A battery installation of 39.6 MW in Los Molares, Sevilla, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power39.6 MW
PromoterAnubis Energía, S.L.U.
ConfigurationAdded to a plant
Plant it is added toAnubis, 46.2 MW, solar
MunicipalityLos Molares
ProvinceSevilla
SubstationDon Rodrigo 400 kV
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
18 May 2026Public consultation; 39.6 MWSubdelegación del Gobierno en SevillaBOE-B-2026-15996

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.