Vitreous LabsEnergy transparency
Latvia · AST’s connection table

Latvia’s transmission operator lists 2,405 MW of standalone batteries asking to connect. 225 MW of it is being built.

2,405 MWin 26 standalone batteries in AST’s connection table, at every step from first papers to construction
1,200 MWin 12 batteries with a connection agreement concluded and building not yet begun
225 MWin three batteries under construction
4,430 MWof storage planned in all, by AST’s own chart, counting the batteries inside solar and wind connections

Battery storage on the transmission grid. The connection table of AST (Augstsprieguma tīkls), read 14 November 2026.

AST, Latvia’s transmission operator, publishes one table of every connection being installed or changed on its grid: who asked, how many megawatts, where on the grid, and how far the work has gone. A connection moves through AST’s steps in order. AST first prepares its technical requirements and sends them, then an agreement is concluded, then come design, construction and acceptance into operation. This page reads the table and counts the batteries in it.

Every battery project in the table

Half of the battery megawatts have an agreement and have not started building

Each bar is one of AST’s steps, for standalone batteries only. AST lists every one of them on the service it calls “ierobežojamais”, which means the connection can be limited. The table gives megawatts and no megawatt hours, so nothing here says how long a battery can run.

Technical requirements being prepared2 batteries150 MWTechnical requirements sent9 batteries830 MWAgreement concluded12 batteries1,200 MWConstruction3 batteries225 MW

Added up by Vitreous from AST’s table of 14 November 2026. The sum, 2,405 MW, is the figure AST’s own chart gives for storage on that service.

The three batteries being built

HolderMWWhere on AST’s grid
Liepaja ESS, SIA100Grobiņa substation
BESS 7, SIA65Džūkste substation
Jaukta Jauda, SIA60line 208 "Ogre – TEC2", a new substation on the line

The 12 with an agreement concluded

HolderMWWhere on AST’s grid
BESS 2, SIA300line 322 "Viskaļi - Brocēni", a new substation on the line
BESS 6, SIA300line 355 "Aizkraukle – Valmiera", a new substation on the line
Enery Latvia, SIA90line 117 and line 118 "Bauska – Nīzere and Iecava – Stelpe", a new substation on the line
BESS 4, SIA75Platene substation
Ventspils BESS, SIA75Ventspils substation
Enery Latvia, SIA60line 190 "Viļāni – Rēzekne", a new substation on the line
Enery Latvia, SIA60line 296 "Līvāni – Līksna", a new substation on the line
RE elektriba, SIA60Imanta substation
Vertius, SIA50Dagda substation
EPP Daugavpils, SIA45line 133 "Daugavpils – Dagda", a new substation on the line
Enery Latvia, SIA45line 292 "Špoģi – Preiļi", a new substation on the line
Enery Latvia, SIA40line 294 "Krustpils – Viļāni", a new substation on the line

The place is AST’s own description: a named substation, or the numbered line a new substation will be built on. AST gives no coordinates, so this page has no map yet.

Who holds the queue

Nordic Storage Systems, SIA holds the most, 400 MW in one battery. AST names the company on the application, which is often a project company, so a group with several companies appears on several lines.

Holder, as AST writes itBatteriesMWFurthest step reached
Nordic Storage Systems, SIA1400Technical requirements sent
BESS 2, SIA1300Agreement concluded
BESS 6, SIA1300Agreement concluded
Enery Latvia, SIA5295Agreement concluded
Monta Spico, SIA1200Technical requirements sent
Melderi wind, SIA1120Technical requirements sent
Liepaja ESS, SIA1100Construction
Utilitas Wind, SIA1100Technical requirements being prepared
BESS 4, SIA175Agreement concluded
Ventspils BESS, SIA175Agreement concluded
BESS 7, SIA165Construction
RE elektriba, SIA160Agreement concluded

The 22 holders of a standalone battery connection; the twelve largest are shown. One applicant is a private person and is shown as such. Every project.

Batteries beside solar and wind

AST lists 27 connections that pair a battery with solar or wind, 3,170 MW for the whole connections. The table does not say how much of each is battery. AST’s chart gives the battery share in total only: 1,484 MW inside connections on its constant service, and 200 MW with capacity reserved and 341 MW without on its flexible service.

