Since 14 November 2026: 9 batteries entered, 950 MW, 12 left, 5 other changes.
Litgrid overwrites its connection map as things change and keeps no history. Its three lists are copied here every day from 14 November 2026, and the difference between one day’s copy and the day before is printed, row by row, for every plant with a battery. Nothing here is inferred from the numbers; it is one capture against the one before, identifier by identifier. The column headed "our reading" is a rule, and it can be wrong.
By month
| Month | Entered | MW entered | Left | Other changes | Respelt or refiled |
|---|---|---|---|---|---|
| November 2026 | 9 | 950 | 12 | 5 | · |
Where this can be wrong
Litgrid gives its rows no lasting number, so a row is known here by its holder, its place and the day its paper was issued or signed; if Litgrid rewrites any of those, the row reads as one that left and one that entered. The last column is a rule. A set of conditions that leaves is said to be followed by a protocol when the same holder has a protocol within a kilometre on that day’s list, to have ended when its end date has passed, and otherwise to have been taken off early. Litgrid does not say why a row goes, and a slip in its table looks the same as a decision. A day the copy was missed joins two days’ changes into one. Wind and solar plant with no battery is not compared here.
Litgrid’s preliminary conditions, storage
A set of conditions is Litgrid’s first answer to a developer and lasts six months. A row enters when Litgrid issues one. It leaves when it ends, when it is withdrawn, or when Litgrid tidies it away after the protocol is signed; the last column says which, by the rule set out under “Where this can be wrong”. 11 captures held, 14 November 2026 to 24 November 2026.
Nothing moved in 7 of the 10 comparisons: 23 November 2026, 22 November 2026, 20 November 2026, 19 November 2026, 18 November 2026, 16 November 2026, 15 November 2026.
24 November 2026, against 23 November 2026
5 changes.
| Battery | What changed | From | To | MW | Our reading |
|---|---|---|---|---|---|
| UAB "Įdarbintas vėjas", Kaunas-Jurbarkas (LN 327), 330 kV, OL įdarbintas vėjas, Kaunas-Jurbarkas (LN 327), 330 kV, OL, issued 2026-05-22 | left | · | · | 232 | a protocol for the same holder at the same place, signed 23 April 2026, is on the protocols list |
| UAB "Unlimited power", Kruonio HAE TP unlimited power, Kruonio HAE TP, issued 2026-05-22 | left | · | · | 200 | ended on 22 November 2026; no protocol for this holder at this place is on the list |
| UAB "Avurena", Kruopių TP avurena, Kruopių TP, issued 2026-05-22 | left | · | · | 120 | a protocol for the same holder at the same place, signed 27 July 2026, is on the protocols list |
| UAB "Primum navitas", Bitėnų TP primum navitas, Bitėnų TP, issued 2026-05-22 | left | · | · | 70 | a protocol for the same holder at the same place, signed 4 September 2026, is on the protocols list |
| UAB "Solmega", Šeduva-Panevėžys, 110 kV, OL solmega, Šeduva-Panevėžys, 110 kV, OL, issued 2026-05-21 | left | · | · | 60 | ended on 21 November 2026; no protocol for this holder at this place is on the list |
21 November 2026, against 20 November 2026
8 changes.
| Battery | What changed | From | To | MW | Our reading |
|---|---|---|---|---|---|
| UAB "Navitas Storage", Bitėnų TP navitas storage, Bitėnų TP, issued 2026-11-19 | entered | · | · | 200 | new conditions, issued 19 November 2026, valid to 19 May 2027 |
| UAB "Ecotix", Bitėnų TP ecotix, Bitėnų TP, issued 2026-11-18 | entered | · | · | 100 | new conditions, issued 18 November 2026, valid to 18 May 2027 |
| UAB "Energetikos plėtra", Bitėnų TP energetikos plėtra, Bitėnų TP, issued 2026-11-18 | entered | · | · | 100 | new conditions, issued 18 November 2026, valid to 18 May 2027 |
| UAB "Energy Trade", Bitėnų TP energy trade, Bitėnų TP, issued 2026-11-17 | entered | · | · | 100 | new conditions, issued 17 November 2026, valid to 17 May 2027 |
| UAB "Inoxis", Bitėnų TP inoxis, Bitėnų TP, issued 2026-11-18 | entered | · | · | 100 | new conditions, issued 18 November 2026, valid to 18 May 2027 |
| UAB" Premium Navitas", Bitėnų TP premium navitas, Bitėnų TP, issued 2026-11-18 | entered | · | · | 100 | new conditions, issued 18 November 2026, valid to 18 May 2027 |
| UAB "Litrinka", Pielių TP litrinka, Pielių TP, issued 2026-05-19 | left | · | · | 150 | a protocol for the same holder at the same place, signed 24 July 2026, is on the protocols list |
| UAB "Spv bess", Kruopių TP spv bess, Kruopių TP, issued 2026-05-19 | left | · | · | 100 | a protocol for the same holder at the same place, signed 24 July 2026, is on the protocols list |
17 November 2026, against 16 November 2026
2 changes.
