Vitreous LabsEnergy transparency

Las Regañas

A battery installation of 51 MW and 204 MWh in Rubí, Barcelona, refused, withdrawn or rejected. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power51 MW
Storage204 MWh
Hours at full power4.0
PromoterPLANTA SOLAR OPDE, 34 S.L.
ConfigurationStand-alone
MunicipalityRubí
ProvinceBarcelona
SubstationCan Jardi 220 kV
Step reachedRefused, withdrawn or rejected

Every act, oldest first

PublishedWhat the act doesAuthorityAct
22 Jul 2025Environmental decision; 51 MW, 204 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2025-15214
24 Dec 2025Public consultation; 51 MWDelegación del Gobierno en CataluñaBOE-B-2025-47609

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.

All installations  ·  On the map  ·  PLANTA SOLAR OPDE, 34 S.L.