Vitreous LabsEnergy transparency
Germany · the change ledger

Since 10 October 2026: 75 batteries entered, 857 MW, 8 left, 218 other changes.

The Bundesnetzagentur publishes the whole Marktstammdatenregister as a daily export. It is read once a week for the storage units of a megawatt or more, every export is kept, and the difference printed, unit by unit. Nothing here is inferred from the numbers; it is one capture against the one before, identifier by identifier. The column headed "our reading" is a rule, and it can be wrong.

3captures held across 1 list, the oldest from 10 October 2026
75batteries entered a list, 857 MW
8left a list
218other changes that moved something; 2 more were respellings or refilings

By month

MonthEnteredMW enteredLeftOther changesRespelt or refiled
November 20267182272042
October 2026435114·

Where this can be wrong

The register is filled in by operators and checked by grid operators, so an entry can change because an operator corrected it, because the grid operator did, or because the plant changed; the register does not say which, and the "grid operator check" column is the nearest thing to a signal. A unit that falls below a megawatt leaves this ledger without leaving the register. The first export is a baseline, not a report.

The whole ledger as a CSV.

The Marktstammdatenregister, batteries of a megawatt and up

A unit enters when it is registered at a megawatt or more and leaves when it is deleted from the register or falls below a megawatt; the register is read daily, and a planned unit becoming an operating one shows as a change of status. 3 captures held, 10 October 2026 to 24 November 2026.

24 November 2026, against 15 October 2026

284 changes, 2 of them the publisher respelling or refiling something.

BatteryWhat changedFromToMWOur reading
ECO POWER THREE C
SEE928453677290
entered··100new to this list
ECO POWER THREE B
SEE932200559470
entered··100new to this list
ROE II
SEE919327282153
entered··55new to this list
ROE I
SEE998384244380
entered··55new to this list
green flexibility BESS Obergünzburg gmbh
SEE909980876691
entered··40new to this list
Attic-Speicher
SEE994964655898
entered··25new to this list
GMH BESS Dillfeld I
SEE982953486851
entered··23new to this list
BESS WWS Invest 3 GmbH & Co. KG
SEE945262782694
entered··22new to this list
SpeicherWerk Münsterland - BESS Borken
SEE901301865483
entered··22new to this list
SpeicherWerk Münsterland - BESS Coesfeld
SEE985364294466
entered··22new to this list
Ems
SEE968860612095
entered··21new to this list
trlyr23 Westerstede BESS
SEE997145078134
entered··20new to this list
BESS-Breitenbich
SEE943426085704
entered··18new to this list
S4 Energy Burhafe
SEE905976745989
entered··17new to this list
Batterie Hansapark
SEE990187259363
entered··16new to this list
trlyr 17
SEE900913716572
entered··15new to this list
Großbatteriespeicher Alfeld
SEE918385807070
net power, MW99.3137.5138up by 38.2
ECO POWER THREE A
SEE901024459440
net power, MW300.0100.0100down by 200
ECO POWER THREE A
SEE901024459440
nameECO POWER THREEECO POWER THREE A100changed
ECO POWER THREE A
SEE901024459440
planned date2027-02-012027-02-19100changed
Kyon-42 Battery Storage
SEE954807594395
planned date2026-10-312027-01-1858changed
Kyon-38 Battery Storage West
SEE989748439733
planned date2026-10-312026-12-1451changed
Kyon-38 Battery Storage Ost
SEE914862084439
planned date2026-10-312026-12-1449changed
SGE Duisburg-Walsum
SEE940654841652
planned date2026-10-312026-11-3047changed
BESS Manheimer Bucht 1
SEE968876748832
statusIn PlanungIn Betrieb40changed
BESS Manheimer Bucht 1
SEE968876748832
planned date2026-10-01·40changed
BESS Manheimer Bucht 1
SEE968876748832
commissioning date·2026-10-2140changed
BESS Kölsa Batteriespeicher
SEE999375739335
planned date2026-10-312027-01-2940changed
BESS Schlön
SEE930343596277
planned date2026-10-012026-12-0136changed
Großbatteriespeicher
SEE935898651709
operatorHermann Braig EntsorgungsfachbetriebHermann Braig Papierrohstoffe e.K.30changed
Batteriespeicher JT Energy Systems GmbH
SEE905820921729
net power, MW25.029.730up by 4.7
Döbrichau BESS
SEE932375452705
net power, MW45.028.028down by 17
Döbrichau BESS
SEE932375452705
planned date2026-12-222026-11-1128changed
BESS Neubrandenburg
SEE983429560709
planned date2026-10-052026-12-3126changed
Großbatteriespeicher Irsingen
SEE958262376688
operatorHermann Braig EntsorgungsfachbetriebHermann Braig Papierrohstoffe e.K.25changed
Kyon-26 Battery Storage
SEE908517074623
planned date2026-10-082026-11-1624changed
Großbatteriespeicher Irsingen
SEE941340244788
operatorHermann Braig EntsorgungsfachbetriebHermann Braig Papierrohstoffe e.K.20changed
Großbatteriespeicher Schwenningen
SEE962311804787
operatorHermann Braig EntsorgungsfachbetriebHermann Braig Papierrohstoffe e.K.20changed
Batteriespeicher Knetzgau
SEE974972238993
planned date2026-08-032026-11-1320changed
PV-Batteriespeicher Overath 1
SEE974247615207
operatorenlop GmbHa natural person20changed
TEP Vesta GmbH & Co KG (Speicher)
SEE935322911287
statusIn PlanungIn Betrieb19changed
TEP Vesta GmbH & Co KG (Speicher)
SEE935322911287
net power, MW22.619.219down by 3.4
TEP Vesta GmbH & Co KG (Speicher)
SEE935322911287
planned date2026-09-18·19changed
TEP Vesta GmbH & Co KG (Speicher)
SEE935322911287
commissioning date·2026-10-0519changed
BESS Immenstadt
SEE953815288937
grid operator checkunder checkchecked16changed
BESS UW Heessen
SEE978423585698
statusIn PlanungIn Betrieb16changed
BESS UW Heessen
SEE978423585698
planned date2026-10-23·16changed
BESS UW Heessen
SEE978423585698
commissioning date·2026-10-2316changed
BESS Leer Nord
SEE902226350702
operatorSWO Energie Leer Nord GmbHVoltuna Leer Nord GmbH15changed
BESS Leer Nord
SEE902226350702
grid operator checkunder checkchecked15changed

