship
podkarpackie
Coordinates
50.05830, 22.51319 (the land parcel of building permit ST-PK-PZ/WNIOSEK/8086/2025 in GUNB’s register, placed by GUGiK)
Grid operator
PGE Dystrybucja (assumed)
Connection, kV
SN
Connection point
own on-site substation, medium-voltage cable connection

What

Power, MW
8
Energy, MWh
16
Hours at full power
2.00
Kind
standalone, front-of-meter, medium voltage
Cells, integrator and builder
EPC Goldbeck Solar Polska (design to commissioning); four battery containers, two PCS units with transformers; suppliers not named

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
NFOŚiGW FM application for ME Wylewa not recommended
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
planned Q2 2026 (not confirmed)
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned turn of Q1/Q2 2027

Evidence

Why this status
Gramwzielone 18 Mar 2026: EPC contract signed, works to start Q2 2026. No later confirmation found.
Its row in the connection lists
PGE Dystrybucja queue not captured.
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Whether works began in Q2 2026 (Goldbeck, Evercon). Project company and exact site.

Sources. status (gramwzielone.pl); grant not recommended (gov.pl); site (wyszukiwarka.gunb.gov.pl)

Tauron BESS Radlna Tarnowiec · Financed, not started · 6 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON BME9 sp. z o.o., NIP 6343042685
Developer
Tauron (in-house)
Also called
BME Radlna Tarnowiec; ME Radlna-Tarnowiec (capacity-market unit)

Where

Gmina
not found
Powiat
not found
Voivodeship
małopolskie
Coordinates
not found
Grid operator
Tauron Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
6
Energy, MWh
not found
Hours at full power
not found
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1398
Capacity obligation, MW
3.567
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
5.8
Other capacity contracts
not found
Grant
€1.82m (7,968,064.60 zł). NFOŚiGW FM grant 7,968,064.60 zł (cost 22,955,000 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant (35-45% of cost) plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q2 2027

Evidence

Why this status
NFOŚiGW co-financing secured (energyglobal, 5 Jan 2026) and listed by Tauron among storage investments in execution, "early stage" (H1 2026 report, gramwzielone 24 Sep 2026). No construction reported.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
By unit name and Tauron SPV; four-hour equivalent 5.8 MW.
Where sources disagree
none recorded
Still missing
Site, gmina, connection point and voltage (Tauron, Tauron queue by station code). Construction start. Supplier/EPC (Tauron tenders). Coordinates.

Sources. status (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); mwh (gramwzielone.pl); cm (ure.gov.pl)

Warzyce BESS (BESS-Group) · Financed, not started · 5 MW

Who

Owner
BESS-Group (investor not otherwise named)
Project company
not found
Developer
BESS-Group
Also called
not found

Where

Gmina
not found
Powiat
jasielski
Voivodeship
podkarpackie
Coordinates
not found
Grid operator
PGE Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
5
Energy, MWh
10
Hours at full power
2.00
Kind
standalone (assumed)
Cells, integrator and builder
ML System+ (design and build, incl. NexuView SCADA/EMS); two identical contracts together about 17.6 m zł net

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Gramwzielone 29 Sep 2026: design-and-build contract signed with ML System+ (treated here as an investment decision); no construction start reported.
Its row in the connection lists
PGE Dystrybucja queue not captured.
How the contract was matched
not found
Where sources disagree
Contract value: "nearly 17.6 m zł net" (body) vs "over 17 m zł" (summary).
Still missing
Owner, financing, connection, schedule (ML System ESPI filing or BESS-Group). Gmina.

Sources. all (gramwzielone.pl)

Niegłowice BESS (BESS-Group) · Financed, not started · 5 MW

Who

Owner
BESS-Group (investor not otherwise named)
Project company
not found
Developer
BESS-Group
Also called
not found

Where

Gmina
not found
Powiat
jasielski
Voivodeship
podkarpackie
Coordinates
not found
Grid operator
PGE Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
5
Energy, MWh
10
Hours at full power
2.00
Kind
standalone (assumed)
Cells, integrator and builder
ML System+ (design and build, incl. NexuView SCADA/EMS); two identical contracts together about 17.6 m zł net

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
not found

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Gramwzielone 29 Sep 2026: design-and-build contract signed with ML System+ (treated here as an investment decision); no construction start reported.
Its row in the connection lists
PGE Dystrybucja queue not captured.
How the contract was matched
not found
Where sources disagree
Contract value: "nearly 17.6 m zł net" (body) vs "over 17 m zł" (summary).
Still missing
Owner, financing, connection, schedule (ML System ESPI filing or BESS-Group). Gmina.

