Sistema de Almacenamiento de Energía con Baterías (SAEB) Barranco Seco 4
A battery installation of 5 MW and 22.4 MWh in Las Palmas de Gran Canaria, Las Palmas, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 5 MW |
| Storage | 22.4 MWh |
| Hours at full power | 4.5 |
| Promoter | Iberdrola Renovables Canarias. S.A.U. |
| Configuration | Stand-alone |
| Access capacity | 5 MW |
| Municipality | Las Palmas de Gran Canaria |
| Province | Las Palmas |
| Step reached | In public consultation |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 29 May 2025 | Public consultation; 5 MW, 22.4 MWh | Gobierno de Canarias, Dirección General de Energía | BOE-B-2025-19696 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.