Vitreous LabsEnergy transparency
Finland · the change ledger

Since 11 October 2026: 14 batteries entered, 500 MW, 38 other changes.

No Finnish body publishes a list of batteries, so the list this site keeps by hand from the owners’ own releases is copied whenever it changes, and the difference between one copy and the one before is printed, battery by battery. Beneath it, Fingrid’s own count: every hour in which its total moved, which is a battery arriving on the grid, unnamed. Nothing here is inferred from the numbers; it is one capture against the one before, identifier by identifier. The column headed "our reading" is a rule, and it can be wrong.

2captures held across 1 list, the oldest from 11 October 2026
14batteries entered a list, 500 MW
0left a list
38other changes that moved something; 3 more were respellings or refilings

By month

MonthEnteredMW enteredLeftOther changesRespelt or refiled
October 2026145000383

Where this can be wrong

The list is kept by hand, so a battery enters it when a source is found, which can be long after the battery started; the date of a change here is the date the list changed, never the date the battery did. The owner’s stated date is on each battery’s page. A step in Fingrid’s count is dated to the hour, but Fingrid adds a unit to its model up to a month before it starts and names nothing, so no step is matched to a name on this site.

The whole ledger as a CSV.

The list of batteries their owners name

A battery enters when a source first names it and leaves only if a source says it was dropped; a change of status is the owner’s own word, read from a later release. The list is kept by hand, so a copy is taken whenever it changes, and the difference printed. 2 captures held, 11 October 2026 to 12 October 2026.

12 October 2026, against 11 October 2026

55 changes, 3 of them the publisher respelling or refiling something.

