Spain’s State gazette names 224 battery installations since 2021, 8,195 MW, and authorised 2,450 MW of them in 2026 alone, nearly five times the year before.
The State gazette read to 25 October 2026; OMIE’s list of units read 25 October 2026. Both are read every day.
Spain publishes no connection queue with names. What it does publish, act by act, is every step the State takes on a battery project: the public consultation, the environmental decision, the authorisations to build and the refusals. This page reads every such act in the Boletín Oficial del Estado since 2021, each one in full and each figure checked against the act’s own words, and joins them into one row per installation. Beside them sit the batteries OMIE, the Iberian market operator, lists as registered to trade.
The State authorised 2,450 MW of batteries in 2026 to 25 October, against 501 MW in the whole of 2025
Each bar is the battery power the State first authorised that year, by the date the act was published in the gazette. Consultations began in earnest in 2023 (24 installations, against 1 in 2022), and the authorisations followed from 2024. Where the gazette carries both, the median installation took 224 days from its public consultation to its authorisation to build; the quickest 118, the slowest 1,078.
The first authorisation (autorización administrativa previa) or the authorisation to build (de construcción), whichever came first; in every one of the 50 installations authorised to build, both were granted in the same act. The last bar is this year to the gazette’s latest read. The battery’s own power, never the access capacity it shares with a plant.
4,744 MW is still in consultation or environmental review
Every installation sits at the furthest step the gazette shows it has reached. A refusal, a withdrawal or an unfavourable environmental decision moves it to the last row, whatever came before.
1 installation declared of public utility with no other step is counted in no bar. Power is the battery’s own: its net power where an act states one (seven installations), and otherwise its installed power, the only figure most acts give. 15 installations whose acts state no battery power count in the installations and not in the MW.
Where the batteries are: Cáceres and Badajoz hold 2,057 MW between them
One circle per installation, sized by its battery power, at the centre of the municipality the gazette names. Amber is a battery registered to trade.
221 of 234 drawn. Not drawn: seven installations in the Canary Islands, listed below, and six registered batteries whose municipality no source we may publish has given yet.
Open the Atlas, every installation on the map Every installation, with every act behind it What changed, month by month180 of the 218 installations whose acts say so are added to a solar or wind plant
Spain lets a battery share the grid connection of a plant already authorised, so most of the gazette’s batteries are hybrids: 180 installations, 6,326 MW, added to a plant, against 38 stand-alone, 1,810 MW. Two sizes of store dominate: 80 of the 179 installations with both figures hold about two hours at full power, and 68 about four. The median is 3.5 hours.
11 of the 50 installations authorised to build connect at one substation, Don Rodrigo 400 kV
The gazette names 15 battery installations at the Don Rodrigo 400 kV substation, 583 MW, in Alcalá de Guadaíra, Carmona, Los Molares and Utrera. 14 of them are the same size, 39.6 MW, each added to a plant of its own and each applied for by a different company. Between 16 July and 25 August 2026 the State authorised 11 of them to build, 424 MW, which is 26% of all the battery power it has authorised to build.
