Tagus 2 HBESS
A battery installation of 176 MW and 662 MWh in Ocaña, Toledo, authorised to build. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 176 MW |
| Storage | 662 MWh |
| Hours at full power | 3.8 |
| Promoter | Khons Sun Power, SL |
| Configuration | Added to a plant |
| Plant it is added to | Tagus 2, 224 MW, solar |
| Access capacity | 177 MW |
| Municipality | Ocaña, Ontígola |
| Province | Toledo |
| Substation | Arganda 220 kV |
| Step reached | Authorised to build |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 4 Jun 2026 | Public consultation; 176 MW, 662 MWh | Delegación del Gobierno en Castilla-La Mancha (Área de Industria y Energía) | BOE-B-2026-18625 |
| 16 Oct 2026 | First authorisation (autorización administrativa previa), authorisation to build (autorización administrativa de construcción); 176 MW, 662 MWh | Ministry for the Ecological Transition, Directorate-General for Energy Policy and Mines | BOE-A-2026-21605 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.