Vitreous LabsEnergy transparency
Poland · PSE’s connection queue and the Grid Act

35 GW of the battery projects in PSE’s queue had until 30 October to pay or lapse. That is 178 of the 279 projects in PSE’s last list before the date.

35 GWof storage in PSE’s queue faced 30 October 2026: 178 projects that lapsed unless their holders paid what the Grid Act asks
14 GWin 79 storage projects with a signed connection agreement, 1 of them already delivering
33 GWin 162 projects holding connection conditions and no agreement
588 MWof batteries running or switched on, 27 of them; 2.1 GW more is being built

PSE’s list under art. 7 ust. 8l, the edition of 30 September 2026, read every day from 20 October 2026; 2 editions held. The deadline has passed; the editions after it show what left. Rebuilt on every refresh.

PSE, the Polish transmission system operator, publishes every month a list of every project asking to connect to its grid: the applicant, the substation, the power, the stage and every date. This page reads the storage projects in it. The Grid Act of 13 March 2026 made many of them lapse by law on 30 October 2026 unless their holders paid more, and PSE’s own dates show which were at risk. The first edition after the date will show which stayed.

Open the Atlas   Who holds the queue

35 GW had to pay by 30 October 2026, or leave the queue

Two groups faced the date. 141 projects hold connection conditions issued before the act came into force on 30 April 2026 and have signed no agreement: their conditions lapse unless the holder tops up the advance to 60 złoty a kilowatt, up to 6 million złoty, within six months of that date (article 9). 37 projects signed an agreement before the act with a connection date after 30 April 2029: their agreement expires by law unless the holder lodges a quarter of the new security within the same six months (article 11).

Conditions, no agreement28 GW · 141 projectsAgreements to 2029 and later6.2 GW · 37 projectsRest of the queue21 GW · 101 projects

Counted from the dates in PSE’s list: the date conditions were issued, the date the agreement was signed and the connection date it sets. The act: Ustawa z dnia 13 marca 2026 r. o zmianie ustawy Prawo energetyczne oraz niektórych innych ustaw, Dz.U. 2026 poz. 516, articles 9, 11 and 38. PSE gives 30 October 2026 as the date in its notice of 15 October 2026. A project that paid stays; one that did not has lapsed. Which paid will show in the editions after the date, which this page reads as they come.

