A battery installation of 35 MW and 145 MWh in Villota del Páramo, Palencia, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power35 MW
Storage145 MWh
Hours at full power4.1
PromoterIberenova Promociones, SAU
ConfigurationAdded to a plant
Plant it is added toVirgen de Areños III, 44.7 MW, solar
MunicipalityVillota del Páramo
ProvincePalencia
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
17 Mar 2026Environmental decision; 35 MW, 145 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2026-6302
25 Sep 2026Public consultation; 35 MW, 145 MWhSubdelegación del Gobierno en PalenciaBOE-B-2026-30931

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.