Latvia’s transmission operator lists 2,405 MW of standalone batteries asking to connect. 225 MW of it is being built.
Battery storage on the transmission grid. The connection table of AST (Augstsprieguma tīkls), read 14 November 2026.
AST, Latvia’s transmission operator, publishes one table of every connection being installed or changed on its grid: who asked, how many megawatts, where on the grid, and how far the work has gone. A connection moves through AST’s steps in order. AST first prepares its technical requirements and sends them, then an agreement is concluded, then come design, construction and acceptance into operation. This page reads the table and counts the batteries in it.
Half of the battery megawatts have an agreement and have not started building
Each bar is one of AST’s steps, for standalone batteries only. AST lists every one of them on the service it calls “ierobežojamais”, which means the connection can be limited. The table gives megawatts and no megawatt hours, so nothing here says how long a battery can run.
Added up by Vitreous from AST’s table of 14 November 2026. The sum, 2,405 MW, is the figure AST’s own chart gives for storage on that service.
The three batteries being built
| Holder | MW | Where on AST’s grid |
|---|---|---|
| Liepaja ESS, SIA | 100 | Grobiņa substation |
| BESS 7, SIA | 65 | Džūkste substation |
| Jaukta Jauda, SIA | 60 | line 208 "Ogre – TEC2", a new substation on the line |
The 12 with an agreement concluded
| Holder | MW | Where on AST’s grid |
|---|---|---|
| BESS 2, SIA | 300 | line 322 "Viskaļi - Brocēni", a new substation on the line |
| BESS 6, SIA | 300 | line 355 "Aizkraukle – Valmiera", a new substation on the line |
| Enery Latvia, SIA | 90 | line 117 and line 118 "Bauska – Nīzere and Iecava – Stelpe", a new substation on the line |
| BESS 4, SIA | 75 | Platene substation |
| Ventspils BESS, SIA | 75 | Ventspils substation |
| Enery Latvia, SIA | 60 | line 190 "Viļāni – Rēzekne", a new substation on the line |
| Enery Latvia, SIA | 60 | line 296 "Līvāni – Līksna", a new substation on the line |
| RE elektriba, SIA | 60 | Imanta substation |
| Vertius, SIA | 50 | Dagda substation |
| EPP Daugavpils, SIA | 45 | line 133 "Daugavpils – Dagda", a new substation on the line |
| Enery Latvia, SIA | 45 | line 292 "Špoģi – Preiļi", a new substation on the line |
| Enery Latvia, SIA | 40 | line 294 "Krustpils – Viļāni", a new substation on the line |
The place is AST’s own description: a named substation, or the numbered line a new substation will be built on. AST gives no coordinates, so this page has no map yet.
Who holds the queue
Nordic Storage Systems, SIA holds the most, 400 MW in one battery. AST names the company on the application, which is often a project company, so a group with several companies appears on several lines.
| Holder, as AST writes it | Batteries | MW | Furthest step reached |
|---|---|---|---|
| Nordic Storage Systems, SIA | 1 | 400 | Technical requirements sent |
| BESS 2, SIA | 1 | 300 | Agreement concluded |
| BESS 6, SIA | 1 | 300 | Agreement concluded |
| Enery Latvia, SIA | 5 | 295 | Agreement concluded |
| Monta Spico, SIA | 1 | 200 | Technical requirements sent |
| Melderi wind, SIA | 1 | 120 | Technical requirements sent |
| Liepaja ESS, SIA | 1 | 100 | Construction |
| Utilitas Wind, SIA | 1 | 100 | Technical requirements being prepared |
| BESS 4, SIA | 1 | 75 | Agreement concluded |
| Ventspils BESS, SIA | 1 | 75 | Agreement concluded |
| BESS 7, SIA | 1 | 65 | Construction |
| RE elektriba, SIA | 1 | 60 | Agreement concluded |
The 22 holders of a standalone battery connection; the twelve largest are shown. One applicant is a private person and is shown as such. Every project.