The 50 largest changes are shown. The other 234, each of 15 MW or less, are in the CSV: 55 entered, 7 left, 172 other changes.

15 October 2026, against 10 October 2026

19 changes.

BatteryWhat changedFromToMWOur reading
UW_Visbek
SEE943914294755
entered··15new to this list
green flexibility BESS Ettringen gmbh
SEE959904987606
entered··10new to this list
ACDC ZW8
SEE926242887332
entered··5new to this list
BESS UW Vierlinden
SEE966521903452
entered··5new to this list
Speicher Kühbach IV - P24-064
SEE997803743657
left··3.4gone from this list
BESS Strübbel
SEE963514247548
grid operator checkunder checkchecked50changed
BESS UW Heessen
SEE978423585698
planned date2026-09-302026-10-2316changed
Pfaffenklinge Speicher
SEE912580321386
grid operator checkcheckedunder check8.8changed
Speicher Beilrode I - Teilanlage 5
SEE939346315557
net power, MW6.25.65.6down by 0.6
Batteriespeicher-Buch
SEE917146636904
grid operator checkunder checkchecked5changed
Batteriespeicher
SEE933255558609
planned date2026-09-172026-11-054.8changed
MM9 - Speicher - Parey
SEE919126258380
grid operator checkunder checkchecked3.5changed
Theilheim Speicher BA III Ino
SEE950334441102
net power, MW3.03.13.1up by 0.1
Theilheim Speicher BA III Ino
SEE950334441102
planned date2025-08-182026-10-193.1changed
BESS Sinzing
SEE921014163461
net power, MW3.43.03down by 0.4
BESS Sinzing
SEE921014163461
grid operator checkunder checkchecked3changed
Batteriespeicher 2
SEE942088999749
planned date2026-09-012026-12-302changed
Speicher Riesa Trst. Fertigung BA 4
SEE988302497264
planned date2026-10-312026-11-271.1changed
Batteriespeicher I-Kubus Quedlinburg
SEE911894016032
grid operator checkunder checkchecked1changed