Bess Valle de Güímar

A battery installation in Arafo, Santa Cruz de Tenerife, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery powernot stated in any act
Storage41.3 MWh
PromoterBess Development 5,S.L.
ConfigurationNot stated
Access capacity10 MW
MunicipalityArafo
ProvinceSanta Cruz de Tenerife
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
22 May 2024Public consultation; 41.3 MWhGobierno de Canarias, Dirección General de EnergíaBOE-B-2024-18536
29 Jan 2025Public consultationGobierno de Canarias, Dirección General de EnergíaBOE-B-2025-3007

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.