Don Rodrigo II

A battery installation of 39.6 MW and 140 MWh in Utrera, Sevilla, authorised to build. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power39.6 MW
Storage140 MWh
Hours at full power3.5
PromoterUrso Solar, SLU
ConfigurationAdded to a plant
Plant it is added toDon Rodrigo II, 45.6 MW, solar
Access capacity40.8 MW
MunicipalityUtrera
ProvinceSevilla
SubstationDon Rodrigo 400 kV
Step reachedAuthorised to build

Every act, oldest first

PublishedWhat the act doesAuthorityAct
23 Apr 2026Public consultation; 39.6 MWSubdelegación del Gobierno en SevillaBOE-B-2026-12663
19 Aug 2026First authorisation (autorización administrativa previa), authorisation to build (autorización administrativa de construcción); 39.6 MW, 140 MWhMinistry for the Ecological Transition, Directorate-General for Energy Policy and MinesBOE-A-2026-17939

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.