Sources. all (gramwzielone.pl)

Krotoszyn PV-coupled BESS (Ekoenergia Solar 10 / Eko Prime) · Financed, not started · 5 MW

Who

Owner
Not confirmed (grant beneficiary Ekoenergia Solar 10 sp. z o.o.; Eko Prime is the contractor)
Project company
EKOENERGIA SOLAR 10 sp. z o.o. (KRS/NIP not found)
Developer
not found
Also called
"Magazyn energii dla elektrowni fotowoltaicznej Krotoszyn" (NFOŚiGW)

Where

Gmina
Krotoszyn
Powiat
krotoszyński
Voivodeship
wielkopolskie
Coordinates
not found
Grid operator
Energa-Operator
Connection, kV
SN
Connection point
GPZ Krotoszyn Południe

What

Power, MW
5
Energy, MWh
25
Hours at full power
5.00
Kind
co-located with PV (5.897 MW PV in queue row)
Cells, integrator and builder
EPC Eko Prime Inwestycje; Linyang 5.015 MWh containers; Polish bidirectional converter (five 1.25 MVA units)

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
€2.03m (8,888,721 zł). NFOŚiGW FM grant 8,888,721 zł recommended (cost 33,015,667 zł)
Trader, optimiser or toll
not found
Financing
NFOŚiGW grant

When

Connection agreement signed
2023-10-20
Connection date in the agreement
2027-09-30
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q1 2027

Evidence

Why this status
Gramwzielone 31 Aug 2026 (sponsored Eko Prime material): contracted, commissioning Q1 2027. Grant on NFOŚiGW list.
Its row in the connection lists
Energa queue P/21/075976: EKOENERGIA SOLAR 10, GPZ Krotoszyn Południe, SN, MIX, storage 4.9 MW out / 5 MW in, PV 5.897 MW, agreement 2023-10-20, agreed date 2027-09-30. Matched by company (grant) and town.
How the contract was matched
not found
Where sources disagree
Source is sponsored content.
Still missing
Confirm Eko Prime's Krotoszyn contract is the Ekoenergia Solar 10 project (owner). Construction start. Owner group.

Sources. equipment (gramwzielone.pl); grant (gov.pl); queue (cdn-netpr.pl)

Tauron BESS Baranowice · Financed, not started · 3.9 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON BME9 sp. z o.o., NIP 6343042685
Developer
Tauron (in-house)
Also called
BME Baranowice

Where

Gmina
not found
Powiat
not found
Voivodeship
śląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
3.9
Energy, MWh
not found
Hours at full power
not found
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
€1.18m (5,179,241.99 zł). NFOŚiGW FM grant 5,179,241.99 zł (cost 14,922,500 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant (35-45% of cost) plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q4 2028

Evidence

Why this status
NFOŚiGW co-financing secured (energyglobal, 5 Jan 2026) and listed by Tauron among storage investments in execution, "early stage" (H1 2026 report, gramwzielone 24 Sep 2026). No construction reported.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
not found
Where sources disagree
none recorded
Still missing
Site, gmina, connection point and voltage (Tauron, Tauron queue by station code). Construction start. Supplier/EPC (Tauron tenders). Coordinates. Possible capacity unit JRM/1440 "ME Rybnik" (TAURON BME9, 2.317 MW = 3.8 MW four-hour equivalent), not confirmed.