Batteries beside solar and wind
AST lists 27 connections that pair a battery with solar or wind, 3,170 MW for the whole connections. The table does not say how much of each is battery. AST’s chart gives the battery share in total only: 1,484 MW inside connections on its constant service, and 200 MW with capacity reserved and 341 MW without on its flexible service.
| Step | Plants | Whole connection, MW |
|---|---|---|
| Technical requirements sent | 5 | 522 |
| Agreement concluded | 4 | 141 |
| Design | 1 | 400 |
| Construction | 8 | 1,270 |
| Acceptance into operation | 9 | 838 |
The 17 solar and wind plants with batteries that are furthest along
These are the connections AST lists as being built or being accepted into operation. AST names the company on the application and the size of the whole connection. Where the owner has published the battery itself, its name and size are in the last column with the address of the release; one of the 17 has been read so far.
| Holder | Kind | Whole connection, MW | Where on AST’s grid | Step | The battery, where its owner names it |
|---|---|---|---|---|---|
| IGN RES DEV2, SIA | Solar with storage | 222 | line 524 "Tume - Imanta", a new substation on the line | Acceptance into operation | Tume battery, 107.2 MW, 214.5 MWh, under constructionIgnitis Renewables, by its own release; matched to this row on place and kind |
| DSE Aizpute Solar, SIA | Solar with storage | 200 | line 425 "Grobiņa - Ventspils", a new substation on the line | Acceptance into operation | · |
| SPV Kurzeme, SIA | Solar with storage | 110 | line 198 "Zilupe - Dagda", a new substation on the line | Acceptance into operation | · |
| Baltic Biorefinery Group, SIA | Solar with storage | 100 | Krustpils substation | Acceptance into operation | · |
| MAX SOLAR, SIA | Solar with storage | 60 | Barkava substation | Acceptance into operation | · |
| Rapsoil, SIA | Wind with storage | 60 | line 162A "Grobiņa – Lauma – Zaļā Birze", a new substation on the line | Acceptance into operation | · |
| Baltazar, SIA | Solar with storage | 46 | Brocēni substation | Acceptance into operation | · |
| Sunly Land Solar 1, SIA | Solar and wind with storage | 40 | line 175 "Valmiera - Aloja", a new substation on the line | Acceptance into operation | · |
| TCK, SIA | Wind with storage | 0 | Tārgale substation | Acceptance into operation | · |
| PurpleGreen Energy B, SIA | Solar with storage | 400 | line 309 "Veļikoreckaja - Rēzekne", a new substation on the line | Construction | · |
| DSE Lazas Solar, SIA | Solar and wind with storage | 275 | line 425 "Grobiņa - Ventspils", a new substation on the line | Construction | · |
| Sunly Land Solar 2, SIA | Solar with storage | 200 | line 323 "Brocēni – Grobiņa", a new substation on the line | Construction | · |
| SIA “Lode Wind” | Wind with storage | 130 | line 502 "TEC-2 - Kilingi Nomme", a new substation on the line | Construction | · |
| SNG Solar Latvia, SIA | Solar with storage | 100 | Bolderāja II substation | Construction | · |
| ib vogt BrocēnI, SIA | Solar with storage | 70 | Brocēni substation | Construction | · |
| Birznieki Industrial Solutions, SIA | Solar with storage | 60 | line 241 "Bišuciems - Olaine", a new substation on the line | Construction | · |
| Verdia Wind, SIA | Wind with storage | 35 | Pope substation | Construction | · |
Who else is asking for the grid
Batteries share AST’s table with solar and wind farms, data centres, hydrogen plants and the distribution operator. The megawatts are AST’s, for every row whatever its step and whether or not capacity is reserved.
| Kind of connection | Rows | MW |
|---|---|---|
| Solar with storage | 20 | 2,551 |
| Battery storage | 26 | 2,405 |
| Data centre | 11 | 1,975 |
| Hydrogen production | 3 | 1,299 |
| Wind | 11 | 1,246 |
| Solar and wind | 4 | 410 |
| Solar | 5 | 391 |
| User, other | 6 | 366 |
| Distribution operator | 12 | 358 |
| Solar and wind with storage | 2 | 315 |
| Wind with storage | 5 | 305 |
| Heat supply | 2 | 76 |
| Hydro | 2 | 30 |
| User | 1 | 10 |
| Wood processing | 1 | 10 |
| Hybrid, other | 3 | 0 |
20 rows that AST gives in megavolt-amperes, most of them the distribution operator’s substations, are left out of this table and are in the CSV.
What is not here, and why
Dates, because AST’s table gives none: not when a request was made, nor when an agreement was concluded. A map, because the table gives a place in words and no coordinates. The battery’s share of a solar or wind connection. How long any battery can run. Batteries already running, batteries on the distribution grid of Sadales tīkls, and what a battery earns. And daily changes: AST’s page refuses automated reads, so it is read through a browser by hand, and the history begins with the copy of 14 November 2026.
Source: AST’s page “Pieslēgumu ierīkošanas un atļautās slodzes izmaiņu statuss”, read 14 November 2026 from the page’s own Latvian text and checked row by row. The holders, megawatts, places, steps and services are AST’s; the English words for them are ours and AST’s Latvian is kept beside them in the CSV.