The 37 agreements that needed new security by 30 October
Project, as PSE names itApplicantConnection pointDate of that stageAgreed connection dateMW
MEE Zwartowo VRespect Energy Pomerania Sp. z o.o.Choczewo27 February 202631 August 20311,000
MEE SłosinkoPomeranian Energy Sp. z o.o.Żydowo Kierzkowo15 October 202530 September 2029396
MEE UstronieLS4 Sp. z o.o.Czarna4 September 202530 December 2029349
MEE EłkMagazyn EE Ełk Sp. z o.o.Ełk Bis1 February 202228 February 2030294
MEE Gdańsk 2Elektrownia PV 61 Sp. z o.o.Gdańsk Błonia18 March 202531 August 2029250
MEE Tursko WielkieMagazyn Energii Tursko Wielkie Sp. z o.o.Połaniec22 May 202530 June 2032250
MEE SokólePV Lipnica Sp. z o.o.Stanisławów2 January 202615 October 2029225
PV+MEE SajczyceEplant 83 Sp. z o.o.Chełm5 December 202526 May 2031220
MEE LeźnoAarten ES Sp. z o.o.Gdańsk Przyjaźń25 February 202630 June 2029204
MEE KoźleGrand Solar 4 Sp. z o.o.Blachownia12 February 20257 May 2033201
MEE HEP 001HEP1 Sp. z o.o.Ołtarzew11 April 202517 January 2030200
MEE Harmony Energy WielopoleHEP6 Sp. z o.o.Wielopole24 March 202631 January 2032200
MEE Skawina 2Power Reserve Sp. z o.o.Skawina8 October 202531 December 2029200
MEE PawłowiczkiNeo Energia Przykona X Sp. z o.o.Blachownia28 February 20257 May 2033184
PV+MEE Zwartowo III (wcześniej PV Zwartowo; FW Choczewo)Respect Energy Solar Zwartowo Sp. z o.o.Żarnowiec5 May 201010 April 2030184
MEE Kozienice 3Greenvolt Wind 7 Sp. z o.o.Kozienice28 April 202630 November 2030176
MEE KrerowoNeo Energia Przykona IX Sp. z o.o.Kromolice7 July 202531 December 2030138
MEE PłochocinGrenergy Polska Sp. z o.o.Ołtarzew29 April 202631 December 2029126
MEE Ełk Solar Plant 25Solar Plant 25 Sp. z o.o.Ełk Bis15 April 202517 December 2029122
MEE PromnikNeo Energia Przykona VII Sp. z o.o.Kielce13 March 202531 December 2031120
PV+MEE DźbówEplant 90 Sp. z o.o.Joachimów4 September 202526 June 2030107
MEE Grzybowice 2Bess6 Sp. z o.o.Rokitnica29 December 202529 August 2029100
MEE ChałupkiGrand Solar 23 Sp. z o.o.Radkowice13 May 202530 June 202997
MEE MikułowaNeo Energia Przykona XV Sp. z o.o.Mikułowa30 April 202531 December 202997
MEE ZgierzNeo Energia Przykona XII Sp. z o.o.Zgierz12 May 202531 March 203097
MEE+PV Goplan Elana 3FRV Poland I Sp. z o.o.Toruń Elana12 October 202531 October 203181
MEE Konin ŻagańskiEplant 51 Sp. z o.o.Marszów (Żagań)30 May 202510 October 203069
MEE Olecko BisOX2 Green Sp. z o.o.Ełk Bis30 October 202430 June 202959
PV+MEE LubiszynSolar West II Sp. z o.o.Baczyna Systemowa16 June 202516 July 203154
MEE Szczurowa 1Future Bess Sp. z o.o.Klikowa17 July 202531 December 202951
MEE KlonówkaBESS Pelplin Sp. z o.o.Pelplin19 September 202531 March 203151
MEE SarnówEW Pasat Sp. z o.o.Łagisza27 December 202530 September 203151
MEE RadkowiceRSE 10 Sp. z o.o.Radkowice16 October 202531 August 202950
MEE BełchatówNala Renewables 5 Sp. z o.o.Rogowiec9 December 202531 May 202950
PV+MEE Bakałarzewo-GóraSun Energy Projekt Sp. z o.o.Ełk Bis28 April 202630 June 203050
PV+MEE LasociceElektrownia PV Lasocice Sp. z o.o.Nysa7 June 20248 June 203044
MEE Zgierz 1NALA Renewables 6 Sp. z o.o.Zgierz29 April 202631 May 203140
The largest of the 141 conditions that needed a larger advance
Project, as PSE names itApplicantConnection pointDate of that stageMW
MEE ChoczewoQair Polska S.A.Choczewo20 March 20261,000
MEE Piła 1 BESSPV 1030 sp. z o.o.Dunowo19 February 2026590
PV+MEE MieszkowicePVE 185 Sp. z o.o.Baczyna Systemowa23 October 2025502
MEE NiemstówPV 1360 Sp. z o.o.Czarna12 November 2025499
MEE Mithra Bess ŻarnowiecMithra Bess H Sp. z o.o.Żarnowiec31 March 2025432
MEE Mithra Bess KrzemienicaMithra Bess F Sp. z o.o.Krzemienica28 March 2025432
MEE Mithra Bess PłockMithra Bess J Sp. z o.o.Płock28 March 2025432
MEE Mithra Bess SłupskMithra Bess D Sp. z o.o.Krzemienica28 March 2025432
MEE Mithra Bess ŻydowoMithra Bess A Sp. z o.o.Żydowo Kierzkowo28 March 2025432
PV+MEE NiwniceEplant 32 Sp. z o.o.Mikułowa4 August 2025414
MEE KalinowoEplant 36 Sp. z o.o.Łomża Systemowa22 July 2025414
MEE Gniewczyna ŁuńcuckaEplant 58 Sp. z o.o.Jarosław (planowana)18 July 2025414
MEE RogowiecPGE INWEST 25 Sp. z o.o.Rogowiec10 September 2025401
MEE Harmony Energy JarząbkowiceHEP3 Sp. z o.o.Podborze15 December 2025401
PV+FW+MEE BoleszkowiceEE Boleszkowice Sp. z o.o.Dunowo30 July 2025400
PV+MEE Wrocław 4Intelligent Energy Wrocław Sp. z o.o.Trębaczew19 December 2025372
MEE Ostrołęka EEnerga Storage Sp. z o.o.Ostrołęka11 February 2026316
MEE SkowronkowaENERGA Storage Sp. z o.o.Grudziądz Węgrowo23 March 2026316
MEE KopciowiceProjekt-Solartechnik Development Sp. z o.o.Byczyna19 February 2026307
MEE KrzewinaEnergia Przykona XVIII Sp. z o.o.Piła Krzewina18 March 2026305
MEE Stanisławów SKStatkraft Poland Invest 2 Sp. z o.o.Stanisławów2 April 2025304
MEE Kobylin-RogówR.Power Solar Sp. z o.o.Stryków (Dmosin)19 December 2025302
MEE Giełczyn 4Elektrownia PV 106 Sp. z o.o.Łomża Systemowa13 April 2026302
PV+MEE MazewoSzamal Investment Sp. z o.o.Ełk Bis9 September 2025302
MEE Baczyna 3NRG 20 Sp. z o.o.Baczyna Systemowa24 January 2025301
MEE BulkowoCEPV 87 Sp. z o.o.Płock11 July 2025300
MEE CzekanówElektrownia PV 106 Sp. z o.o.Ostrów20 March 2025300
MEE WodnicaElektrownia PV 106 Sp. z o.o.Krzemienica4 March 2025300
MEE Radzanowo-PłockNRG 20 Sp. z o.o.Płock28 October 2024300
MEE Czajków-ALTILIUMAltilium Energy 2 Sp. z o.o.Witonia13 August 2025299
PV+MEE DusznikiEplant 35 Sp. z o.o.Plewiska7 October 2025276
PV+MEE BrzozowaEplant 81 Sp. z o.o.Połaniec1 October 2025276
PV+MEE BrzezinkaSolarfarm Brzezinka Sp. z o.o.Pasikurowice11 August 2025276
MEE MarianowoEplant 73 Sp. z o.o.Morzyczyn22 July 2025276
MEE Wysoka IIA 200 - zm. WPEplant 72 Sp. z o.o.Rożki22 July 2025276
PV+MEE Żydowo IIIEplant 64 Sp. z o.o.Żydowo Kierzkowo17 July 2025276
MEE Plewiska KomornikiLightsource Development Polska Sp. z o.o.Plewiska22 May 2025252
MEE NiwnicaFRV Pomeralia Sp. z o.o.Nysa17 April 2026251
MEE Koryta TorzymBess4 Poland I Sp. z o.o.Baczyna Systemowa22 July 2025246
MEE Jaworzno III 2TAURON Wytwarzanie S.A.Byczyna25 August 2025232