Sources. status (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); mwh (gramwzielone.pl)

Tauron BESS Pilchowice · Financed, not started · 2 MW

Who

Owner
Tauron Polska Energia
Project company
TAURON BME4 sp. z o.o., NIP 6343042745
Developer
Tauron (in-house)
Also called
BME Pilchowice; ME Pilchowice I (capacity-market unit)

Where

Gmina
not found
Powiat
not found
Voivodeship
dolnośląskie
Coordinates
not found
Grid operator
Tauron Dystrybucja (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
2
Energy, MWh
not found
Hours at full power
not found
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
JRM/1403
Capacity obligation, MW
1.226
Contract years
17
First delivery year
2029
Four-hour equivalent, MW
2.0
Other capacity contracts
not found
Grant
€0.58m (2,537,976.13 zł). NFOŚiGW FM grant 2,537,976.13 zł (cost 7,315,000 zł); Tauron secured 537.75 m zł of NFOŚiGW co-financing for 11 projects (reported 5 Jan 2026)
Trader, optimiser or toll
Tauron group
Financing
NFOŚiGW grant (35-45% of cost) plus Tauron

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
planned Q2 2028

Evidence

Why this status
NFOŚiGW co-financing secured (energyglobal, 5 Jan 2026) and listed by Tauron among storage investments in execution, "early stage" (H1 2026 report, gramwzielone 24 Sep 2026). No construction reported.
Its row in the connection lists
Not matched (anonymised Tauron queue).
How the contract was matched
By unit name and Tauron SPV; four-hour equivalent 2.0 MW.
Where sources disagree
none recorded
Still missing
Site, gmina, connection point and voltage (Tauron, Tauron queue by station code). Construction start. Supplier/EPC (Tauron tenders). Coordinates.

Sources. status (gramwzielone.pl); grant (gov.pl); grant signed (energyglobal.com); mwh (gramwzielone.pl); cm (ure.gov.pl)

Luboń BESS (Tavion) · Financed, not started · · MW

Who

Owner
Tavion (Sweden)
Project company
not found
Developer
Tavion
Also called
Tavion sister project to Bydgoszcz

Where

Gmina
Luboń
Powiat
poznański
Voivodeship
wielkopolskie
Coordinates
not found
Grid operator
Enea Operator (assumed)
Connection, kV
not found
Connection point
not found

What

Power, MW
not found
Energy, MWh
not found
Hours at full power
not found
Kind
standalone, front-of-meter
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
Part of Tavion's three-park financing (equity plus debt raised Sept 2026); the 13 Oct article implies financial close for Luboń was still pending

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
due about two weeks after 13 Oct 2026
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
grid connection expected 2027

Evidence

Why this status
Gramwzielone 13 Oct 2026: construction to start within about two weeks; land, grid connection and permits secured. Gramwzielone 15 Sep 2026: three projects (69 MW) financed and to start in 2026.
Its row in the connection lists
Possible Enea queue rows: WA Farm 4 sp. z o.o., Luboń SN, 2 x 10 MW, agreements 2025-12-18 and 2026-01-14 (unconfirmed; matched by town and size).
How the contract was matched
not found
Where sources disagree
Size not published; Bydgoszcz 20 MW plus Luboń plus a third park total 69 MW.
Still missing
MW and MWh, project company, connection point, financial close date, construction start (Tavion).

Sources. status (gramwzielone.pl); financing (gramwzielone.pl); queue (operator.enea.pl)

Third Tavion park (undisclosed site) · Financed, not started · · MW

Who

Owner
Tavion (Sweden)
Project company
not found
Developer
Tavion
Also called
not found

Where

Gmina
not found
Powiat
not found
Voivodeship
not found
Coordinates
not found
Grid operator
not found
Connection, kV
not found
Connection point
not found

What

Power, MW
not found
Energy, MWh
not found
Hours at full power
not found
Kind
standalone (assumed)
Cells, integrator and builder
not found

Money

Capacity unit
not found
Capacity obligation, MW
not found
Contract years
not found
First delivery year
not found
Four-hour equivalent, MW
not found
Other capacity contracts
not found
Grant
not found
Trader, optimiser or toll
not found
Financing
Covered by Tavion's September 2026 debt raise

When

Connection agreement signed
not found
Connection date in the agreement
not found
Building started
not found
Switched on
not found
Qualified for PSE’s balancing
not found
Commercial operation
not found

Evidence

Why this status
Gramwzielone 13 Oct 2026: a third park is financed by the September debt; site, size and schedule not disclosed.
Its row in the connection lists
Not matched.
How the contract was matched
not found
Where sources disagree
Luboń and this park together are 49 MW if Bydgoszcz is 20 MW of the 69 MW total.
Still missing
Everything except owner: site, size, schedule (Tavion).

