Circle area is the gigawatts asked for in the municipality

814 municipalities, every one with at least one request, drawn where Terna places them. Click a circle for its figure and its five stages.

Italy · Terna Econnextion · requests at 31 August 2026

Puglia and Sicilia hold 43% of the queue. One municipality, Brindisi, has asked for 13.3 GW, more than 12 of Italy’s 20 regions.

Terna publishes every request to connect storage to the Italian transmission grid, by municipality, by technology and by how far along it is. 290 GW is asked for across 3,460 applications in 814 municipalities. Only 10.5 GW has reached a signed contract, the stage the decree of 8 September 2026 protects. The Italy page reads the same register as tables.

Asking to connect290GW
Stand-alone batteries259GW
Contract signed10.5GW · 4%
Municipalities814

Showing the whole register. Filter by region, stage or technology, or search a place.

How far along the requests are

Terna sorts every request into five stages. Nearly all of the queue sits in the first four. The last stage, a signed contract, is the one the new rule leaves alone.

Solution issued, not yet acceptedSTMG issued: connection solution issued, not yet accepted by the applicant47.6 GW
Solution acceptedSTMG accepted: connection solution accepted85.0 GW
Under assessmentProject under assessment61.4 GW
ClearedProject cleared: nulla osta85.3 GW
Contract signedSTMD or contract: final solution or contract signed10.5 GW

The decree of 8 September 2026 ends first come, first served. Capacity is reserved only for a project that holds its permit, and connection solutions already issued lose effect within fifteen days of the regulator’s measures unless the works behind them are validated, authorised or built.

Every municipality in the register

Largest first. Click a row to centre the map there. Terna prints each figure to the nearest 10 MW, so the rows add to slightly more than the total.

MunicipalityProvinceRegionGWApplicationsSigned
BrindisiBrindisiPuglia13.291010.01
Chiaramonte GulfiRagusaSicilia4.3332—
GalatinaLeccePuglia3.96330.50
TroiaFoggiaPuglia3.8635—
RotelloCampobassoMolise3.7639—
TuscaniaViterboLazio3.68400.26
MelfiPotenzaBasilicata3.59260.52
CerignolaFoggiaPuglia3.19350.10
ButeraCaltanissettaSicilia2.84430.01
BeneventoBeneventoCampania2.76280.22
BanziPotenzaBasilicata2.6723—
CataniaCataniaSicilia2.66200.02
RamaccaCataniaSicilia2.60390.01
Castelluccio dei SauriFoggiaPuglia2.57220.10
San SeveroFoggiaPuglia2.48240.17
FoggiaFoggiaPuglia2.43390.09
Montalto di CastroViterboLazio2.3918—
Priolo GargalloSiracusaSicilia2.34230.14
SassariSassariSardegna2.31390.31
TarquiniaViterboLazio2.2712—
UtaCagliariSardegna2.1917—
Cancello Ed ArnoneCasertaCampania2.15260.44
OstigliaMantovaLombardia2.14140.25
LarinoCampobassoMolise2.1222—
Ascoli SatrianoFoggiaPuglia2.06290.09
By region
RegionGWShare
Puglia76.326%
Sicilia48.217%
Sardegna20.97%
Basilicata20.17%
Lombardia18.46%
Lazio17.66%
Campania17.16%
Emilia-Romagna13.55%
Piemonte12.74%
Calabria8.53%
Toscana7.83%
Molise7.63%
Veneto7.53%
Friuli-Venezia Giulia5.72%
Umbria3.11%
Abruzzo2.01%
Marche1.71%
Trentino-Alto Adige0.80%
Liguria0.20%

Liguria, Trentino-Alto Adige carry under 1 GW each, and Valle d'Aosta has no request at all.

What changed since last month
The first comparison arrives with the October readTerna updates the register monthly and we read it on the 5th. From then on this section, and the “What changed” view of the map, show every municipality whose figure moved: capacity that arrived, capacity that moved between stages, and capacity that left.
  • Capacity that moved to a signed contract
  • Municipalities that entered or left the register
  • The largest rises and falls, by region
What is not published, and why

Terna does not publish the applicant’s name, the size of a single request or the connection point. The decree orders them onto Terna’s Portale Terra; no date is set. The operating fleet by site is not published either, so no ratio of paper to built is drawn for Italy. Requests to the distribution grids are held by the distributors and are not in this register.

Source: Terna, Econnextion, the embedded report at dati.terna.it, read with the report’s own export function on 29 September 2026. Totals are the figures Terna’s charts print; the municipality rows are Terna’s underlying export. Region boundaries from ISTAT. Nothing on this page is modelled. What you may do with it.