Two more deadlines follow, on building permits

59 agreements, 9.3 GW, were signed between 30 April 2022 and 30 April 2026. They expire unless a final building permit for 80% of the battery’s power and 80% of its energy is notified within 30 months of the act, by 30 October 2028 (article 13). 6 older agreements, 1.5 GW, must show a final building permit within three months (article 14). The act counts those three months from 30 April 2026, but brings article 14 itself into force only six months after publication, so from when they run is disputed, and this page does not choose. 19 of the 59 agreements facing the first of them, 2.6 GW, belong to a company already named in a battery building permit near the site. Every building permit for a battery.

Poland has 65.3 GW of batteries in its grid queues and 11.2 GW with capacity contracts, 2.1 GW being built, and 588 MW running or switched on

One square for every 100 MW. The queue, drawn hollow because it exists only on paper, is standalone batteries with grid offers or signed agreements, from PSE’s national totals. The contracts are the four-hour batteries behind every battery’s capacity obligation for 2027 to 2030. Being built and running are counted battery by battery in the register of every battery. The last row is the reserve product batteries chase most, as PSE buys it each hour.

65.3 GWwith grid offers or agreements11.2 GWholding capacity contracts2.1 GWbeing built588 MWrunning or switched on451 MWof aFRR up PSE buys an hour

Sources: PSE’s national totals of 30 September 2026 (distribution part 30 September 2026); the capacity contracts, unit by unit; the batteries running and being built; PSE’s reserve purchases, the average of the last twelve months.

Across all of Poland’s grids, 65.3 GW of standalone batteries hold grid offers or signed agreements, and the lists read here name 86% of it

Every grid operator must publish its own list of the projects asking to connect, and PSE publishes the national totals. PSE’s list covers its transmission grid; Energa’s, Enea’s and Tauron’s cover most of the distribution grids, at 110 kV and below. PGE Dystrybucja’s site refuses automated reading, and Stoen’s list for Warsaw was not found, so their share is shown by difference.