Sources. status (gramwzielone.pl)

What is known, and what is still missing

For each fact, how many of the batteries in each status have it. The darker the cell, the more complete. Owners, sizes and statuses are near complete; exact sites, building dates, switch-on dates and balancing qualification are the gaps, and most need a person to ask.

FactRunningSwitched onBeing builtFinanced, not startedAll
Owner13 of 1313 of 1412 of 1220 of 2098%
Project company and its KRS or NIP12 of 1313 of 1410 of 1216 of 2086%
Gmina9 of 1312 of 1411 of 1210 of 2071%
Coordinates4 of 136 of 147 of 122 of 2032%
Grid operator13 of 1313 of 1412 of 1218 of 2095%
Connection point11 of 1314 of 149 of 124 of 2064%
Connection voltage7 of 1311 of 1410 of 125 of 2056%
Power13 of 1314 of 1412 of 1218 of 2097%
Energy13 of 1311 of 1412 of 1214 of 2085%
Cells, integrator or builder9 of 138 of 149 of 127 of 2056%
Grant11 of 134 of 147 of 1216 of 2064%
Trader, optimiser or toll13 of 134 of 145 of 1214 of 2061%
Financing11 of 133 of 1411 of 1217 of 2071%
Connection agreement date4 of 135 of 149 of 123 of 2036%
Building start4 of 131 of 1410 of 122 of 2029%
Switch-on date1 of 1313 of 140 of 120 of 2024%
Balancing qualification2 of 131 of 140 of 120 of 205%
Commercial operation, actual or planned11 of 133 of 1412 of 1215 of 2069%

Points to check first

  • Two batteries owe capacity from 1 January 2027 with no sign of building, and no building permit in either name. Battery ESS-1 sp. z o.o. holds 9.2 MW of obligation (JRM/777) and its owner is not known; PKE Pomorze holds 6.65 MW (JRM/774) for a 7.5 MW Hynfra project near Wrocław.
  • Renegia Bulla won capacity for 2026, and none of its batteries is in Tauron’s register. It holds 11 units around Opole, about 50 MW of obligation from 2028, and quarter-long contracts for 50.2 MW in the first and fourth quarters of 2026, which require delivery this year. GUNB’s register shows building permits in its name in Opole, decided on 31 March 2025, and nothing since.
  • PSE’s list of 31 August still shows Turośń Kościelna as an agreement, not as connected, though the plant opened on 30 July and the same row gives 30 July as its delivery start.
  • For three large batteries, PSE’s agreed connection date is years after the planned opening. Gdańsk II is due around the turn of 2027 and 2028 and its PSE date is June 2032; Dzięgielewo’s is March 2030; Ełk runs on a temporary 220 kV connection, and its PSE row is for a later 400 kV connection, dated February 2030.
  • Stary Grodków’s capacity contract is held by Respect Energy, not EDF. URE lists Respect Energy S.A. for JRM/885, which fits the news that Respect Energy now trades the plant. A search by EDF’s name misses it.
  • Tauron’s Proszówek battery does not fit the contract of the company that owns it. The register lists 9.5 MW under FF Park PV sp. z o.o.; the same tax number holds JRM/2150, whose obligation stands for a 55 MW four-hour battery, probably the planned 47 MW Proszówek II.
  • The grid operators’ registers carry errors, kept as published and flagged in each row: a 3.084 MW battery at Bytnica listed with 0.006 MWh, company founding dates given as storage start dates, a nine-digit KRS number, and a start date after the entry date.

Where the sources disagree

Where two sources give different figures, both are kept, in the row and here. The register uses the owner’s own figure unless a grid operator’s register is more recent.

