BESS II Valle Solar
A battery installation of 167 MW and 333 MWh in Jarafuel, Valencia, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 167 MW |
| Storage | 333 MWh |
| Hours at full power | 2.0 |
| Promoter | BOMBO VALLE SOLAR, S.L. |
| Also named | SPV Genia Davinci, SL |
| Configuration | Added to a plant |
| Plant it is added to | Valle Solar, 192 MW, solar |
| Municipality | Jarafuel |
| Province | Valencia |
| Step reached | Environmental decision |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 8 Apr 2025 | Environmental decision; 167 MW, 333 MWh | Ministry for the Ecological Transition, Directorate-General for Environmental Quality and Assessment | BOE-A-2025-7087 |
| 12 Feb 2026 | Public consultation; 167 MW, 333 MWh | Subdelegación del Gobierno en Valencia, Área de Industria y Energía | BOE-B-2026-4036 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.