Grid operatorProjectsGWList dated
PSE, the transmission grid18938.630 September 2026
Enea Operator79912.6no date given; its latest entry is 28 August 2026
Tauron Dystrybucja3974.730 June 2026
PGE Dystrybucja and Stoen Operator, not read·about 9.4by difference
All of Poland, PSE’s national total·65.3distribution 30 September 2026, transmission 30 September 2026

Standalone batteries (type MEE) with connection conditions issued or an agreement signed, at their installed discharge power. PSE’s national totals: Wykaz Zagregowanych Informacji o Przyłączeniach under art. 7 ust. 8n, Table 2. The distribution lists are read row by row from the PDFs each operator publishes; Tauron withholds every applicant’s name, and Enea never states the battery inside its hybrids and often records a battery’s connection only as power drawn from the grid. The national totals and the lists carry different dates, so the comparison is approximate.

The signed agreements peak in 2028 and 2029, and only 1.3 GW is due to connect by the end of 2027

Every connection agreement sets the date the battery is to start taking and giving energy. These are those dates for the 81 agreements that give one, by year, in GW of battery power. A date in an agreement is a plan, not a promise: projects slip, and the Grid Act’s deadlines will end some of them.

01234GW20260.420271.020282.720293.420302.420312.220321.120330.420360.1

PSE’s list (30 September 2026) and Energa’s and Tauron’s lists, the column “data rozpoczęcia dostarczania energii”. 558 signed agreements in the distribution lists give no date, most of Tauron’s and all of Enea’s, so the distribution grids are under-counted here. Every battery project in the four lists as a CSV.

PSE’s own list holds 56 GW of storage in 279 projects

Each project counts at the battery power PSE lists for it, never the whole connection of a hybrid with solar or wind. 12 GW of it is in 81 hybrids.

Connected0.3 GW · 1 projectAgreement signed13 GW · 78 projectsConditions, no agreement33 GW · 162 projectsApplication8.9 GW · 38 projectsRefused, lapsed, withdrawn7.2 GW · 40 projects

PSE S.A., the art. 7 ust. 8l list, edition of 30 September 2026, the rows of type MEE (storage) and MIX (a hybrid with storage), at their storage discharge power. A project whose agreed connection date had come by the edition’s date is counted as connected.

Where the queue is

One circle per project, sized by battery power, at the substation PSE names where OpenStreetMap maps one of that name. Blue has a signed agreement, pale blue has conditions only, grey is an application or has left.