The 15 installations at Don Rodrigo 400 kV
| Installation, as the gazette names it | Place | Promoter | MW | MWh | Step reached | Date |
|---|---|---|---|---|---|---|
| Don Rodrigo II | Utrera, Sevilla | Urso Solar, SLU | 39.6 | 140 | Authorised to build | 19 Aug 2026 |
| BESS GES | Alcalá de Guadaíra, Sevilla | Gestenia Energía, SL | 39.6 | 140 | Authorised to build | 19 Aug 2026 |
| BESS Afrodita | Los Molares, Sevilla | Afrodita Solar, SL | 39.6 | 140 | Authorised to build | 18 Aug 2026 |
| Freya | Carmona, Sevilla | Freya Solar, SLU | 39.6 | 140 | Authorised to build | 31 Jul 2026 |
| SES | Alcalá de Guadaíra, Sevilla | Senen Energía, SL | 39.6 | 140 | Authorised to build | 20 Jul 2026 |
| Jade | Alcalá de Guadaíra, Sevilla | Jade Sostenible, SL | 39.6 | 140 | Authorised to build | 20 Jul 2026 |
| Heracles | Alcalá de Guadaíra, Sevilla | Heracles Solar, SLU | 39.6 | 140 | Authorised to build | 20 Jul 2026 |
| Esmeralda | Alcalá de Guadaíra, Sevilla | Esmeralda Solar, SL | 39.6 | 140 | Authorised to build | 20 Jul 2026 |
| Elvisa | Alcalá de Guadaíra, Sevilla | Elvisa Solar, SLU | 39.6 | 140 | Authorised to build | 16 Jul 2026 |
| Artemisa | Alcalá de Guadaíra, Sevilla | Artemisa Energía, SL | 39.6 | 140 | Authorised to build | 16 Jul 2026 |
| Demeter | Los Molares, Sevilla | Demeter Energía, S.L.U. | 39.6 | · | In public consultation | 18 May 2026 |
| Anubis | Los Molares, Sevilla | Anubis Energía, S.L.U. | 39.6 | · | In public consultation | 18 May 2026 |
| Híbrida Don Rodrigo III | Carmona, Sevilla | Teonas Solar, S.L.U. | 39.6 | · | In public consultation | 27 Apr 2026 |
| Agatha | Alcalá de Guadaira, Sevilla | Agatha Energía, S.L. | 39.6 | · | In public consultation | 23 Apr 2026 |
| Bianor | Utrera, Sevilla | Bianor Solar, SLU | 28.4 | 100 | Authorised to build | 25 Aug 2026 |
The substation as each act names it. The acts name a different promoter for each installation; which group stands behind them the gazette does not say.
The largest installations in the gazette
| Installation, as the gazette names it | Place | Promoter | MW | MWh | Step reached | Date |
|---|---|---|---|---|---|---|
| BAT Cedillo | Cedillo, Cáceres | Iberenova Promociones, S.A.U. | 215 | 888 | In public consultation | 2 Oct 2025 |
| BAT Oriol | Ceclavín, Cáceres | Dehesa Solar Sur, S.L. | 205 | 846 | In public consultation | 3 Nov 2025 |
| ST Palmosilla | Tarifa, Cádiz | Rolwind Andalucía 10, SL | 200 | 885 | First authorisation | 4 Jun 2026 |
| Valdesolar | Valdecaballeros, Badajoz | Valdesolar Hive S.L. | 200 | 413 | In public consultation | 17 Mar 2026 |
| Tagus 2 HBESS | Ocaña, Toledo | Khons Sun Power, SL | 176 | 662 | Authorised to build | 16 Oct 2026 |
| BESS II Valle Solar | Jarafuel, Valencia | BOMBO VALLE SOLAR, S.L. | 167 | 333 | Environmental decision | 12 Feb 2026 |
| BESS FV La Puebla 3 | Cerro de Andévalo, Huelva | Jinko Greenfield Spain 1, S.L. | 150 | 600 | In public consultation | 16 Sep 2026 |
| La Farga BESS | Vilademuls, Girona | Cadaques Directorship, SL | 148 | 297 | First authorisation | 16 May 2026 |
| BESS Gaetana | La Roca de la Sierra, Badajoz | Gaetana Solar, SLU | 120 | 432 | In public consultation | 9 Jul 2026 |
| SPK Trujillo | Trujillo, Cáceres | SPK FALCON, S.L. | 109 | 402 | In public consultation | 23 Jun 2026 |
| BESS AUREA | La Roca de la Sierra, Badajoz | Aurea Solar, S.L.U | 108 | 432 | In public consultation | 6 Jul 2026 |
| Picassent BESS 132 kV | Picassent, Valencia | Sargao Energy, SL | 108 | 216 | First authorisation | 21 May 2026 |
Every installation, with a page each listing the acts behind it. The register as a CSV.
Over the thirty days to 26 October 2026, Spanish power was cheapest at 14:00, €53/MWh on average, and dearest at 20:00, €241/MWh
A battery earns by buying power when it is cheap and selling it when it is dear. Spain’s solar farms push the price down in the middle of the day and it climbs again after sunset, which is the shape a Spanish battery trades. Each bar is the average day-ahead price in that hour of the day; the two cheapest and the two dearest hours are in colour.
