Vitreous LabsEnergy transparency
Spain · the installations

Every battery installation in Spain’s State gazette, 224 of them

224 installations, 8,195 MW, from every act on battery storage the gazette has published since 2021. Each has a page listing the acts behind it, with the figures each act states and a link to the act itself.

Largest first. The date is the latest step. The list as a CSV, with each step’s date and the acts.

Installation, as the gazette names itPlacePromoterMWMWhStep reachedDate
BAT CedilloCedillo, CáceresIberenova Promociones, S.A.U.215888In public consultation2 Oct 2025
BAT OriolCeclavín, CáceresDehesa Solar Sur, S.L.205846In public consultation3 Nov 2025
ST PalmosillaTarifa, CádizRolwind Andalucía 10, SL200885First authorisation4 Jun 2026
ValdesolarValdecaballeros, BadajozValdesolar Hive S.L.200413In public consultation17 Mar 2026
Tagus 2 HBESSOcaña, ToledoKhons Sun Power, SL176662Authorised to build16 Oct 2026
BESS II Valle SolarJarafuel, ValenciaBOMBO VALLE SOLAR, S.L.167333Environmental decision12 Feb 2026
BESS FV La Puebla 3Cerro de Andévalo, HuelvaJinko Greenfield Spain 1, S.L.150600In public consultation16 Sep 2026
La Farga BESSVilademuls, GironaCadaques Directorship, SL148297First authorisation16 May 2026
BESS GaetanaLa Roca de la Sierra, BadajozGaetana Solar, SLU120432In public consultation9 Jul 2026
SPK TrujilloTrujillo, CáceresSPK FALCON, S.L.109402In public consultation23 Jun 2026
BESS AUREALa Roca de la Sierra, BadajozAurea Solar, S.L.U108432In public consultation6 Jul 2026
Picassent BESS 132 kVPicassent, ValenciaSargao Energy, SL108216First authorisation21 May 2026
Picassent BESSPicassent, ValenciaSargao Energy, SL108216Environmental decision24 Mar 2025
BESS PachecoCartagena, MurciaAMELIE PV, S.L.105499In public consultation3 Jun 2026
LagerungSant Julià de Ramis, GironaA Green Message, SL102407First authorisation17 Jun 2026
Tabiella BessGozón, AsturiasTagenergy Spain Investments 1, SL100216Environmental decision11 Dec 2024
VisentaSesué, HuescaFull Solar Energy, SL100407Refused, withdrawn or rejected10 Jul 2026
PerdigueroBenasque, HuescaPower Tarida, SL100407Refused, withdrawn or rejected25 Jun 2026
Tabiella Bess 132 kVGozón, AsturiasTagenergy Spain Investments 1, SL100·First authorisation11 Mar 2026
Storage at GecamaAtalaya de Cañavate, CuencaGeneración Eólica Castilla-La Mancha, SL100200Authorised to build14 Jul 2025
Storage at parque eólico GecamaAtalaya del Cañavate, CuencaGeneración Eólica Castilla-La Mancha, SL100200Environmental decision11 Dec 2024
Storage at Parque GECAMA EÓLICOAtalaya del Cañavate, CuencaGENERACION EOLICA CASTILLA LA MANCHA, S.L.100·In public consultation3 Jan 2023
BESS Hibridaciones FV ArenalesCáceres, CáceresParque Solar Cáceres, SL95392Environmental decision30 May 2026
BESS I Valle SolarJarafuel, ValenciaBOMBO VALLE SOLAR, S.L.92.5185Environmental decision12 Feb 2026
Unnamed storage (BOE-B-2023-18032)Sant Antoni de Portmany, Illes BalearsRed Eléctrica de España, Sociedad Anónima Unipersonal9067.5In public consultation13 Jun 2023
