A battery installation of 35 MW and 145 MWh in Villota del Páramo, Palencia, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 35 MW |
| Storage | 145 MWh |
| Hours at full power | 4.1 |
| Promoter | Iberenova Promociones, SAU |
| Configuration | Added to a plant |
| Plant it is added to | Virgen de Areños III, 44.7 MW, solar |
| Municipality | Villota del Páramo |
| Province | Palencia |
| Step reached | Environmental decision |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 17 Mar 2026 | Environmental decision; 35 MW, 145 MWh | Ministry for the Ecological Transition, Directorate-General for Environmental Quality and Assessment | BOE-A-2026-6302 |
| 25 Sep 2026 | Public consultation; 35 MW, 145 MWh | Subdelegación del Gobierno en Palencia | BOE-B-2026-30931 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.