OMIE, the Spanish day-ahead price of every quarter hour from 27 September 2026 to 26 October 2026, averaged by hour. Days when the clocks change are left out of the shape.
On the median day of September 2026, the two dearest hours cost €216/MWh more than the two cheapest
That gap is what a battery that charges and discharges once a day for two hours is paid to close, before its losses. Each bar is the month’s median day. In October 2025 the gap was €104/MWh.
The two hour spread is the average of the day’s eight dearest quarter hours less the average of its eight cheapest, as EPEX SPOT defines its TB2 index; the same figure as on the European prices page. OMIE’s prices, read daily to 25 October 2026. The last bar is the month so far.
20 batteries are registered to trade on OMIE, 256 MW where a source we may publish gives their size
OMIE publishes every day the units allowed to bid in the Iberian market, with the company that trades each. The storage units on it are the batteries registered to trade, grouped here one battery to a row. 13 have their size from the gazette or the owner’s own release. For the other seven, only Red Eléctrica’s register gives a size, and its terms allow publication for information only, so we have asked to publish it and show “held” until it answers.
| Battery | Province | Traded on OMIE by | MW | MWh | Configuration |
|---|---|---|---|---|---|
| Campo Arañuelo | Cáceres | Iberdrola Energía España | 52.7 | 120 | Added to a plant |
| Las Lomillas | Cuenca | EDP España | 36 | 72 | Added to a plant |
| Olmedilla | Cuenca | Iberdrola Energía España | 27.5 | 59.9 | Added to a plant |
| Revilla Vallejera | Burgos | Iberdrola Energía España | 27.5 | 59.9 | Added to a plant |
| Romeral | Cuenca | Iberdrola Energía España | 27.5 | 59.9 | Added to a plant |
| Andévalo | Huelva | Iberdrola Energía España | 26.4 | 59.9 | Added to a plant |
| Tabernas I | Almería | Naturgy (Gas Natural Comercializadora) | 19.8 | 46.7 | Added to a plant |
| Tabernas II | Almería | Naturgy (Gas Natural Comercializadora) | 19.8 | 46.7 | Added to a plant |
| Abadiño | Bizkaia | Iberdrola Energía España | 6 | 3.5 | Added to a plant |
| Elgea-Urkilla | Araba/Álava | Iberdrola Energía España | 5 | 5 | Added to a plant |
| Puertollano | Ciudad Real | Iberdrola Energía España | 5 | 22.8 | Added to a plant |
| Extremadura III | Badajoz | Acciona Green Energy Developments | 2 | 5 | Added to a plant |
| ACADIEMS | · | Ignis Energía | 1 | 1.8 | Stand-alone |
| Cuerva | Toledo | Energya VM | held | · | Stand-alone |
| FV ALZ | · | Iberdrola Energía España | held | · | Added to a plant |
| FV ALZ II | · | Iberdrola Energía España | held | · | Added to a plant |
| Hércules | Zamora | Solaria Representación en Mercado | held | · | Added to a plant |
| Soto de Ribera | Asturias | EDP España | held | · | Added to a plant |
| TOR I | · | Solaria Representación en Mercado | held | · | Added to a plant |
| XEN | · | Gnera Energía y Tecnología | held | · | Not stated |
Registered to trade is not by itself proof of running; what each battery has traded is below, from OMIE’s matched offers. OMIE’s storage list also carries Portuguese units, since the Iberian market is one, and units held by the regulated retailers that name no site; neither is counted here. Every registered battery, with a page each; the companies that trade them.
Spain’s batteries bought 10.9 GWh to charge in June 2026, nearly seven times as much as in the whole of 2025, at €22/MWh on average
OMIE publishes, about ninety days after each day, every offer made in the day-ahead market and the intraday auctions, with the unit that made it and how much of it was matched. A battery charges through a charging unit of its own, so what that unit bought is the battery’s charging, priced at what the market cleared at. Each bar is a month of the fleet’s charging.
OMIE, the offer curves of the day-ahead market and the intraday auctions with every unit named, January 2024 to June 2026, the latest month OMIE has published in full; each matched megawatt valued at the Spanish price of its market and period. Balancing services and the continuous intraday market are not in these files. OMIE’s monthly files lack the intraday offers of 29 April 2025 and 28 February 2026, though the auctions were held, so those days’ intraday trades are not counted.