BESS La AtalayaVillena, AlicanteMURSOLAR 14, S.L.83.7331In public consultation30 Jul 2026
ST CerrilloÁlora, MálagaRolwind Málaga 1, SL77.6340Authorised to build5 Jun 2026
Orcoyen AlmacenaOrcoyen, NavarraEnergía Frigoria 2, S. L. U.73.6222In public consultation16 Jun 2026
PB Babor 7Tarifa, CádizArena Power Ren 29, SL66198First authorisation1 Jul 2026
PB Navegantes 32Mieres, AsturiasArena Power Ren 34, SLU; Arena Power Ren 31, SLU65210Environmental decision18 Apr 2026
El TelloPicassent, ValenciaGANDASOLAR 29, SLU63·Refused, withdrawn or rejected21 Mar 2025
BESS San MartínAlbalate del Arzobispo, TeruelEnel Green Power España, SL60.8·Refused, withdrawn or rejected25 Jun 2026
Agrupación Maira AlphaLlano de Bureba, BurgosSOLARIA Promoción y Desarrollo Fotovoltaico, S.L.U.60240Environmental decision22 Dec 2025
Glauco AlmacenaVilademuls, GironaEnergía Glauco, SL55.4222First authorisation16 May 2026
BESS Cuevasla Vall d'Uixó, CastellónSoner Picasso, SLU55.2221First authorisation23 Oct 2026
BESS OlindaOnda, CastellónGLOBAL BAZA S.L52.6·In public consultation5 May 2026
Las RegañasRubí, BarcelonaPLANTA SOLAR OPDE, 34 S.L.51204Refused, withdrawn or rejected24 Dec 2025
Solaben ST1Logrosán, CáceresSolaben Electricidad Seis, S.A.U.50200In public consultation9 Jul 2026
Instalación de un conjunto de baterías en la subestación MercadalEs Mercadal, Illes BalearsRed Eléctrica de España, Sociedad Anónima Unipersonal5037.5In public consultation1 Jun 2023
BESS CAMARREALCamargo, CantabriaFotowatio Renewable Ventures Servicios España, S.L.U.49.9206In public consultation23 Jul 2026
BESS SOLÓRZANOSolórzano, CantabriaBess Development 6, S. L.49.7200Authorised to build7 Aug 2026
GAZULES I HIBRIDACIÓNAlcalá de los Gazules, CádizPLANTA SOLAR OPDE 1, S.L.U.45.8·In public consultation25 Feb 2026
Storage at Los LimonetesBadajoz, BadajozMonegros Solar, SA45.791.4Environmental decision29 Jan 2026
Agrupación Maira «Gamma»Briviesca, BurgosSOLARIA Promoción y Desarrollo Fotovoltaico, S.L.U.45180Environmental decision24 Jul 2026
Agrupación Maira DeltaValluércanes, BurgosSOLARIA Promoción y Desarrollo Fotovoltaico, S.L.U.45180Environmental decision22 Dec 2025
Agrupación Maira BetaLa Vid de Bureba, BurgosSOLARIA Promoción y Desarrollo Fotovoltaico, S.L.U.45180Environmental decision22 Dec 2025
BESS Azor Solar 2Paracuellos de Jarama, MadridAzor Solar, SLU44.6179First authorisation12 Oct 2026
Hibridación Covatillas 3Castillejo de Iniesta, CuencaPlanta Solar OPDE 25, SL43.9300Authorised to build21 Aug 2026
Archo IIAntequera, MálagaMatilde Solar, S.L.U.42.6·In public consultation6 Apr 2026
Archo IAntequera, MálagaIrineo Energía, S.L.U.42.6·In public consultation6 Apr 2026
BESS MudéjarAndorra, TeruelEnel Green Power España, SLU41.689.5Refused, withdrawn or rejected30 Jul 2026
Baterías Puntiró HIVEPalma, Illes BalearsSUN HIVE 85 SL4182In public consultation15 Apr 2024
ALM HIB San Serván 2020Mérida, BadajozALTER ENERSUN MÉRIDA UNO, S.A.40160In public consultation20 Oct 2026
BESS Los FrailesBadajoz, BadajozRalos Investment Fotovoltaico Sur, S.L.40160In public consultation28 Jul 2026
