ST Palmosilla
A battery installation of 200 MW and 885 MWh in Tarifa, Cádiz, first authorisation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 200 MW |
| Storage | 885 MWh |
| Hours at full power | 4.4 |
| Promoter | Rolwind Andalucía 10, SL |
| Configuration | Stand-alone |
| Access capacity | 200 MW |
| Municipality | Tarifa |
| Province | Cádiz |
| Substation | Puerto de la Cruz 220 kV |
| Step reached | First authorisation |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 11 Nov 2024 | Environmental decision; 200 MW, 885 MWh | Ministry for the Ecological Transition, Directorate-General for Environmental Quality and Assessment | BOE-A-2024-23395 |
| 25 Apr 2025 | Public consultation; 200 MW, 885 MWh | Delegación del Gobierno en Andalucía, Área de Industria y Energía | BOE-B-2025-15042 |
| 18 Mar 2026 | Public consultation; 200 MW | Delegación del Gobierno en Andalucía, Área de Industria y Energía | BOE-B-2026-8374 |
| 4 Jun 2026 | First authorisation (autorización administrativa previa); 200 MW, 885 MWh | Ministry for the Ecological Transition, Directorate-General for Energy Policy and Mines | BOE-A-2026-12017 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.