A battery installation of 2 MW and 8.5 MWh in Oyón-Oion, Araba/Álava, refused, withdrawn or rejected. Every fact below is taken from the latest act in the regional gazette of the Basque Country that states it, and every act is linked.

In the gazette

Battery power2 MW
Storage8.5 MWh
Hours at full power4.3
PromoterButroe, S.L.
ConfigurationStand-alone
MunicipalityOyón-Oion
ProvinceAraba/Álava
SubstationLínea 1 Oyón-Casablanca 13,2 kV
Step reachedRefused, withdrawn or rejected

Every act, oldest first

PublishedWhat the act doesAuthorityAct
9 Oct 2025Environmental decision; 2 MW, 8.5 MWhIndustria, Transición Energética y SostenibilidadBOPV-2025-10-4282
2 Feb 2026Other act; 2 MWIndustria, Transición Energética y SostenibilidadBOPV-2026-02-500

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of the Basque Country, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.