AquariiVillamejil, LeónPLANTA FV 127, S.L.40160In public consultation22 Apr 2026
Don Rodrigo IIUtrera, SevillaUrso Solar, SLU39.6140Authorised to build19 Aug 2026
BESS GESAlcalá de Guadaíra, SevillaGestenia Energía, SL39.6140Authorised to build19 Aug 2026
BESS AfroditaLos Molares, SevillaAfrodita Solar, SL39.6140Authorised to build18 Aug 2026
FreyaCarmona, SevillaFreya Solar, SLU39.6140Authorised to build31 Jul 2026
SESAlcalá de Guadaíra, SevillaSenen Energía, SL39.6140Authorised to build20 Jul 2026
JadeAlcalá de Guadaíra, SevillaJade Sostenible, SL39.6140Authorised to build20 Jul 2026
HeraclesAlcalá de Guadaíra, SevillaHeracles Solar, SLU39.6140Authorised to build20 Jul 2026
EsmeraldaAlcalá de Guadaíra, SevillaEsmeralda Solar, SL39.6140Authorised to build20 Jul 2026
ElvisaAlcalá de Guadaíra, SevillaElvisa Solar, SLU39.6140Authorised to build16 Jul 2026
ArtemisaAlcalá de Guadaíra, SevillaArtemisa Energía, SL39.6140Authorised to build16 Jul 2026
DemeterLos Molares, SevillaDemeter Energía, S.L.U.39.6·In public consultation18 May 2026
AnubisLos Molares, SevillaAnubis Energía, S.L.U.39.6·In public consultation18 May 2026
Híbrida Don Rodrigo IIICarmona, SevillaTeonas Solar, S.L.U.39.6·In public consultation27 Apr 2026
AgathaAlcalá de Guadaira, SevillaAgatha Energía, S.L.39.6·In public consultation23 Apr 2026
Valdecaballero BateríaCasas de Don Pedro, BadajozEnel Green Power España Solar 1, SLU38.577First authorisation13 Jun 2026
Navalvillar BateríaCasas de Don Pedro, BadajozEnel Green Power España Solar 1, SLU38.577First authorisation13 Jun 2026
Castilblanco BateríaCasas de Don Pedro, BadajozEnel Green Power España Solar 1, SLU38.577First authorisation13 Jun 2026
Hernán CortésLogrosán, CáceresDehesa de los Guadalupes Solar, SLU38.560First authorisation19 Dec 2025
Hibridación La Loma con batería de almacenamientoAliaga, TeruelCOMIOLICA, S.L.U.3671.9Environmental decision3 Nov 2025
Las LomillasTébar, CuencaTébar Eólica, SA3672Authorised to build23 Oct 2025
BESS Rey III SolarCarmona, SevillaVillablanca Solar 1, S.L.35.1·In public consultation11 Sep 2026
Herrera de los NavarrosHerrera de los Navarros, ZaragozaSistemas Energéticos Barandón, S.L.35.170.2In public consultation18 Jun 2026
BESS Hibridación FV Virgen de Areños IIIVillota del Páramo, PalenciaIberenova Promociones, SAU35145Environmental decision25 Sep 2026
Bat Tagus IVAlcántara, CáceresIberenova Promociones, SA35145Environmental decision5 Feb 2026
Bat Tagus IIIAlcántara, CáceresIberenova Promociones, SA35145Environmental decision5 Feb 2026
Bat Tagus IIAlcántara, CáceresIberenova Promociones, SA35145Environmental decision5 Feb 2026
Bat Tagus IAlcántara, CáceresIberenova Promociones, SA35145Environmental decision5 Feb 2026
El CucoMontealegre del Castillo, AlbaceteEL CUCO ENERGY, S.L.33.6100In public consultation19 Jun 2026
Ribadelago HíbridoPalacios de Sanabria, ZamoraEmaldi Project Spain, S.L.U.32.1129In public consultation23 Oct 2026
PegasoValladolid, ValladolidPlanta FV112, SL3172Environmental decision17 Sep 2026
BESS Hibridación PE IglesiasIglesias, BurgosBoreas Wind, SL30.3124Authorised to build29 Jun 2026
