A battery installation of 30 MW and 124 MWh in Cedillo, Cáceres, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power30 MW
Storage124 MWh
Hours at full power4.1
PromoterSolar Majada Alta, S.L.
ConfigurationAdded to a plant
Plant it is added toFV San Antonio, 42 MW, solar
Access capacity267 MW
MunicipalityCedillo
ProvinceCáceres
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
15 Sep 2025Environmental decision; 30 MW, 124 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2025-18284
2 Oct 2025Public consultation; 30 MW, 124 MWhDelegación del Gobierno en ExtremaduraBOE-B-2025-35404

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.