They charge in the middle of the day: 83% of their charging falls between 12:00 and 17:00, when solar makes power cheapest
Each bar is the average power the batteries bought in that hour of the day, from their charging units, over April 2026, May 2026, June 2026. Set it beside the price shape above: the batteries buy in the hours when the price is lowest.
What each battery bought and sold, July 2025 to June 2026
A battery’s sales are its own only where every unit it trades through is a storage unit and it sold no more than it bought, since a battery loses energy on the way. Two pass that test. Most of Spain’s batteries were added to a solar or wind plant and sell through a unit they share with it, so that unit’s sales are the plant’s output and the battery’s together. Two have storage units of their own but sold more than they bought, so they also charge from the plant beside them without buying.
| Battery | First traded on its own units | Bought to charge, MWh | Average price paid | What it sold |
|---|---|---|---|---|
| Revilla Vallejera | Mar 2026 | 5,566 | €11 | Not its own: it sells through a unit it shares with its plant |
| Olmedilla | Mar 2026 | 5,167 | €7.6 | Not its own: it sells through a unit it shares with its plant |
| Romeral | Mar 2026 | 4,845 | €8.4 | Not its own: it sells through a unit it shares with its plant |
| Puertollano | Aug 2024 | 3,392 | €5.5 | Not its own: it sells through a unit it shares with its plant |
| XEN | Nov 2025 | 2,272 | €15 | Not its own: it sold 5.62 times what it bought, so it also charges from its plant without buying |
| Andévalo | Jun 2026 | 2,104 | €35 | Not its own: it sells through a unit it shares with its plant |
| FV ALZ | Jun 2026 | 942 | €19 | Not its own: it sells through a unit it shares with its plant |
| Elgea-Urkilla | Jul 2024 | 688 | €7.5 | Not its own: it sells through a unit it shares with its plant |
| Abadiño | Jan 2024 | 482 | €8.4 | Not its own: it sold 1.01 times what it bought, so it also charges from its plant without buying |
| FV ALZ II | Jun 2026 | 454 | €28 | Not its own: it sells through a unit it shares with its plant |
| ACADIEMS | Sep 2025 | 428 | €21 | €103/MWh; received less paid, €39 a kW a year |
| Extremadura III | Nov 2025 | 332 | €43 | Not its own: it sells through a unit it shares with its plant |
| Soto de Ribera | Dec 2025 | 25.7 | €13 | €70/MWh; received less paid, €3.7 a kW a year |
| Hércules | · | · | · | Not its own: it sells through a unit it shares with its plant |
| Campo Arañuelo | · | · | · | Not its own: it has no storage unit of its own on OMIE |
No offer yet matched on their own storage units, which can mean a battery not yet running or one that charges only from its plant: Las Lomillas, Tabernas I, Tabernas II, Cuerva, Hércules, TOR I. Received less paid leaves out balancing services, the continuous intraday market and what a battery pays the grid, and it is for a year per kilowatt of the battery’s published power, over the months it traded. Basado en datos de OMIE.
50 installations authorised to build, 1,623 MW
The largest twelve. Every one was given its first authorisation and its authorisation to build in one act, so the date is that act’s.