Almacenamiento Iniesta hibridoIniesta, CuencaPARQUE EÓLICO INIESTA, S.L.30120In public consultation4 Jun 2026
BESS OPDE Trévago 1Fuentestrún, SoriaPlanta Solar OPDE 42 S.L.U.30120In public consultation18 May 2026
QuijoteLogrosán, CáceresFuratena Solar 1, SLU3060First authorisation18 Dec 2025
ApicioFregenal de la Sierra, BadajozEnel Green Power España Solar 1, SLU3060First authorisation18 Dec 2025
BAT San AntonioCedillo, CáceresSolar Majada Alta, S.L.30124Environmental decision2 Oct 2025
BAT Majada AltaCedillo, CáceresSolar Majada Alta, S.L.30124Environmental decision2 Oct 2025
BeturiaFregenal de la Sierra, BadajozDehesa de los Guadalupes Solar, SLU3060First authorisation25 Aug 2025
NertobrigaFregenal de la Sierra, BadajozBaylio Solar, SLU3060First authorisation21 Aug 2025
CincinatoBodonal de la Sierra, BadajozSeguidores Solares Planta 2, SLU3060First authorisation21 Aug 2025
ALM Ardila BateríaFregenal de la Sierra, BadajozFuratena Solar 1, SLU3060Authorised to build6 Jan 2025
BianorUtrera, SevillaBianor Solar, SLU28.4100Authorised to build25 Aug 2026
BESS Hibridación FV TeruelAzaila, TeruelIberdrola Renovables Aragón, SAU27.659.9Authorised to build20 Oct 2026
BESS Hibridación OlmedillaAlarcón, CuencaDesarrollos Renovables FV Olmedilla, SL27.559.9Authorised to build29 Jan 2026
BESS Hibridación RomeralAlarcón, CuencaDesarrollos Renovables FV Romeral, SL27.559.9Authorised to build27 Jan 2026
BESS Hibridación FV Revilla-VallejeraVallejera, BurgosIberenova Promociones, SA27.559.9Authorised to build7 Oct 2024
Hibridación MontesolCañada Vellida, TeruelPlanta Solar OPDE 6, SL26.7140Authorised to build22 Oct 2026
Hibridación LarralZaragoza, ZaragozaPLANTA SOLAR OPDE 8, S.L.26.7126Environmental decision22 Oct 2026
Hibridación Los BelosLa Muela, ZaragozaPlanta Solar OPDE 3, SL26.7125Authorised to build20 Oct 2026
Hibridación Los ArcosAndorra, TeruelPlanta Solar OPDE 17, SL26.7140Authorised to build19 Oct 2026
Hibridación OPDE Belinchón 2Barajas de Melo, CuencaPlanta Solar OPDE 52, SL26.7126Authorised to build20 Jun 2026
Hibridación OPDE Belinchón 1Barajas de Melo, CuencaPlanta Solar OPDE 51, SL26.7126Authorised to build20 Jun 2026
Hibridación Plana de la Pena 1Botorrita, ZaragozaPLANTA SOLAR OPDE 12, S.L.26.7126In public consultation13 May 2026
BESS Belinchón 3Barajas de Melo, CuencaPLANTA SOLAR OPDE 53, S.L.26.7126In public consultation6 Feb 2026
BESS Hibridación FV AndévaloPuebla de Guzmán, HuelvaIberdrola Renovables Andalucía, SAU26.459.9Authorised to build15 Sep 2025
BESS Hibridación Almaraz IIBelvís de Monroy, CáceresIBERENOVA PROMOCIONES S.A.U.26.459.9In public consultation19 Jun 2024
BESS Hibridación AlmarazBelvís de Monroy, CáceresIBERENOVA PROMOCIONES S.A.U.26.459.9In public consultation19 Jun 2024
BESS CillamayorAguilar de Campoo, PalenciaMacrina Solar 6, SL25.4110In public consultation6 Oct 2026
ALM Alambor SolarPinos Puente, GranadaAlambor Solar S.L.U.24.6·In public consultation6 Oct 2026
Bolarque ITinajas, CuencaSolar Bolarque, SL24.640Authorised to build6 Nov 2025
