Sweden · the named batteries
Grums
Operating, 10 MW · 10 MWh, in Grums (SE3), owned by Ellevio Energy Solutions. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 10 MW |
| Capacity | 10 MWh |
| Duration | 1.0 hours |
| Status | Operating, as of 4 June 2024 |
| Owner’s date | 2023, actual |
| Municipality | Grums |
| Bidding zone | SE3, Stockholm |
| Placed on the map | at Grums, the seat of its municipality (GeoNames) |
Who is behind it
| Owner | Ellevio Energy Solutions |
| Ultimate owner | Ellevio |
| Developer | Ellevio Energy Solutions |
| Built by | Alfen (TheBattery Elements) |
Not published anywhere we have found: traded by, cells.
What the sources say
Ellevio's first grid battery, 2023. Alfen gives 10 MW and 10 MWh; energi.se (May 2023) and Energy-Storage.news give 11.9 MWh. Alfen's figure is used.
Evidence and sources
- name, municipality, owner, parent, developer, builder, power, capacity, bidding zone, status: alfen.com/en/news/alfen-partners-with-ellevio-energy-solu…
From the owners’, developers’ and builders’ own releases and the press, read by Vitreous. Svenska kraftnät publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in each reserve market is on the markets page, for the market as a whole. List id SE-B006.