ST Palmosilla

A battery installation of 200 MW and 885 MWh in Tarifa, Cádiz, first authorisation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power200 MW
Storage885 MWh
Hours at full power4.4
PromoterRolwind Andalucía 10, SL
ConfigurationStand-alone
Access capacity200 MW
MunicipalityTarifa
ProvinceCádiz
SubstationPuerto de la Cruz 220 kV
Step reachedFirst authorisation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
11 Nov 2024Environmental decision; 200 MW, 885 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2024-23395
25 Apr 2025Public consultation; 200 MW, 885 MWhDelegación del Gobierno en Andalucía, Área de Industria y EnergíaBOE-B-2025-15042
18 Mar 2026Public consultation; 200 MWDelegación del Gobierno en Andalucía, Área de Industria y EnergíaBOE-B-2026-8374
4 Jun 2026First authorisation (autorización administrativa previa); 200 MW, 885 MWhMinistry for the Ecological Transition, Directorate-General for Energy Policy and MinesBOE-A-2026-12017

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.