| Battery | What changed | From | To | MW | Our reading |
|---|---|---|---|---|---|
| UAB "SPV ES1", Šiaulių TP spv es1, Šiaulių TP, issued 2026-11-06 | entered | · | · | 50 | new conditions, issued 6 November 2026, valid to 6 May 2027 |
| UAB "Pietvis", Jonavos TP pietvis, Jonavos TP, issued 2026-05-12 | left | · | · | 50 | a protocol for the same holder at the same place, signed 23 October 2026, is on the protocols list |
Litgrid’s intent protocols, storage
A protocol is signed between the developer and Litgrid, and Litgrid then counts the capacity as reserved. Litgrid gives a map point and no connection point for these, so the place shown is the nearest substation. 11 captures held, 14 November 2026 to 24 November 2026.
Nothing moved in 7 of the 10 comparisons: 23 November 2026, 22 November 2026, 20 November 2026, 19 November 2026, 18 November 2026, 16 November 2026, 15 November 2026.
24 November 2026, against 23 November 2026
1 change.
| Battery | What changed | From | To | MW | Our reading |
|---|---|---|---|---|---|
| SOLI LT, UAB, near Šyša soli lt, near Šyša, signed 2025-01-27 | left | · | · | 150 | a plant of 150 MW at the same place is new on the connected list |
21 November 2026, against 20 November 2026
2 changes.
| Battery | What changed | From | To | MW | Our reading |
|---|---|---|---|---|---|
| Unlimited power 4, UAB, near Mūša unlimited power 4, near Mūša, signed 2026-10-23 | left | · | · | 200 | taken off before its end date of 23 December 2030, and nothing new at this place on the connected list |
| Pietvis, UAB, near Jonava pietvis, near Jonava, signed 2026-10-23 (2) | left | · | · | 50 | taken off before its end date of 23 December 2030, and nothing new at this place on the connected list |
17 November 2026, against 16 November 2026
2 changes.
| Battery | What changed | From | To | MW | Our reading |
|---|---|---|---|---|---|
| Pietvis, UAB, near Jonava pietvis, near Jonava, signed 2026-10-23 (2) | entered | · | · | 50 | Litgrid lists this row twice, the same in every field; it may be Litgrid’s slip |
| Jursola, UAB, near Pieliai jursola, near Pieliai, signed 2026-10-23 | left | · | · | 150 | taken off before its end date of 23 December 2030, and nothing new at this place on the connected list |
Litgrid’s connected plant, storage
Plant on the transmission grid. Litgrid names no holder on this list, so a row is known by its connection point. 11 captures held, 14 November 2026 to 24 November 2026.
Nothing moved in 9 of the 10 comparisons: 23 November 2026, 22 November 2026, 21 November 2026, 20 November 2026, 19 November 2026, 18 November 2026, 17 November 2026, 16 November 2026, 15 November 2026.
24 November 2026, against 23 November 2026
1 change.
| Battery | What changed | From | To | MW | Our reading |
|---|---|---|---|---|---|
| Šyšos TP Šyšos TP, battery storage | entered | · | · | 150 | new on the connected list |
Litgrid’s zones, room for storage
Litgrid divides its grid into zones and gives, for each, the capacity still free for storage and the capacity reserved by signed protocols, for 2026. A zone appears here on a day either figure moves; the MW column is the free capacity after the move. A move with no row entering or leaving the lists above is Litgrid’s own recount, and is printed as it stands. 11 captures held, 14 November 2026 to 24 November 2026.
Nothing moved in 9 of the 10 comparisons: 24 November 2026, 23 November 2026, 22 November 2026, 21 November 2026, 20 November 2026, 19 November 2026, 18 November 2026, 16 November 2026, 15 November 2026.
17 November 2026, against 16 November 2026
5 changes.
| Battery | What changed | From | To | MW | Our reading |
|---|---|---|---|---|---|
| Zone 94: Mūša zone 94 | free for storage, MW | 200 | 400 | 400 | up by 200 |
| Zone 94: Mūša zone 94 | reserved for storage, MW | 420 | 220 | 400 | down by 200 |
| Zone 96 zone 96 | free for storage, MW | 200 | 400 | 400 | up by 200 |
| Zone 68: Kruopiai, Pieliai, Telšiai zone 68 | free for storage, MW | 3 | 153 | 153 | up by 150 |
| Zone 68: Kruopiai, Pieliai, Telšiai zone 68 | reserved for storage, MW | 637 | 487 | 153 | down by 150 |