Vitreous Labs EirGrid 5 August 2026 · ESB Networks 1 July 2026
Show
CSV

Circle area is the megawatts

EnergisedContracted, not yet energised
48 batteries drawn at their station: 45 placed from OpenStreetMap’s substations, 3 from GeoNames by the station’s name, 3 not placed. The transmission grid’s energised batteries are not in any list EirGrid now publishes, so they are not drawn.

Ireland and Northern Ireland · EirGrid and ESB Networks lists · EirGrid 5 August 2026 · ESB Networks 1 July 2026

3,858 MW of batteries hold a signed connection agreement on the island and are not yet energised. 340 MW of it is one station, Louth.

EirGrid publishes every generator with a signed transmission connection agreement that is not yet energised, and ESB Networks publishes the same for the distribution grid, with what it has energised. The batteries are read out of those lists: 45 contracted, 6 energised at distribution. The figures are maximum export capacity, which is the connection and never the battery. The Ireland page reads the same lists as tables.

Contracted3,858MW · 45 batteries
Of it at transmission3,740MW · 36
Energised, distribution75MW · 6
Largest station340MW · Louth

Showing every battery in the lists. Filter by status, grid or batch, or search a name, a station or a reference.

Every battery in the lists

Largest first. Click a row to centre the map on its station. A station is placed from OpenStreetMap or GeoNames by its name; 3 of 51 rows could not be placed and are in the table only.

BatteryStationGridBatchMEC, MWSigned or energisedPlaced by

Sources: EirGrid, Contracted TSO generators, wind and non-wind, correct as of 5 August 2026; ESB Networks, distribution contracted and energised generators and live connection assessments, correct as of 1 July 2026. Read as published, checked against each list’s printed total. Station positions from OpenStreetMap (Open Database Licence) and GeoNames (CC BY 4.0), never from the lists. Northern Ireland’s own lists (SONI, NIE Networks) are not yet held.