Paraje Las Flotas de los ÁlamosTotana, MurciaSEGUIDORES SOLARES PLANTA 2, S.L.24.540In public consultation20 Jun 2023
OPDE MiramundoPuerto Real, CádizPlanta Solar OPDE Extremadura 2, S.L.24121Environmental decision30 Jul 2026
Hibridación ZafraAlcalá de Guadaíra, SevillaPlanta Solar OPDE Andalucía 1, SL24126Authorised to build27 Apr 2026
La FernandinaMérida, BadajozPlanta Solar OPDE La Fernandina, S.L.24125Environmental decision30 Jul 2025
BESS Azor Solar 1Paracuellos de Jarama, MadridAzor Solar, SLU23.996.7First authorisation12 Oct 2026
PB SONORA SUBIRATS 1Subirats, BarcelonaSONORA POWER, S.L.23.554In public consultation4 Sep 2025
Hibridación Villanueva del ReyLa Luisiana, SevillaNaturgy Renovables, S.L.U.22.9·In public consultation9 Mar 2026
Talayuela II BESSTalayuela, CáceresOropesa Solar, SL22.347.7Authorised to build1 Jul 2026
Solnova ST1Sanlúcar la Mayor, SevillaSolnova Electricidad, S.A.22·In public consultation20 Feb 2026
módulo de almacenamiento AitanaAltarejos, CuencaGR Aitana Renovables, SLU21.943.4Authorised to build15 Aug 2026
TurbónAltarejos, CuencaGR Turbón Renovables, SLU21.743.4Authorised to build17 Aug 2026
BañuelaAltarejos, CuencaGR Bañuela Renovables, SLU21.743.4Authorised to build17 Aug 2026
AspeAltarejos, CuencaGR Aspe Renovables, SLU21.743.4Authorised to build15 Aug 2026
Hibridación BESS Greencar 3Carmona, SevillaGreen Ric Energy, S.L.U21.685.7In public consultation23 Sep 2026
módulo de almacenamiento energético MulhacénEsquivias, ToledoMulhacén Solar, SLU21.644.1First authorisation12 Oct 2026
ALM Los Naipes IIBadajoz, BadajozNaturgy Renovables, SLU21.4·Environmental decision11 May 2026
ALM Los NaipesBadajoz, BadajozNaturgy Renovables, SLU21.4·Environmental decision11 May 2026
ALM El Encinar IBadajoz, BadajozNaturgy Renovables, SLU21.4·Environmental decision11 May 2026
BESS La NavaAlmodóvar del Campo, Ciudad RealNaturgy Renovables, SLU20.846.7Authorised to build27 Mar 2025
Planta de Almacenamiento de Energía con Baterías Carpio de TajoEl Carpio de Tajo, ToledoNaturgy Renovables, SLU20.846.7Authorised to build21 Mar 2025
Planta de Almacenamiento Frontones Híbrida Fase IICorral-Rubio, AlbaceteELAWAN EÓLICA FRONTONES, S.L.2080In public consultation31 Aug 2026
Storage at P.E. San BlasValverde de Campos, ValladolidNaturgy Renovables, SLU20·Refused, withdrawn or rejected18 Aug 2026
ArmusVillamediana, PalenciaPlanta FV 124, SL2080Environmental decision2 Jun 2026
Telesto 3San Andrés del Rey, GuadalajaraPlanta FV 155 SL2040Environmental decision25 Mar 2026
Telesto 2San Andrés del Rey, GuadalajaraPlanta FV 155 SL2040Environmental decision25 Mar 2026
Almacenamiento Elawan Torrijos I HíbridoNovés, ToledoELAWAN TORRIJOS 220, S.L.2092.2In public consultation17 Mar 2026
ThermiscoBudia, GuadalajaraPlanta FV 146 SL, Planta FV 148 SL, Planta FV 149 SL, Planta FV 147 SL, Planta FV 145 SL y Planta FV 144 SL2040Environmental decision16 Mar 2026
TethysBudia, GuadalajaraPlanta FV 146 SL, Planta FV 148 SL, Planta FV 149 SL, Planta FV 147 SL, Planta FV 145 SL y Planta FV 144 SL2040Environmental decision16 Mar 2026
