A battery installation of 43.9 MW and 300 MWh in Castillejo de Iniesta, Cuenca, authorised to build. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power43.9 MW
Storage300 MWh
Hours at full power6.8
PromoterPlanta Solar OPDE 25, SL
ConfigurationAdded to a plant
Plant it is added toCovatillas 3, 48.1 MW, solar
Access capacity41.7 MW
MunicipalityCastillejo de Iniesta
ProvinceCuenca
SubstationMinglanilla 400 kV
Step reachedAuthorised to build

Every act, oldest first

PublishedWhat the act doesAuthorityAct
16 Mar 2026Public consultation; 43.9 MW, 300 MWhSubdelegación del Gobierno en CuencaBOE-B-2026-8111
21 Aug 2026First authorisation (autorización administrativa previa), authorisation to build (autorización administrativa de construcción); 43.9 MW, 300 MWhMinistry for the Ecological Transition, Directorate-General for Energy Policy and MinesBOE-A-2026-18008