BatteryWhat changedFromToMWOur reading
Sandås BESS (Fu-Gen)
FI-B075
entered··125new to this list
Mehtäperä battery storage (FRV Nivala Oy)
FI-B065
entered··100new to this list
Pälli battery storage (Fortum)
FI-B066
entered··60new to this list
Pahkakoski BESS
FI-B071
entered··50new to this list
Icecreek Energy II portfolio (five sites, western Finland)
FI-B076
entered··34new to this list
Relletinsuo battery storage and substation
FI-B064
entered··30new to this list
Kyrö BESS (Fu-Gen)
FI-B074
entered··30new to this list
Alvar BESS
FI-B070
entered··25new to this list
Västervik–Riskula BESS
FI-B072
entered··25new to this list
Ypyrinneva BESS
FI-B073
entered··12new to this list
Kouvola (Usva Energia)
FI-B077
entered··5new to this list
Paarmasuontie energy storage, Raahe
FI-B069
entered··1.9new to this list
NW JBox container battery, Raahe (Kivipelto, Romuperäntie)
FI-B067
entered··1.2new to this list
NW JBox container battery, Raahe (Järvelä I, Mutalantie 97)
FI-B068
entered··1.2new to this list
Haapajärvi (Pysäysperä)
FI-B020
stated date2027 mid2027 H1125changed
AKKU One
FI-B023
builderDelta Capacity (EPC management); NYAB (balance of plant); Sungrow (battery system); Rejlers; Ampner; GreenPowerMonitorDelta Capacity (EPCM); NYAB (balance of plant); Sungrow (battery system); Rejlers (technical support); Ampner (grid studies); GreenPowerMonitor (EMS and SCADA)125changed
Kärppiö / Karppio (Delta Capacity)
FI-B024
builderSungrow (battery system); NEPower (balance of plant, substation); Despro (engineering)Sungrow (BESS technology); NEPower (balance of plant, electrification, substation); Despro (owner's engineering)125changed
Nala Vuolijoki
FI-B025
builderDespro (EPC management); Destia (balance of plant); Sungrow (battery system)Despro (EPCM); Destia Oy (balance of plant); Sungrow (BESS technology)125changed
Kannisto wind farm BESS (OX2)
FI-B026
power, MW110125125up by 15
Kannisto wind farm BESS (OX2)
FI-B026
capacity, MWh220250125up by 30
Kukonkylä
FI-B040
ownerEnlight Renewable EnergyEnlight Renewable Energy Ltd125a respelling; the thing is the same
Korkeamaa wind farm BESS (OX2)
FI-B022
power, MW125110110down by 15
Korkeamaa wind farm BESS (OX2)
FI-B022
capacity, MWh250220110down by 30
Teuva (Prime Capital, from Usva Energia)
FI-B043
ownerPrime CapitalPrime Green Energy Infrastructure Fund II, managed by Prime Capital AG100changed
Pyhäjoki (Enlight, from Usva Energia)
FI-B044
ownerEnlight Renewable EnergyEnlight Renewable Energy Ltd100a respelling; the thing is the same
Alapitkä battery park
FI-B045
ownerre:cap global investors (FP Lux European Battery Storage Fund)re:cap global investors (FP Lux European Battery Storage fund)95a respelling; the thing is the same
Alapitkä battery park
FI-B045
municipality·Lapinlahti95changed
Alapitkä battery park
FI-B045
builderSMA Altenso (EPC incl. grid and MV/HV); SMA Solar (grid-forming inverters)SMA Altenso (full EPC: balance of plant, medium to high voltage, grid integration); SMA (Sunny Central Storage UP-S grid-forming inverters)95changed
Alapitkä battery park
FI-B045
stated date2027 H2202795changed
Pyhäsalmi BESS (SENS and Dovre)
FI-B047
namePyhäsalmi (SENS)Pyhäsalmi BESS (SENS and Dovre)85changed
Pyhäsalmi BESS (SENS and Dovre)
FI-B047
ownerPrime Capital (inferred, see notes)Prime Capital AG renewable energy fund (Pyhäsalmi BESS Oy)85changed
Simo, phase 2
FI-B048
statusAnnouncedBeing built70changed
Simo, phase 2
FI-B048
ownerFRV with AMPTank Energy OyFRV with AMP Tank70changed
Simo, phase 2
FI-B048
stated date·202670changed
Uusnivala BESS
FI-B029
ownerL&G NTR Clean Power (Europe) Fund (Uusnivala Energy Storage Oy)L&G NTR Clean Power (Europe) III Fund (Uusnivala Energy Storage Oy)55changed
Uusnivala BESS
FI-B029
stated date·2026 mid55changed
Kauhava (Nala Renewables)
FI-B019
statusOperatingEnergised, commissioning50changed
Kauhava (Nala Renewables)
FI-B019
builderKSBR (construction); Sungrow (22 PowerTitan 2.0 units of 5 MWh)KSBR (construction); Sungrow (22 PowerTitan 2.0 units of 5 MWh); Ramboll (partner)50changed
Kauhava (Nala Renewables)
FI-B019
stated dateby 2026-102026 end50changed
Kalanti BESS
FI-B031
builderSuvic Oy (balance of plant); Sungrow (20 PowerTitan 2.0 units)Suvic Oy (balance of plant); Sungrow (20 PowerTitan 2.0 units, Energy-Storage.news only)50changed
Isokangas (Eco Stor)
FI-B032
ownerÅ Energi (largest share), Farvatn, AmpTank and Eco StorÅ Energi (majority), with Farvatn Capital and Eco-Stor AS; AMP Tank keeps a minority50changed
Isokangas (Eco Stor)
FI-B032
builderEco Stor (build)Eco Stor (build; Energy-Storage.news only)50changed
Pedersöre (Ingrid Capacity)
FI-B050
ownerIngrid Capacity with Mirova investmentIngrid Capacity with Mirova (partnership)45changed
Nurmijärvi (Helen and Evli)
FI-B015
builderNot named (36 container modules); Siemens is operation and management partnerSiemens (technology supplier: electrification, energy management software, lifecycle services); 36 container modules, maker not named40changed
Simo, phase 1
FI-B009
builderSungrow (PowerTitan 1.0 LFP containers)Sungrow (PowerTitan LFP containers)30changed
Ainola BESS (Piiparinmäki wind farm)
FI-B010
ownerNuveen Infrastructure (90%), Ilmatar (10%)Nuveen Infrastructure (majority), Ilmatar (10%)30changed
Ainola BESS (Piiparinmäki wind farm)
FI-B010
municipality·Pyhäntä30changed
Ainola BESS (Piiparinmäki wind farm)
FI-B010
builderAlfen (TheBattery Elements)Ilmatar (constructor); Alfen TheBattery Elements (Energy-Storage.news only)30changed
Valkeakoski (Alpiq)
FI-B014
stated date2025-10-302025-1030changed
Rautavaara (Winda Energy)
FI-B034
builderGAZ GmbH (battery system); Ingeteam (inverters)GAZ Energy (integrated battery); Ingeteam (inverter)30changed
Kellarijanka (UB Renewable Energy Fund)
FI-B051
ownerUB Renewable Energy Fund (majority), part of United BankersUB Renewable Energy Fund (significant majority, bought from AmpTank Finland Oy), part of United Bankers30changed
Rando Grid
FI-B005
ownerJTel Oy and Rando Ventures OyRando Grid Oy, owned by JTel Oy and Rando Ventures Oy5changed
Rando Grid
FI-B005
builderCactos (units built in Kempele); Kaco invertersCactos (supplier and operator; 24 Cactos units made in Kempele); Kaco inverters (ESS News only)5changed
Rando Grid
FI-B005
stated date2025-01-242025-015changed
Batcave (Järvenpää power plant)
FI-B001
stated date2017-032017-03-012changed

Fingrid’s count, hour by hour

Dataset 424, read 16 October 2026; 47 hours in which the count moved since its first reading on 11 March 2026, 47 of them up by 841 MW in all. 14 of the steps are exactly 1.25 MW, the size of one container battery. 3 one-hour readings in which the feed fell to a fraction of the hour before and came straight back are left out as faults. No step is matched to a name, because Fingrid publishes none.