Telesto 7Budia, GuadalajaraPlanta FV 146 SL, Planta FV 148 SL, Planta FV 149 SL, Planta FV 147 SL, Planta FV 145 SL y Planta FV 144 SL2040Environmental decision16 Mar 2026
Telesto 4Budia, GuadalajaraPlanta FV 146 SL, Planta FV 148 SL, Planta FV 149 SL, Planta FV 147 SL, Planta FV 145 SL y Planta FV 144 SL2040Environmental decision16 Mar 2026
TelestoBudia, GuadalajaraPlanta FV 146 SL, Planta FV 148 SL, Planta FV 149 SL, Planta FV 147 SL, Planta FV 145 SL y Planta FV 144 SL2040Environmental decision16 Mar 2026
RheaBudia, GuadalajaraPlanta FV 146 SL, Planta FV 148 SL, Planta FV 149 SL, Planta FV 147 SL, Planta FV 145 SL y Planta FV 144 SL2040Environmental decision16 Mar 2026
Titan SolarPeralveche, GuadalajaraSolaria Promoción y Desarrollo Fotovoltaico, SLU2080Environmental decision27 Feb 2026
Mimas SolarPeralveche, GuadalajaraSolaria Promoción y Desarrollo Fotovoltaico, SLU2080Environmental decision27 Feb 2026
Dione SolarPeralveche, GuadalajaraSolaria Promoción y Desarrollo Fotovoltaico, SLU2080Environmental decision27 Feb 2026
Storage at Fuente-ÁlamoChinchilla de Montearagón, AlbaceteElawan Eólica Fuente Álamo, SL20·Refused, withdrawn or rejected9 Oct 2025
FRV PALAUPalau-solità i Plegamans, BarcelonaFRV ARROYADAS 2 SL2080.2In public consultation19 May 2025
CastorHuecas, ToledoPlanta FV 115, SL2080Authorised to build22 Oct 2026
Solaria-Santiz IValdelosa, SalamancaPlanta FV100, SL20100Authorised to build20 Oct 2026
Solaria-Tordesillas IITordesillas, ValladolidPlanta FV101, SL20·In public consultation17 Sep 2026
ALM Ictio Alcázar IIIAlcázar de San Juan, Ciudad RealIctio Solar Berenice, SL2040First authorisation14 Oct 2026
ALM Ictio Alcázar IIAlcázar de San Juan, Ciudad RealIctio Solar Auriga, SL2080First authorisation14 Oct 2026
BESS Tabernas ITabernas, AlmeríaNaturgy Renovables, SLU19.846.7Authorised to build21 Oct 2026
BESS Tabernas IITabernas, AlmeríaNaturgy Renovables, SLU19.846.7Authorised to build13 Oct 2026
BESS Picón IIPorzuna, Ciudad RealNaturgy Renovables, SLU19.846.7Authorised to build26 Feb 2026
BESS Picón IIIPorzuna, Ciudad RealNaturgy Renovables, SLU19.846.7Authorised to build19 Feb 2026
BESS Picón IPorzuna, Ciudad RealNaturgy Renovables, SLU19.846.7Authorised to build19 Feb 2026
ALM Coracha SolarPinos Puente, GranadaCoracha Solar S.L.U.19.7·In public consultation6 Oct 2026
ALM Cimera SolarPinos Puente, GranadaCimera Solar S.L.U.19.7·In public consultation6 Oct 2026
Castillo GarcimuñozPinarejo, CuencaEDP RENOVABLES ESPAÑA S.L.U19.539In public consultation29 Sep 2026
BESS El TamborHíjar, TeruelEnel Green Power España, SL19·Refused, withdrawn or rejected25 Jun 2026
Serván 8Solana de los Barros, BadajozFVR San Serván 8, S.L.U.18.886Environmental decision21 May 2026
Serván 7Solana de los Barros, BadajozFVR San Serván 7, S.L.U.18.886Environmental decision21 May 2026
Serván 6Solana de los Barros, BadajozFVR San Serván 6, S.L.U.18.886Environmental decision21 May 2026
Bess ValdiviesoAlcázar de San Juan, Ciudad RealGalp Energía España, SAU18.537Environmental decision27 Jan 2026
Alm Bess ValdecarroAlcázar de San Juan, Ciudad RealGalp Energía España, SAU18.537Environmental decision27 Jan 2026