MEE Mątki, 1,295 MWME BESS Choczewo, 1,200 MWME Siedlce, 1,050 MWMEE Choczewo, 1,000 MWMEE Zwartowo V, 1,000 MWMEE Siedlce 1 i 2, 600 MWMEE Piła 1 BESS, 590 MWPV+MEE Mieszkowice, 502 MWPV + ME Solar Ledno, 500 MWMEE Niemstów, 499 MWME BESS Olsztyn, 480 MWMEE Ostrowiec Świętokrzyski, 455 MWMEE Mithra Bess Żarnowiec, 432 MWMEE Mithra Bess Płock, 432 MWMEE Mithra Bess Żydowo, 432 MWMEE Mithra Bess Trębaczew, 432 MWMEE Mithra Bess Baczyna, 432 MWMEE Janówka, 414 MWPV+MEE Niwnice, 414 MWMEE Kalinowo, 414 MWMEE Rybnik, 401 MWMEE Rogowiec, 401 MWMEE Gryfino, 400 MWMEE Dźwierzno, 400 MWMEE Połaniec 2, 400 MWMEE Mątki, 400 MWPV+FW+MEE Boleszkowice, 400 MWPV+ME Besiekierz, 400 MWMEE Słosinko, 396 MWPV+MEE Wrocław 4, 372 MWMEE Środa, 369 MWMEE Ustronie, 349 MWMEE Ostrołęka E, 316 MWMEE Skowronkowa, 316 MWMEE Kartoszyno, 313 MWPV+ME Sajczyce, 308 MWMEE Kopciowice, 307 MWMEE Krzewina, 305 MWMEE Stanisławów SK, 304 MWMEE Kobylin-Rogów, 302 MWMEE Giełczyn 4, 302 MWPV + ME Karsinka II, 302 MWPV + ME Mazewo, 302 MWPV+MEE Mazewo, 302 MWMEE Baczyna 3, 301 MWPV+MEE Komorów, 300 MWMEE Bydgoszcz Zachód, 300 MWMEE Bulkowo, 300 MWMEE Czekanów, 300 MWMEE Radzanowo-Płock, 300 MWMEE Brańszczyk, 300 MWMEE Dzięgielewo, 300 MWMEE Lewin Brzeski, 299 MWMEE Turośń Kościelna, 294 MWMEE Ełk, 294 MWMEE BESS Płock, 288 MWPV+MEE Duszniki, 276 MWPV+MEE Brzozowa, 276 MWPV+MEE Brzezinka, 276 MWMEE Marianowo, 276 MWMEE Wysoka IIA 200 - zm. WP, 276 MWPV+MEE Żydowo III, 276 MWPV+ME Barzkowice, 273 MWMEE Leśniów 1, 273 MWMEE Kartoszyno, 263 MWMEE Elko 1, 259 MWMEE Plewiska Komorniki, 252 MWMEE Niwnica, 251 MWMEE Gdańsk 2, 250 MWMEE Tursko Wielkie, 250 MWMEE Koryta Torzym, 246 MWMEE Mieczysławów, 245 MWMEE Świętoszowice, 234 MWMEE Szczecinek, 233 MWMEE Jaworzno III 2, 232 MWMEE Jaworzno III 4, 232 MWMEE+ODB Kompleks energetyczno-chemiczny, 226 MWMEE Sokóle, 225 MWPV+ME Pieniążkowo, 222 MWME Trzebinia, 220 MWMEE Wróblik Królewski, 220 MWMEE Baczyna 2, 220 MWPV+MEE Sajczyce, 220 MWMEE Stalowa Wola 4, 218 MWMEE Głogówek, 210 MWME Pątnów Pokoje, 210 MWMEE Żagań Bess, 208 MWMEE Żarnowiec, 206 MWMEE Leźno, 204 MWMEE Parnowo, 204 MWMEE Kędzierzyn-Koźle Bess, 204 MWMEE Vivos 10, 204 MWMEE Vivos 2, 204 MWMEE Vivos 4, 204 MWMEE Vortex Energy, 204 MWMEE+FW Prabuty, 204 MWMEE+FW Moryń Cedynia, 204 MWMEE Klikowa 2, 202 MWMEE Żydowo, 202 MWPV+MEE Wrocław, 202 MWMEE Jawiszów Kamienna Góra, 202 MWMEE Wysoka, 202 MWPV+ME Leśniów, 202 MWMEE BESS 2 Ostrów Wielkopolski, 202 MWMEE Wieńkowo, 202 MWPV + ME Gaworzyce, 202 MWMEE Koźle, 201 MWMEE Murat - zm. WP, 201 MWMEE Łomża, 200 MWMEE HEP 002, 200 MWMEE HEP 001, 200 MWMEE Harmony Energy Wielopole, 200 MWMEE Wałbrzych, 200 MWMEE Enea Kozienice, 200 MWMEE Dębno, 200 MWMEE Błonie, 200 MWMEE Pelplin 2000, 200 MWPV+MEE Gębarzów, 200 MWMEE Nakło-BESS, 200 MWPV+MEE Biskupiec, 200 MWMEE Ełk Bess 1, 200 MWMEE Ełk Bess 2, 200 MWMEE Wieprzec, 200 MWMEE Mieczysławów, 200 MWMEE Koluszki, 200 MWMEE Twardowice, 200 MWMEE Brzeźnica, 200 MWMEE Skawina 2, 200 MWMEE Zabrze II, 200 MWMEE Raczkowice, 200 MWMEE Lubin 3 - zm. WP, 199 MWMEE Kaczory, 198 MWMEE Dzierzgoń, 195 MWMEE Żarnowiec 2, 190 MWMEE Krerowo 2, 186 MWPV+ME Zwartowo, 184 MWMEE Pawłowiczki, 184 MWPV+MEE Zwartowo III (wcześniej PV Zwartowo; FW Choczewo), 184 MWPV+ME P.A.M., 181 MWMEE Tarnawa 2, 180 MWMEE Kozienice 3, 176 MWME Olecko Bis, 171 MWMEE+PV+FW Jasna, 170 MWMEE BESS Opole, 170 MWPV+MEE Łęg, 168 MWMEE Czajków, 168 MWMEE BESS Turów, 165 