BatteryStatusMunicipalityMWMWhOwner’s date
Eskilstuna (BW ESS and Ingrid)OperatingEskilstuna20·10 October 2024
Varberg (BW ESS and Ingrid)OperatingVarberg202010 October 2024
Vimmerby (BW ESS and Ingrid)OperatingVimmerby20·10 October 2024
Katrineholm (BW ESS and Ingrid)OperatingKatrineholm20·10 October 2024
Sandviken (BW ESS and Ingrid)OperatingSandviken20·10 October 2024
Värnamo (BW ESS and Ingrid)OperatingVärnamo20·10 October 2024
Falköping (BW ESS and Ingrid)OperatingFalköping16·10 October 2024
Karlskrona (BW ESS and Ingrid)OperatingKarlskrona16·10 October 2024
Gävle (BW ESS and Ingrid)OperatingGävle12·10 October 2024
Vaggeryd (BW ESS and Ingrid)OperatingVaggeryd11·10 October 2024
Västerås (BW ESS and Ingrid)OperatingVästerås11·10 October 2024
Mjölby (BW ESS and Ingrid)OperatingMjölby8·10 October 2024
Falkenberg (BW ESS and Ingrid)OperatingFalkenberg··10 October 2024
Sala (BW ESS and Ingrid)OperatingSala··10 October 2024

Ellevio Energy Solutions

Behind it, as the sources state it: Ellevio.

BatteryStatusMunicipalityMWMWhOwner’s date
OrmestaOperatingÖrebro40402025
MoraOperatingMora4040June 2026
SöderalaOperatingSöderhamn40402025
HanhalsOperatingKungsbacka1515May 2024
LindomeOperatingMölndal1515May 2024
GrumsOperatingGrums10102023

Neoen

BatteryStatusMunicipalityMWMWhOwner’s date
Isbillen Power ReserveOperatingSollefteå94942025
Storen Power ReserveOperatingRagunda525217 June 2024

Vattenfall

BatteryStatusMunicipalityMWMWhOwner’s date
Bruzaholm (beside the wind farm)OperatingEksjö3838December 2025
Hjuleberg (beside the wind farm)OperatingFalkenberg30352024
Höge väg (beside the wind farm)OperatingKristianstad25292025
Uppsala (Vattenfall)OperatingUppsala5202020

Ånge Storage Solutions AB

Behind it, as the sources state it: WOOD & Company Renewables Sub-Fund and Delta Capacity.

BatteryStatusMunicipalityMWMWhOwner’s date
Ånge BESSOperatingÅnge7016023 June 2026

Flower

BatteryStatusMunicipalityMWMWhOwner’s date
BredhällaOperatingUppvidinge42·August 2024
PajkölenNo word since its date·40802025
Kungälv (Flower)OperatingKungälv15·21 August 2024

Ingrid Capacity and Locus Energy

BatteryStatusMunicipalityMWMWhOwner’s date
Göteborg (Ingrid and Locus)OperatingGöteborg24·2025
Lerum (Ingrid and Locus)OperatingLerum20202025
Rättvik (Ingrid and Locus)OperatingRättvik121224 September 2025
Falköping (Ingrid and Locus)OperatingFalköping···
Tuve (Ingrid and Locus)Being builtGöteborg··2026
Lidköping (Ingrid and Locus)Being builtLidköping··2026
Götene (Ingrid and Locus)Being builtGötene··2026

Centrica

BatteryStatusMunicipalityMWMWhOwner’s date
RommeOperatingBorlänge2020April 2026
BullerforsenOperating·2020April 2026

Axpo

BatteryStatusMunicipalityMWMWhOwner’s date
Filipstad (Axpo)No word since its dateFilipstad25·2024
Elektra, LandskronaOperatingLandskrona202012 February 2024

Polar Capacity and Stockholm Exergi

BatteryStatusMunicipalityMWMWhOwner’s date
Haninge (Polar Capacity)OperatingHaninge20·October 2023

Varberg Energi

BatteryStatusMunicipalityMWMWhOwner’s date
TvååkerOperatingVarberg11··

Jönköping Energi

BatteryStatusMunicipalityMWMWhOwner’s date
Torsvik, JönköpingOperatingJönköping101023 May 2025

Primrock

BatteryStatusMunicipalityMWMWhOwner’s date
Falkenberg (Primrock)OperatingFalkenberg5.4··

Fortum

BatteryStatusMunicipalityMWMWhOwner’s date
Forshuvud (beside the hydro plant)OperatingBorlänge56.22019
Landaforsen (beside the hydro plant)Operating····

Hydro

BatteryStatusMunicipalityMWMWhOwner’s date
Vetlanda (Hydro)OperatingVetlanda4.5··

Mölndal Energi

BatteryStatusMunicipalityMWMWhOwner’s date
Riskulla, MölndalOperatingMölndal44.4January 2026

