BESS Cillamayor

A battery installation of 25.4 MW and 110 MWh in Aguilar de Campoo, Palencia, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power25.4 MW
Storage110 MWh
Hours at full power4.3
PromoterMacrina Solar 6, SL
ConfigurationAdded to a plant
Plant it is added toCillamayor 49,90 MW, 49.9 MW, solar
MunicipalityAguilar de Campoo
ProvincePalencia
SubstationCillamayor 220 kV
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
6 Oct 2026Public consultation; 25.4 MW, 110 MWhSubdelegación del Gobierno en PalenciaBOE-B-2026-32448