| Installation, as the gazette names it | Place | Promoter | MW | MWh | Date |
|---|---|---|---|---|---|
| Tagus 2 HBESS | Ocaña, Toledo | Khons Sun Power, SL | 176 | 662 | 16 Oct 2026 |
| Storage at Gecama | Atalaya de Cañavate, Cuenca | Generación Eólica Castilla-La Mancha, SL | 100 | 200 | 14 Jul 2025 |
| ST Cerrillo | Álora, Málaga | Rolwind Málaga 1, SL | 77.6 | 340 | 5 Jun 2026 |
| BESS SOLÓRZANO | Solórzano, Cantabria | Bess Development 6, S. L. | 49.7 | 200 | 7 Aug 2026 |
| Hibridación Covatillas 3 | Castillejo de Iniesta, Cuenca | Planta Solar OPDE 25, SL | 43.9 | 300 | 21 Aug 2026 |
| Don Rodrigo II | Utrera, Sevilla | Urso Solar, SLU | 39.6 | 140 | 19 Aug 2026 |
| BESS GES | Alcalá de Guadaíra, Sevilla | Gestenia Energía, SL | 39.6 | 140 | 19 Aug 2026 |
| BESS Afrodita | Los Molares, Sevilla | Afrodita Solar, SL | 39.6 | 140 | 18 Aug 2026 |
| Freya | Carmona, Sevilla | Freya Solar, SLU | 39.6 | 140 | 31 Jul 2026 |
| SES | Alcalá de Guadaíra, Sevilla | Senen Energía, SL | 39.6 | 140 | 20 Jul 2026 |
| Jade | Alcalá de Guadaíra, Sevilla | Jade Sostenible, SL | 39.6 | 140 | 20 Jul 2026 |
| Heracles | Alcalá de Guadaíra, Sevilla | Heracles Solar, SLU | 39.6 | 140 | 20 Jul 2026 |
Every installation, sorted the same way.
11 installations refused, withdrawn or rejected, 489 MW
| Installation | Province | MW | Ended by |
|---|---|---|---|
| Visenta | Huesca | 100 | withdrawn, 10 Jul 2026 |
| Perdiguero | Huesca | 100 | withdrawn, 25 Jun 2026 |
| El Tello | Valencia | 63 | unfavourable environmental decision |
| BESS San Martín | Teruel | 60.8 | withdrawn, 25 Jun 2026 |
| Las Regañas | Barcelona | 51 | unfavourable environmental decision |
| BESS Mudéjar | Teruel | 41.6 | refused, 30 Jul 2026 |
| Storage at P.E. San Blas | Valladolid | 20 | withdrawn, 18 Aug 2026 |
| Storage at Fuente-Álamo | Albacete | 20 | refused, 9 Oct 2025 |
| BESS El Tambor | Teruel | 19 | withdrawn, 25 Jun 2026 |
| Piruquito | Cantabria | 8.5 | unfavourable environmental decision |
| Raposeras | La Rioja | 5 | withdrawn, 30 May 2026 |
The Canary Islands
The islands are their own small grids, apart from the mainland’s, and some of the Canary government’s battery acts appear in the State gazette as well as its own. Seven installations, 25 MW:
- Sistema de almacenamiento de energía con baterías Marzagán, Las Palmas, 8 MW, in public consultation
- HIB. SAE PILETAS I, Las Palmas, 6.3 MW, first authorisation
- Sistema de Almacenamiento de Energía con Baterías (SAEB) Barranco Seco 4, Las Palmas, 5 MW, in public consultation
- Sistema de Almacenamiento de Energía con Baterías (SAEB) Barranco Seco, Las Palmas, 5 MW, in public consultation
- Storage at Planta Fotovoltaica Los Frailes, Las Palmas, 0.8 MW, in public consultation
- Bess Valle de Güímar, Santa Cruz de Tenerife, · MW, in public consultation
- BESS ICOR II, Santa Cruz de Tenerife, · MW, declared of public utility
What is not here, and why
A connection queue, because Spain publishes connection requests only as totals by node, under the CNMC’s Circular 6/2025; we have asked the CNMC to publish its maps of capacity by node and will add them when it answers. Any figure only Red Eléctrica gives, including the registered power of the batteries marked “held”, until it answers our letter of 23 October 2026. Batteries authorised by the regions rather than the State: the State authorises installations over 50 MW, those crossing more than one region and those added to a plant it authorised, and the regions authorise the rest in their own gazettes, which are being read but are not yet in this register. A meter on any battery, and what any battery earns. Prices: the Spanish day-ahead price is on the European prices page. Nothing on this page is modelled.
Sources: Boletín Oficial del Estado, every act on battery storage since 1 January 2021, read to 25 October 2026. Basado en datos de la Agencia Estatal Boletín Oficial del Estado; this page is not an official publication. OMIE, the list of units allowed to bid, read daily since 23 October 2026, used with the source named. Municipality centres from the Instituto Geográfico Nacional. Land from Natural Earth.