DracoToro, ZamoraPlanta FV109, S.L.1872Environmental decision5 May 2026
DelphinusToro, ZamoraPlanta FV108, S.L.17.972Environmental decision5 May 2026
Tesouro StorageAs Pontes de García Rodríguez, A CoruñaEnel Green Power España, SL17.537Authorised to build19 Oct 2026
BESS La SolanillaTrujillo, CáceresFRV La Solanilla, S.L.17.570In public consultation4 Jun 2026
La IslaAlcalá de Guadaira, SevillaNovasol Invest La Isla, S.L.16.5·In public consultation21 Apr 2026
Alcázar 2Alcázar de San Juan, Ciudad RealGalp Energía España, SAU16.533Environmental decision27 Jan 2026
Alcázar 1Alcázar de San Juan, Ciudad RealGalp Energía España, SAU16.533Environmental decision27 Jan 2026
ZurbaránLogrosán, CáceresBaylio Solar, SLU1530First authorisation18 Dec 2025
ALM BateríasBelvís de Monroy, CáceresIberdrola Generación, SAU15·Authorised to build7 Mar 2024
Storage at Coria VilletasCoria, CáceresSoner Goya, SLU13.827.5First authorisation17 Dec 2025
Coria VilletasGuijo de Coria, CáceresSoner Goyan SLU13.827.5Environmental decision30 Jul 2025
Broza SolarHorche, GuadalajaraBroza Solar, SLU10.921.8First authorisation9 Oct 2025
Moeche StorageMoeche, A CoruñaEnel Green Power España, S.L.10.522.2In public consultation28 Apr 2026
PiruquitoAmpuero, CantabriaEnerfín Renovables IX, SLU8.517Refused, withdrawn or rejected13 Nov 2025
Sistema de almacenamiento de energía con baterías MarzagánTelde, Las PalmasIberdrola Renovables Canarias, S.A.U.840.3In public consultation21 May 2025
HIB. SAE PILETAS IAgüimes, Las PalmasNaturgy Renovables, S.L.U.6.312.9First authorisation5 May 2025
BESS Azuer IManzanares, Ciudad RealCalatrava Solar I, S.L.U.615In public consultation6 Oct 2026
PHFV CENTELLESCentelles, BarcelonaRENEW GREEN GENERATOR IV, S.L.5.533In public consultation20 Oct 2026
PHFV PENEDESVilafranca del Penedès, BarcelonaRENEW GREEN GENERATOR IV SL5.522In public consultation6 Feb 2026
RaposerasPradejón, La RiojaEnergías Alternativas Eólicas Riojanas, SL5·Refused, withdrawn or rejected30 May 2026
Almacenamiento Hibridación Las AzubíasFuendejalón, ZaragozaMolinos del Moncayo, SL510First authorisation27 Apr 2026
ValdejalónRueda de Jalón, ZaragozaMolinos del Ebro, SA510First authorisation4 May 2026
El TolloRueda de Jalón, ZaragozaMolinos del Ebro, SA510First authorisation4 May 2026
Almacenamiento Hibridación El LlanoRueda de Jalón, ZaragozaMolinos del Ebro, SA530First authorisation18 Apr 2026
Storage at PicadorFuendejalón, ZaragozaMolinos del Moncayo, SL510Environmental decision23 Mar 2026
Sistema de Almacenamiento de Energía con Baterías (SAEB) Barranco Seco 4Las Palmas de Gran Canaria, Las PalmasIberdrola Renovables Canarias. S.A.U.522.4In public consultation29 May 2025
Sistema de Almacenamiento de Energía con Baterías (SAEB) Barranco SecoLas Palmas de Gran Canaria, Las PalmasIberdrola Renovables Canarias. S.A.U.522.4In public consultation23 May 2025
Storage at Santiago Sil-JaresVilamartín de Valdeorras, OrenseIberdrola Generación, SAU55Authorised to build12 Feb 2024
Storage at Central Hidroeléctrica Santiago Sil-JaresVilamartín de Valdeorras, OurenseIberdrola Generación S.A.U.5·In public consultation2 Jan 2023
