Sistema de almacenamiento de energía con baterías Marzagán

A battery installation of 8 MW and 40.3 MWh in Telde, Las Palmas, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power8 MW
Storage40.3 MWh
Hours at full power5.0
PromoterIberdrola Renovables Canarias, S.A.U.
ConfigurationStand-alone
MunicipalityTelde
ProvinceLas Palmas
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
21 May 2025Public consultation; 8 MW, 40.3 MWhGobierno de CanariasBOE-B-2025-18392

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.