Owner not stated

BatteryStatusMunicipalityMWMWhOwner’s date
Humlestaden, Göteborg (reused car batteries)OperatingGöteborg2.82.6July 2023
Hallstahammar hydropower station batteryOperatingHallstahammar·8·
Grycksbo paper mill batteryNo word since its dateFalun··2025
Munkedal paper mill batteryNo word since its dateMunkedal··2025

Skellefteå Kraft

BatteryStatusMunicipalityMWMWhOwner’s date
Båtfors (beside the hydro plant)Operating·2.54.4November 2024

E.ON

BatteryStatusMunicipalityMWMWhOwner’s date
E.ON Malmö batteryOperatingMalmö11·

Jämtkraft

BatteryStatusMunicipalityMWMWhOwner’s date
Granboforsen (beside the hydro plant)Operating·112021
Hissmofors (beside the hydro plant)No word since its dateKrokom·152024

Ingrid Capacity

Behind it, as the sources state it: Mirova (equity investor).

BatteryStatusMunicipalityMWMWhOwner’s date
HorsarydAnnouncedKarlshamn1002002028
Vaggeryd (Ingrid, 100 MW)AnnouncedVaggeryd1004002028
Karlshamn, Duveryd (70 MW)No word since its dateKarlshamn70·2024
Karlshamn pilot (reused bus batteries)No word since its dateKarlshamn3·2023

SENS

BatteryStatusMunicipalityMWMWhOwner’s date
Hallsberg (SENS)AnnouncedHallsberg50··
Katrineholm (SENS)AnnouncedKatrineholm50··
Motala (SENS)AnnouncedMotala···

OX2

BatteryStatusMunicipalityMWMWhOwner’s date
Fageråsen (beside the wind farm)AnnouncedMalung-Sälen502092027
NäsbyholmAnnouncedSkurup45··

Volvo Group

BatteryStatusMunicipalityMWMWhOwner’s date
Volvo Mariestad energy parkAnnouncedMariestad702602027

Polar Structure

BatteryStatusMunicipalityMWMWhOwner’s date
Boden (Polar Structure)No word since its dateBoden501002024

Nuvve

BatteryStatusMunicipalityMWMWhOwner’s date
Nuvve and OMNIA first batteryAnnounced·50752026

ib vogt

BatteryStatusMunicipalityMWMWhOwner’s date
Emmaboda EnergiparkAnnouncedEmmaboda40·2028

Mälarenergi

BatteryStatusMunicipalityMWMWhOwner’s date
Mälarenergi battery park at the Västerås power stationBeing builtVästerås30602026

Öresundskraft

BatteryStatusMunicipalityMWMWhOwner’s date
Åkerslundsverket, ÄngelholmNo word since its dateÄngelholm20·2024

RES and SCR

BatteryStatusMunicipalityMWMWhOwner’s date
Alingsås (RES and SCR)No word since its dateAlingsås20·2024

Rabbalshede Kraft

BatteryStatusMunicipalityMWMWhOwner’s date
Femstenaberg (beside the wind farm)No word since its dateStrömstad20202025

Vasa Vind

BatteryStatusMunicipalityMWMWhOwner’s date
Vasa Vind wind farm battery, StrömsundNo word since its dateStrömsund20202024

Ilmatar

BatteryStatusMunicipalityMWMWhOwner’s date
Knihult (beside the solar farm)No word since its date·20·2025

Tekniska verken

BatteryStatusMunicipalityMWMWhOwner’s date
Tekniska verken, Mjölby truck charging parkNo word since its dateMjölby442024

Monsson Energy AB

BatteryStatusMunicipalityMWMWhOwner’s date
Eskilstuna (Monsson)No word since its dateEskilstuna·60·
Härryda (Monsson)AnnouncedHärryda·20·

Hylte Paper

BatteryStatusMunicipalityMWMWhOwner’s date
Hylte Paper battery parkOperatingHylte·42December 2024

CA Batteribalans

BatteryStatusMunicipalityMWMWhOwner’s date
CA Batteribalans, LerumNo word since its dateLerum·28April 2025

Falu Energi & Vatten

BatteryStatusMunicipalityMWMWhOwner’s date
Falu Energi & Vatten, FalunOperatingFalun·12December 2024

Nordic Solar

BatteryStatusMunicipalityMWMWhOwner’s date
Nordic Solar, SödertäljeBeing builtSödertälje·18·

Nybro Energi

BatteryStatusMunicipalityMWMWhOwner’s date
Nybro EnergiNo word since its dateNybro·12·

Uniper

BatteryStatusMunicipalityMWMWhOwner’s date
Edsele (beside the hydro plant)OperatingSollefteå··2021
Lövön (beside the hydro plant)Operating···2021
Bodum (beside the hydro plant)Operating···2022
Fjällsjö (beside the hydro plant)Operating···2022