Circle area is the megawatts
Poland · the batteries in PSE’s connection queue · edition of 30 September 2026
PSE’s queue holds 78 battery projects with signed connection agreements, 13.2 GW, and 162 more with connection conditions, 33.2 GW.
PSE publishes every project asking to connect to its grid, with the applicant, the connection point and every date. These are the storage projects in it, each at its connection point where OpenStreetMap maps a substation of that name. The distribution operators’ queues are not yet drawn.
Showing every storage project in PSE’s list. Filter by stage, type, voltage or whether it could be placed, or search a project, an applicant or a substation.
Every storage project in PSE’s queue
Largest first. Power is the storage discharge power PSE lists, never a hybrid’s whole connection. The date is the agreement’s, the conditions’ or the application’s, whichever is latest. A project naming two connection points carries both.
| Project | Applicant | Connection point | Stage | MW | Date |
|---|
Source: PSE S.A., Informacje publikowane zgodnie z Art. 7 ust. 8l ustawy Prawo energetyczne, stan na 30 September 2026, the rows of type MEE and MIX with storage. Positions from OpenStreetMap. Nothing here is modelled.