StepPlantsWhole connection, MW
Technical requirements sent5522
Agreement concluded4141
Design1400
Construction81,270
Acceptance into operation9838

The 17 solar and wind plants with batteries that are furthest along

These are the connections AST lists as being built or being accepted into operation. AST names the company on the application and the size of the whole connection. Where the owner has published the battery itself, its name and size are in the last column with the address of the release; one of the 17 has been read so far.

HolderKindWhole connection, MWWhere on AST’s gridStepThe battery, where its owner names it
IGN RES DEV2, SIASolar with storage222line 524 "Tume - Imanta", a new substation on the lineAcceptance into operationTume battery, 107.2 MW, 214.5 MWh, under constructionIgnitis Renewables, by its own release; matched to this row on place and kind
DSE Aizpute Solar, SIASolar with storage200line 425 "Grobiņa - Ventspils", a new substation on the lineAcceptance into operation·
SPV Kurzeme, SIASolar with storage110line 198 "Zilupe - Dagda", a new substation on the lineAcceptance into operation·
Baltic Biorefinery Group, SIASolar with storage100Krustpils substationAcceptance into operation·
MAX SOLAR, SIASolar with storage60Barkava substationAcceptance into operation·
Rapsoil, SIAWind with storage60line 162A "Grobiņa – Lauma – Zaļā Birze", a new substation on the lineAcceptance into operation·
Baltazar, SIASolar with storage46Brocēni substationAcceptance into operation·
Sunly Land Solar 1, SIASolar and wind with storage40line 175 "Valmiera - Aloja", a new substation on the lineAcceptance into operation·
TCK, SIAWind with storage0Tārgale substationAcceptance into operation·
PurpleGreen Energy B, SIASolar with storage400line 309 "Veļikoreckaja - Rēzekne", a new substation on the lineConstruction·
DSE Lazas Solar, SIASolar and wind with storage275line 425 "Grobiņa - Ventspils", a new substation on the lineConstruction·
Sunly Land Solar 2, SIASolar with storage200line 323 "Brocēni – Grobiņa", a new substation on the lineConstruction·
SIA “Lode Wind”Wind with storage130line 502 "TEC-2 - Kilingi Nomme", a new substation on the lineConstruction·
SNG Solar Latvia, SIASolar with storage100Bolderāja II substationConstruction·
ib vogt BrocēnI, SIASolar with storage70Brocēni substationConstruction·
Birznieki Industrial Solutions, SIASolar with storage60line 241 "Bišuciems - Olaine", a new substation on the lineConstruction·
Verdia Wind, SIAWind with storage35Pope substationConstruction·

Who else is asking for the grid

Batteries share AST’s table with solar and wind farms, data centres, hydrogen plants and the distribution operator. The megawatts are AST’s, for every row whatever its step and whether or not capacity is reserved.

Kind of connectionRowsMW
Solar with storage202,551
Battery storage262,405
Data centre111,975
Hydrogen production31,299
Wind111,246
Solar and wind4410
Solar5391
User, other6366
Distribution operator12358
Solar and wind with storage2315
Wind with storage5305
Heat supply276
Hydro230
User110
Wood processing110
Hybrid, other30

20 rows that AST gives in megavolt-amperes, most of them the distribution operator’s substations, are left out of this table and are in the CSV.

What is not here, and why

Dates, because AST’s table gives none: not when a request was made, nor when an agreement was concluded. A map, because the table gives a place in words and no coordinates. The battery’s share of a solar or wind connection. How long any battery can run. Batteries already running, batteries on the distribution grid of Sadales tīkls, and what a battery earns. And daily changes: AST’s page refuses automated reads, so it is read through a browser by hand, and the history begins with the copy of 14 November 2026.

Source: AST’s page “Pieslēgumu ierīkošanas un atļautās slodzes izmaiņu statuss”, read 14 November 2026 from the page’s own Latvian text and checked row by row. The holders, megawatts, places, steps and services are AST’s; the English words for them are ours and AST’s Latvian is kept beside them in the CSV.