Valdesolar

A battery installation of 200 MW and 413 MWh in Valdecaballeros, Badajoz, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power200 MW
Storage413 MWh
Hours at full power2.1
PromoterValdesolar Hive S.L.
ConfigurationAdded to a plant
Plant it is added toValdesolar, 221 MW, solar
MunicipalityValdecaballeros
ProvinceBadajoz
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
17 Mar 2026Public consultation; 200 MW, 413 MWhDelegación del Gobierno en ExtremaduraBOE-B-2026-8272

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.