MWPV+MEE Płużnica, 162 MWMEE Podgórze, 160 MWMEE Dołhobyczów, 159 MWMEE BESS Piła Krzewina, 154 MWMEE Ożarów SK, 152 MWMEE Turów, 150 MWMEE Żydowo 2 Solarig, 150 MWMEE Widuchowa 1, 150 MWMEE Średnia Wieś, 150 MWMEE Kąty Wrocławskie, 147 MWPV+ME Biesiekierz Cieszyn, 146 MWME Kozienice, 141 MWPV+ME Parszowice 2, 141 MWMEE Kobiernice, 141 MWMEE Krerowo, 138 MWMEE Trzebinia, 132 MWMEE Środa, 130 MWMEE BESS Plewiska, 126 MWMEE Bess Wyszków, 126 MWMEE Płochocin, 126 MWMEE Strzelce Opolskie, 123 MWMEE Kamionka, 122 MWMEE Ełk Solar Plant 25, 122 MWPark Solarny PEG - ZS, 120 MWMEE Lubsko-Lipinki, 120 MWMEE Kielce SK, 120 MWMEE Kobiernice, 120 MWMEE Promnik, 120 MWMEE Lubiszyn Południe, 119 MWMEE Żagań, 119 MWMEE Żydowo Solarig, 118 MWMEE Jelonki, 116 MWMEE Kozienice, 112 MWPV+ME Spręcowo Sętal, 111 MWME Czerwona Woda 2, 111 MWMEE Starołęcka 1, 110 MWMEE Dunowo, 110 MWMEE GRN Gdańsk, 110 MWPV+MEE Bukowica, 110 MWMEE Buk, 110 MWPV+MEE Dźbów, 107 MWMEE Micigózd - Piekoszów, 105 MWMEE Zwonowice, 103 MWMEE Kromolice 1, 103 MWMEE Wyszków Turzyn, 102 MWMEE Plewiska, 101 MWMEE Micigózd, 101 MWMEE Wólka Czarnińska - zm. WP, 101 MWMEE Janiszewko, 101 MWMEE Nowy Konik (uprzednio MEE Miłosna EDPR), 101 MWMEE Świebodzice, 101 MWMEE Grzybowice 2, 100 MWMEE Mościska BESS, 100 MWFW+MEE Bełżyce, 100 MWPV+MEE Świdwin, 100 MWMEE Turośń Kościelna 2, 100 MWMEE Łobez, 100 MWMEE Jenków, 100 MWPV+MEE Gołdap, 100 MWPV+MEE Łobez, 100 MWMEE Kamionka (Turek 1 etap 1), 100 MWPV+MEE Wisznice, 100 MWMEE Kosów Mniejszy, 100 MWMEE Chęciny, 100 MWMEE Polanów, 100 MWPV+ME Giżkowo, 100 MWMEE Kolno 1, 100 MWMEE Żukówka, 99 MWMEE Lipno, 97 MWMEE Chałupki, 97 MWMEE Mikułowa, 97 MWMEE Zgierz, 97 MWMEE Ostrowiec, 97 MWMEE BESS Zgierz Solarig, 96 MWMEE Żydowo Polanów, 96 MWMEE 4045 Chmielów 2S, 95 MWPV+ME Łagów, 90 MWPV+ME Łagów, 90 MWPV+ME Łagów, 90 MWMEE+PV Lotnisko (za pośrednictwem istniejącej infrastrutkury FW Osieki), 89 MWPV+ME Godetowo, 88 MWMEE BESS Siedlce 1.S 4078, 88 MWPV+MEE Dobroń - zm. WP, 87 MWMEE Struga, 87 MWMEE Kraków 2, 85 MWMEE+PV Goplan Elana 3, 81 MWMEE Wysoka-Południe, 81 MWME Reptowo 70/280, 81 MWFW+PV+ME Margonin, 80 MWPV+ME Glinki, 80 MWMEE Ząbkowice, 80 MWMEE Lyski, 75 MWMEE Gronówko, 71 MWMEE Połaniec, 70 MWPV+MEE Rusocin 2, 69 MWMEE Łośnice, 69 MWMEE Konin Żagański, 69 MWPV+MEE Tarnawa, 66 MWMEE Klikowa, 63 MWMEE Mil 2, 61 MWPV+MEE Łukaszów, 61 MWPV+ME Rybnik, 60 MWMEE Plewiska Gołuski, 60 MWMEE Pabianice, 59 MWMEE Olecko Bis, 59 MWPV+MEE Olecko Bis, 58 MWPV+MEE Lubiszyn, 54 MWMEE Legacz (dawniej Stanisławów), 52 MWMEE Leśniów 2, 51 MWMEE 504 Plewiska, 51 MWMEE Stalowa Wola 3, 51 MWMEE Szczurowa 1, 51 MWMEE Klonówka, 51 MWMEE Sarnów, 51 MWPV+ME Łambinowice 2, 50 MWMEE Radkowice, 50 MWMEE Bełchatów, 50 MWPV+MEE Bakałarzewo-Góra, 50 MWMEE Platerówka, 49 MWMEE Łubowo, 48 MWMEE Turośń Kościelna, 48 MWPV+MEE Czerwona Woda, 47 MWMEE Baczyna, 46 MWPV+MEE Lubin, 45 MWPV + ME Solarpark Polanów, 45 MWPV+MEE Recław, 44 MWPV+MEE Lasocice, 44 MWMEE Zgierz 1, 40 MWPV + ME Niedźwiedź, 40 MWPV+MEE Złotogłowice, 39 MWPV+ME Projekt Widuchowa, 34 MWMEE Kotowice Pęcław, 31 MWMEE Rabowice, 28 MWMEE Żarnowiec 3, 25 MWPV+MEE Iłowa, 20 MWPV+MEE Mikolin, 15 MWBALTIC SEACZECHIASLOVAKIAUKRAINEBELARUSLITHUANIARUSSIAWarsawKrakówŁódźWrocławPoznańGdańskSzczecinBydgoszcz
ConnectedAgreement signedConditions issued, no agreementApplicationRefused, lapsed, withdrawn or endedTransmission lines, 220 kV and up, OpenStreetMap