Every disagreement, battery by battery
BatteryWhat differs
Turośń Kościelna BESSPSE queue row is for 294 MW against 200 MW built. The PSE list of 31 Aug 2026 still shows the agreement in force, not "connected", although its delivery start date (30 Jul 2026) has passed. IFC had planned construction completion for June 2026.
Stary Grodków BESSSize: 50 MW / 120 MWh (EDF, gramwzielone, register 120.36 MWh) vs 50 MW / 100 MWh and two-hour duration (gramwzielone 20 Oct 2026). Register installed power 60.192 MW with 50 MW discharge; ESS News says 60 MW installed, 50 MW grid connection. The URE list names Respect Energy, not an EDF company, as capacity supplier.
Nowe Czarnowo I BESS24 MW / 56 MWh (Energix, Axpo, gramwzielone) vs 28 MW (Modo, Apr 2026).
Łozienica BESS9.4 MW / 18.8 MWh (NGEN, press) vs 9.636 MW / 19.272 MWh (Enea register). Modo counts 9.4 MW.
Bystra hybrid BESSGramwzielone (Dec 2022) said it would be connected to the national system after the pilot phase, so its grid status in 2021-2022 is unclear.
Garbce traction BESSEnergy: 1.2 MWh usable (Railway Gazette) vs 1.88 MWh total / 1.5 MWh usable (gramwzielone 15 Jun 2021). Power 5.5 MW (Railway Gazette) vs 5 MW (Railtech).
Herby BESSRegister: 5.04 MW / 10.03 MWh vs 5 MW / 10 MWh. Register start date (28 Jul) is after first-entry date (10 Jul).
Tauron BESS PrzewózRegister: 4.41 MW installed / 4.0 MW discharge / 17.556 MWh, vs 4 MW / 16 MWh in Tauron statements. Register owner is TAURON Ekoenergia, capacity contract holder TAURON BME4. Register lists the site as Rybitwy; Tauron calls it Przewóz (adjacent Kraków districts); matched by Tauron press saying both Kraków units sit on hydro-plant land. Building permit for "BESS Przewóz" (GUNB ST-MA-KR/WNIOSEK/14947/2025) names TAURON BME4 sp. z o.o. as investor; the register lists the battery under TAURON Ekoenergia.
Tauron BESS DąbieRegister: 4.41 MW installed / 4.0 MW discharge / 17.556 MWh vs 4 MW / 16 MWh (Tauron).
Cieszanowice BESSInstalled 3,330 kW but maximum charge/discharge 2,000 kW. Gramwzielone (11 Feb 2026) misprinted it as 33 MW.
Ełk BESSEBRD NTS: 200.6 MW and 842 MWh grid-side vs 200 MW / 800 MWh. EBRD planned commissioning for Sept 2026, IFC for April 2026. PSE queue gives 294 MW and 2030 for the permanent connection.
Nowe Czarnowo II BESS25 MW / 71 MWh (gramwzielone) vs 52 MWh (Energix website, no MW).
Zawiercie BESSRegister: 9.823 MW installed, 8.07 MW discharge, 19.6 MWh.
Tauron BESS Proszówek8 MW / 16 MWh (Tauron, Dec 2025) vs 9.5 MW (Tauron H1 2026) vs 10 MW installed / 8 MW discharge / 20.064 MWh (register). Match of register row "FF Park PV, Grębocice, Kalinówka" to Tauron's "BESS Proszówek (gmina Grębocice, on a PV farm)" is by gmina and timing, not by name.
Tauron BESS Kuźnia RaciborskaRegister: 7.5 MW installed / 6.9 MW discharge / 30.096 MWh; Tauron Dec 2025: 6.9 MW / 28 MWh; NFOŚiGW grant release (energyglobal): 6.9 MW / 30 MWh.
Stawiszyn hybrid PV+BESSStorage figures in the row: discharge 6 MW, charge 2.5 MW, "mw" 5.04.
