BESS El Tambor

A battery installation of 19 MW in Híjar, Teruel, refused, withdrawn or rejected. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power19 MW
PromoterEnel Green Power España, SL
ConfigurationAdded to a plant
Plant it is added toEl Tambor, 65.3 MW, solar and wind
MunicipalityHíjar, Samper de Calanda
ProvinceTeruel
SubstationMudéjar 400 kV
Step reachedRefused, withdrawn or rejected

Every act, oldest first

PublishedWhat the act doesAuthorityAct
26 Feb 2026Environmental decision; 19 MWMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2026-4494
25 Jun 2026Withdrawal, the promoter’s or the State’s; 19 MWMinistry for the Ecological Transition, Directorate-General for Energy Policy and MinesBOE-A-2026-13870

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.