HourMoved, MWCount after, MWOur reading
15 October 2026, 12:00 UTC+342,057a battery, or a batch, added to Fingrid’s model
15 October 2026, 11:00 UTC+8.82,022a battery, or a batch, added to Fingrid’s model
24 September 2026, 14:00 UTC+1.22,013a battery, or a batch, added to Fingrid’s model
24 September 2026, 13:00 UTC+9.92,012a battery, or a batch, added to Fingrid’s model
23 September 2026, 11:00 UTC+5.42,002a battery, or a batch, added to Fingrid’s model
15 September 2026, 12:00 UTC+2.51,997a battery, or a batch, added to Fingrid’s model
14 September 2026, 07:00 UTC+10.01,994a battery, or a batch, added to Fingrid’s model
11 September 2026, 08:00 UTC+3.81,984a battery, or a batch, added to Fingrid’s model
3 September 2026, 08:00 UTC+1321,980a battery, or a batch, added to Fingrid’s model
28 August 2026, 14:00 UTC+1941,848a battery, or a batch, added to Fingrid’s model
28 August 2026, 13:00 UTC+411,655a battery, or a batch, added to Fingrid’s model
18 June 2026, 09:00 UTC+1.21,614a battery, or a batch, added to Fingrid’s model
15 June 2026, 11:00 UTC+3.81,613a battery, or a batch, added to Fingrid’s model
15 June 2026, 10:00 UTC+4.81,609a battery, or a batch, added to Fingrid’s model
11 June 2026, 14:00 UTC+1.21,604a battery, or a batch, added to Fingrid’s model
11 June 2026, 12:00 UTC+1.21,603a battery, or a batch, added to Fingrid’s model
11 June 2026, 09:00 UTC+2.51,602a battery, or a batch, added to Fingrid’s model
11 June 2026, 08:00 UTC+1.21,599a battery, or a batch, added to Fingrid’s model
8 June 2026, 12:00 UTC+1.21,598a battery, or a batch, added to Fingrid’s model
5 June 2026, 12:00 UTC+171,597a battery, or a batch, added to Fingrid’s model
5 June 2026, 07:00 UTC+301,579a battery, or a batch, added to Fingrid’s model
1 June 2026, 10:00 UTC+1.21,549a battery, or a batch, added to Fingrid’s model
1 June 2026, 09:00 UTC+1211,548a battery, or a batch, added to Fingrid’s model
29 May 2026, 08:00 UTC+1.21,427a battery, or a batch, added to Fingrid’s model
29 May 2026, 07:00 UTC+7.21,426a battery, or a batch, added to Fingrid’s model
26 May 2026, 10:00 UTC+1.21,418a battery, or a batch, added to Fingrid’s model
26 May 2026, 07:00 UTC+1.21,417a battery, or a batch, added to Fingrid’s model
26 May 2026, 06:00 UTC+21,416a battery, or a batch, added to Fingrid’s model
25 May 2026, 08:00 UTC+21,414a battery, or a batch, added to Fingrid’s model
25 May 2026, 07:00 UTC+5.81,412a battery, or a batch, added to Fingrid’s model
22 May 2026, 13:00 UTC+231,406a battery, or a batch, added to Fingrid’s model
22 May 2026, 12:00 UTC+2.51,383a battery, or a batch, added to Fingrid’s model
22 May 2026, 11:00 UTC+51,381a battery, or a batch, added to Fingrid’s model
22 May 2026, 10:00 UTC+7.21,376a battery, or a batch, added to Fingrid’s model
22 May 2026, 09:00 UTC+1.21,369a battery, or a batch, added to Fingrid’s model
21 May 2026, 14:00 UTC+2.51,367a battery, or a batch, added to Fingrid’s model
21 May 2026, 10:00 UTC+5.21,365a battery, or a batch, added to Fingrid’s model
18 May 2026, 10:00 UTC+661,360a battery, or a batch, added to Fingrid’s model
13 May 2026, 16:00 UTC+8.81,293a battery, or a batch, added to Fingrid’s model
23 April 2026, 09:00 UTC+131,284a battery, or a batch, added to Fingrid’s model
13 April 2026, 07:00 UTC+1.21,272a battery, or a batch, added to Fingrid’s model
9 April 2026, 13:00 UTC+1.21,271a battery, or a batch, added to Fingrid’s model
23 March 2026, 08:00 UTC+9.91,269a battery, or a batch, added to Fingrid’s model
17 March 2026, 11:00 UTC+181,259a battery, or a batch, added to Fingrid’s model
17 March 2026, 10:00 UTC+181,241a battery, or a batch, added to Fingrid’s model
13 March 2026, 11:00 UTC+1.21,223a battery, or a batch, added to Fingrid’s model
11 March 2026, 17:00 UTC+6.81,222a battery, or a batch, added to Fingrid’s model
05001,0001,5002,0002,500Mar 2026AprMayJunJulAugSepOct+66 MW18 May+121 MW1 Jun+234 MW28 Aug in two hours+132 MW3 Sep1,215 MW, 11 Mar 20262,057 MW16 Oct 2026

The same hours drawn as the line on the Finland page.