Września BESSOne-hour battery (5.0 MW / 5.0 MWh). Register KRS has 9 digits.
Bytnica BESSRegister gives 0.006 MWh, which cannot be right for a 3.084 MW battery; energy left blank.
Kunice BESSRegister discharge power 0.995 MW, below 1 MW; installed 2.032 MW.
Goczałkowice-Zdrój BESSDischarge power 0.861 MW.
Dzięgielewo BESSCapacity delivery from 2029 (gramwzielone, ESS News) vs 2030 main auction in URE list. PSE connection date 2030 vs COD 2027/28.
Żarnowiec BESSEnergy: 981 MWh (contract, KPO) vs about 1,020 MWh nominal (H1 2026 report) vs 900 MWh (2024 tender). Power 262 vs 263 MW. Cost 1.555 bn zł gross (contract) vs about 1.3 bn zł (H1 2026 budget).
Gdańsk II BESSPSE agreed connection date 30 Jun 2032 is years after the planned COD (2027/28); a capacity obligation starts 2029.
Mieczysławów BESSCOD: early 2028 (energy-storage.news 2 Oct 2026) vs mid-2028 (gramwzielone 1 Oct 2026, which gives Kamionka early 2028). Energy-storage.news says grants of about 1 bn zł; PKO and gramwzielone say about 280 m zł, which matches the ranking list (282.0 m zł).
Jedwabno BESSConstruction start Feb 2026 (energyglobal) vs March 2026 (ESS News). Axpo deal Jan 2026 (energyglobal) vs Feb 2026 (gramwzielone) vs May 2026 (ESS News).
Trzebinia BESSEnergy: 532 MWh (Columbus 2024) vs 622 MWh (Fluence, DRI) vs 623 MWh (Actis). Power 133 vs 132 MW. Gmina: Columbus 2024 article said gmina Chrzanów; project name and PSE substation (Siersza) point to Trzebinia.
Kamionka BESSCOD differs between sources (see Mieczysławów). PSE agreed delivery date 26 Dec 2026 vs COD 2028.
Lwówek Śląski BESSA reader comment claims the site is in a flood zone and faces local opposition (unverified).
Osiek Jasielski BESSEnergy: 100 MWh (gramwzielone 2024) vs 120 MWh (OX2 2026). "Construction underway" in July 2024 vs investment decision announced June 2026.
Gryfino BESSContract value 1.142 bn zł gross (tender result) vs 1.1 bn zł (H1 report).
Zwartowo III PV + BESSPSE agreement date 2010-05-05 reflects the original wind-farm agreement.
Tauron hybrid Stare Bogaczowice ITauron also holds capacity unit JRM/1399 "ME Stare Bogaczowice 3" (TAURON BME7, 63.121 MW = 103 MW four-hour equivalent), which fits Stare Bogaczowice II (105 MW, no grant), not this project.
Trześń BESSSource is sponsored content. Link between Eko Prime's Trześń contract and PEI PV 03's grant is by place name only.
CLIP logistics centre BESS near PoznańFour systems of about 2 MW each; only the total is above 1 MW per site if each is 2 MW (not stated).
Warzyce BESSContract value: "nearly 17.6 m zł net" (body) vs "over 17 m zł" (summary).
Niegłowice BESSContract value: "nearly 17.6 m zł net" (body) vs "over 17 m zł" (summary).
Krotoszyn PV-coupled BESSSource is sponsored content.
Luboń BESSSize not published; Bydgoszcz 20 MW plus Luboń plus a third park total 69 MW.
Third Tavion parkLuboń and this park together are 49 MW if Bydgoszcz is 20 MW of the 69 MW total.