Storage at Puertollano IIPuertollano, Ciudad RealIberdrola Renovables Castilla La Mancha, SA522.8Authorised to build2 Dec 2021
PHFV CastelletL'Arboç, TarragonaRenew Green Generator I, S.L.5·In public consultation24 Jul 2026
Bess Autoconsumo PuertollanoPuertollano, Ciudad RealRepsol Petróleo, SA416.3Environmental decision20 Jun 2026
Planta de Almacenamiento FrontonesCorral Rubio, AlbaceteElawan Eólica Frontones, SL49.2First authorisation28 May 2025
Campanario I HíbridoBonete, AlbaceteELAWAN FOTOVOLTAICA CAMPANARIO 1, S.L.3.89.2Authorised to build7 Jun 2025
Storage at Planta Fotovoltaica Los FrailesTelde, Las PalmasPSF Los Frailes, S.L.U.0.80.8In public consultation15 Apr 2026
Centro de Seccionamiento equipado con batería de almacenamientoCillorigo de Liébana, CantabriaViesgo Distribución Eléctrica, S.L.0.60.9In public consultation19 Sep 2022
PS_PB BESS BrunyolaBrunyola y Sant Martí Sapresa, GironaPrime Rubau Energy, SL0.51In public consultation7 Oct 2026
Proyecto para abastecimiento energético mediante almacenamiento y gestión inteligente de la demanda en zonas con protección ambiental en Extremadura, en el término municipal de Santa Marta de MagascaSanta Marta de Magasca, CáceresEléctricas Pitarch Distribución, S.L.U.0.20.6In public consultation10 May 2021
BESS PIXINCorvera de Asturias, AsturiasREADY TO BUILD RENEWABLES SLU··In public consultation6 Mar 2026
Bess Valle de GüímarArafo, Santa Cruz de TenerifeBess Development 5,S.L.·41.3In public consultation22 May 2024
Son Molines BESS 4Palma, Illes BalearsEFM Balears Sostenible 05, S.L.·40In public consultation25 Nov 2024
Son Molines BESS 3Palma, Illes BalearsEFM Balears Sostenible 05, S.L.·40In public consultation25 Nov 2024
Son Molines BESS 2Palma, Illes BalearsEFM Balears Sostenible 05, S.L.·40In public consultation25 Nov 2024
Son Molines BESS 1Palma, Illes BalearsEFM Balears Sostenible 05, S.L.·40In public consultation25 Nov 2024
Almacenamiento Bess Es Rafal Can Valero 2Palma, Illes BalearsEFM Balears Sostenible 04, S.L.·40In public consultation25 Nov 2024
Almacenamiento Bess Es Rafal Can Valero 1Palma, Illes BalearsEFM Balears Sostenible 04, S.L.·40In public consultation25 Nov 2024
INCA BESS 66 kVInca, Illes BalearsONE VICTORIA SOLAR 2, SL·123In public consultation19 Nov 2024
Almacenamiento Calvià Bess 2Calvià, Illes BalearsEFM Sostenible 02 SL·6In public consultation23 Jul 2024
Almacenamiento Calvià Bess 1Calvià, Illes BalearsEFM Sostenible 02 SL·20In public consultation23 Jul 2024
BESS Baleares 3Alcúdia, Illes BalearsCantabria 5 Renovable, SLU·108In public consultation20 May 2024
BESS ICOR IIArico, Santa Cruz de TenerifeDISA RENOVABLES S.L.U.·9.6Declared of public utility14 May 2024
Sant Martí BESSAlcúdia, Illes BalearsMERAK STORAGE 2, SL·79In public consultation6 May 2024
Storage at Santiago Sil-XaresVillamartín de Valdeorras, OurenseIBERDROLA GENERACIÓN, S.A.U.··In public consultation24 Jan 2024

Source: Boletín Oficial del Estado, read to 25 October 2026. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.