283 of 319 projects placed.

Connection pointProjectsMW askedMW with an agreement
Choczewo33,2001,000
Baczyna Systemowa142,852651
Żydowo Kierzkowo122,631396
Olsztyn Mątki62,6020
Krzemienica61,9310
Ełk Bis111,857525
Żarnowiec91,767536
Siedlce Ujrzanów31,738600
Dunowo61,5500
Leśniów81,3350
Płock41,332300
Czarna51,095349
Open the Atlas, every project on the map What changed between PSE’s editions

Who holds the queue

PSE names every applicant. Most are project companies, one per site; the company register (KRS) says who stands behind each, and who owns the pipeline traces every one to its group.

ApplicantGroupMW agreedMW in conditionsProjects
Respect Energy Pomerania Sp. z o.o.Respect Energy1,00001
Magazyn EE Siedlce Sp. z o.o.Greenvolt (KKR)60001
Mithra Bess E Sp. z o.o.ENGIE43201
Mithra Bess C Sp. z o.o.Mithra Energy / Barrallier Limited43201
PGE Inwest 22 Sp. z o.o.PGE40001
Pomeranian Energy Sp. z o.o.Proland Group sp. z o.o.39601
LS4 Sp. z o.o.Kudła Fundacja Rodzinna W Organizacji34901
NRG 20 Sp. z o.o.Sagittarius Power Pte. Ltd.3007514
Elektrownia PV 96 Sp. z o.o.R.Power30002
Magazyn EE Ełk Sp. z o.o.Greenvolt (KKR)29401
PGE Inwest 14 Sp. z o.o.PGE2633132
Enea Wytwarzanie Sp. z o.o.Enea25901
Elektrownia PV 61 Sp. z o.o.R.Power25001
Magazyn Energii Tursko Wielkie Sp. z o.o.ENGIE25001
Grand Solar 23 Sp. z o.o.Equinor24702
Who owns the pipeline, traced through the company register Every applicant and every project

A megawatt in PSE’s reserves was paid up to about €411,000 over the last twelve months

PSE buys most of its balancing capacity the day before, hour by hour, in seven products, and publishes every price. One megawatt accepted in every hour of its aFRR up procurement would have been paid about €411,000 from November 2025 to October 2026. PSE buys a few hundred megawatts of each product; the queue holds tens of gigawatts of batteries. Every product, month by month.

173 batteries hold capacity contracts for 2027 to 2030, about 11.2 GW of four-hour batteries

URE’s auction results never say which units are batteries, so every published total is an estimate. Counted unit by unit, batteries hold 5,063 MW of de-rated obligation, which stands for about 11,157 MW of four-hour batteries. Every unit, its holder and why it counts as a battery.