Left out, and why

A project enters the register only with a dated source for building, a signed supply or building contract, or closed financing. Those with only grid conditions, a grid agreement, a capacity contract or a recommended grant are left out; the most notable are here, to be moved in when that evidence appears.

The 28 projects watched, and why each is left out
ProjectOwnerSize, MW / MWhWhy left out
Kobiernice (Porąbka)EDF + Eurus120 MW / 280 MWhBuilding "about to start" (Jul 2026); opening H2 2027
Tursko WielkieEngie (from R.Power)250 MW / 1,000 MWh (+70/280)Ready to build; building from early 2027
TrębaczewEngie (from Mithra, Futureal)438 / 876Ready to build only in Q4 2026
KozieniceActis (from DRI)112 / 518Ready to build; 95 MW capacity contract from 2028
BaczynaErgy + Eiffel46 / 184Ready to build; opening 2028
Jelenia GóraGoldenPeaks8 / 32Capacity contract only
WolborzGore Street fund40 / 160Acquired; opening Q1 2028; no building reported
SzprotawaPolenergia50 / 101.6Grant given up; no contractor chosen
Lotnisko, Ścieki, Wojciechowo, PelplinPGE372 MWh togetherContractors still being chosen; grants of about 178 m zł
Storage portfolioEneaabout 1.4 GWContractors to be chosen in 2026; building from 2027
13 projectsEnerga Green Developmentup to 119 / 467Grants of 210 m zł; no investment decision reported
Alastor 1–2, Albus 1–2Grenergyabout 32 MW / 135 MWhGrants; contractor chosen March 2026; no building reported
Kowala, RadkowiceQair2 × 200 / 4002029 capacity contracts only
Mościska, Zabrze IIHynfra100 MW, 204 MW2029 capacity contracts only
Seven Krotoszyn unitsMithraabout 1.5 GW four-hour equivalent2030 capacity contracts only
HEP 001/002; RybnikHarmony Energy2 × 200; 200Capacity contracts; Rybnik decision not taken
Ząbkowice, Klikowa, Rzeszówformer Columbus companies (sold to Ruby01A, Oct 2026)80, 63, 202 MWNo building reported
Krosno; second joint-venture projectGreen Capitalup to 220 MW; not disclosedIn development
Jodłowa, Kolno IOX22 × 99.5 / 199In preparation
Malbork, SztumEuropean Energy2 × 42 MW2029 capacity contracts and grid agreements only
Small 2028-delivery unitsEncos, FRV (4), NRG 21, Neo Energy, MEWRO, Claritas, Grand Solar3.7–130 MW of obligationMust deliver from 1 Jan 2028; no building found
Battery ESS-1, PKE Pomorzeunknown; Hynfra/HCMG9.2 and 6.65 MW of obligationSee the points to check
Second Polish projectNGENnot publishedEBRD loan approved; site not named
AdamówkaEko Primeabout 5 MWh, power unknownMay be below 1 MW
Rova Systems projectunnamed10 / 20Investor and site not named
Łagisza, Ostrów Szlachecki, Stare Bogaczowice II, Proszówek II, Opole-Zawada, Mierzyn, IH BytomTauron20–105 MWEarly stage, no grant
Port Polska airportCPK50 MW, two hoursDesign contract only
CisnaPGEabout 2 MWPlanned in 2021; no report it was built

How it was built

Every battery of 1 MW and more in Tauron’s and Enea’s storage registers; the rows marked connected in the four connection lists; then a search for every owner and every capacity contract holder, the storage sections of gramwzielone.pl from May to October 2026 and energy-storage.news back to March 2025, lenders’ disclosures (EBRD, IFC), suppliers’ releases and stock-exchange filings. A status is given only with a dated source: running when a source reports commercial operation or the unit has run for years; switched on when it is connected and powered with no commercial operation reported, which an entry in a storage register shows, since those registers hold connected batteries only; being built when a dated source says building has started; financed when a supply or building contract is signed or financing has closed, and for Tauron alone, a secured grant with Tauron’s statement that the project is in progress. Each battery is matched to its connection row and its capacity unit by tax number, company name, or for Tauron, whose list withholds names, by substation code and size, marked inferred. Money in euros at the ECB rate of 20 October 2026, 4.3768 zł, with złoty in brackets.

Sources: Tauron Dystrybucja and Enea Operator, storage registers under art. 43g of the Energy Law; PSE, Energa-Operator, Enea Operator and Tauron Dystrybucja, connection lists under art. 7 ust. 8l; URE, final results of the capacity auctions for 2027 to 2030 and the quarterly auctions for 2026 and 2027; NFOŚiGW, the ranking list of the storage grant call, 10 December 2025; and the owners’, lenders’, suppliers’ and press sources linked in each battery. PGE Dystrybucja’s area is the weakest: its site could not be read from a data centre.