315 MW of batteries runs commercially, 273 MW more is switched on, and 2.1 GW is being built

No Polish body lists the batteries running or being built, so this site keeps the list: 59 batteries of 1 MW and more, each with its owner, site, grid, size, suppliers, contracts and dates, and the source for every fact. Of the capacity obligation batteries owe from January 2028, 65% is held by a battery visibly running or being built.

BatteryOwnerPlaceMWMWhStatus
Turośń KościelnaGreenvolt Power (Greenvolt Group, owned by KKR)Turośń Kościelna, podlaskie200800Running
Stary GrodkówEDF power solutions (EDF group)Skoroszyce, opolskie50120Running
Nowe Czarnowo IEnergix Group (Energix Polska)Gryfino, zachodniopomorskie2456Running
ŁozienicaNGEN (NGEN Energetske rešitve d.o.o., Slovenia)Goleniów, zachodniopomorskie9.419Running
Bystra hybridEnerga (Orlen group)pomorskie627Running
Garbce tractionPGE Energetyka Kolejowa (formerly PKP Energetyka)dolnośląskie5.51.2Running
HerbyR.PowerHerby, śląskie510Running
Tauron PrzewózTauron Polska EnergiaKraków, małopolskie416Running
Tauron DąbieTauron Polska EnergiaKraków, małopolskie416Running
EłkGreenvolt Power (Greenvolt Group, owned by KKR)Ełk, warmińsko-mazurskie200800Switched on
Nowe Czarnowo IIEnergix Group (Energix Polska)Gryfino, zachodniopomorskie2571Switched on
ZawiercieNot foundZawiercie, śląskie9.8220Switched on
Tauron ProszówekTauron Polska EnergiaGrębocice, dolnośląskie9.520Switched on
Tauron Kuźnia RaciborskaTauron Polska EnergiaKuźnia Raciborska, śląskie6.928Switched on
Stawiszyn hybrid PV and batteryTK Powerwielkopolskie5.04·Switched on
WrześniaR.Power (Elektrownia PV-numbered companies are R.Power SPVs; ownership of PV 99 not confirmed)Września, wielkopolskie5.015.01Switched on
SiedlceGreenvolt Power (KKR)Zbuczyn (from the permit’s parcel), mazowieckie6002,400Being built
DzięgielewoR.PowerStara Biała (from the permit’s parcel), mazowieckie3001,200Being built
ŻarnowiecPGE Polska Grupa EnergetycznaKrokowa (Kartoszyno, from PSE row name; confirm), pomorskie262981Being built
Gdańsk IIR.PowerGdańsk, pomorskie2501,000Being built
MieczysławówNorthland Power (bought from Greenvolt, Nov 2025)Ślesin (from the permit’s parcel), wielkopolskie200800Being built
JedwabnoR.PowerLubicz, kujawsko-pomorskie150300Being built
TrzebiniaDRI (DTEK Renewables International, DTEK group); Actis to acquire on completion (announced 6 Oct 2026)Trzebinia (name) or Chrzanów (Columbus 2024 article): see disagreements, małopolskie133622Being built
KamionkaNorthland Power (bought from Greenvolt, Nov 2025)wielkopolskie100400Being built
Lwówek ŚląskiGreen Capital S.A. and Prime Capital AG (50% of this project), joint ventureLwówek Śląski, dolnośląskie80320Being built
Osiek JasielskiOX2Osiek Jasielski, podkarpackie50120Being built
BydgoszczTavion (Sweden)Bydgoszcz, kujawsko-pomorskie2040Being built
PuławyRelyAssets (Spain)Puławy, lubelskie416Being built
Every battery running, switched on, being built or financed, with everything found

What is not here, and why

A meter on any battery, because PSE publishes output only for its largest units and no battery is among them, and ENTSO-E shows none. Any instruction PSE gives a battery, because PSE publishes balancing only in totals. PGE Dystrybucja’s and Stoen’s connection lists, not yet read: PGE’s site sets a picture test for every visitor, and Stoen’s bars automated reading.

Sources: PSE S.A., the art. 7 ust. 8l list and market data. Tauron Dystrybucja and Enea Operator, storage registers under art. 43g. Owners’ releases as linked. The Grid Act, Dz.U. 2026 poz. 516. Positions from OpenStreetMap.