A battery installation of 10 MW and 45.1 MWh in Belchite, Zaragoza, in public consultation. Every fact below is taken from the latest act in the regional gazette of Aragón that states it, and every act is linked.

In the gazette

Battery power10 MW
Storage45.1 MWh
Hours at full power4.5
PromoterElawan Fotovoltaica Fuendetodos 2, SL
ConfigurationAdded to a plant
Plant it is added toParque eólico Elawan Fuendetodos II híbrido, wind + solar
MunicipalityBelchite
ProvinceZaragoza
SubstationSET Elawan Fuendetodos 30/132 kV
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
13 Oct 2026Public consultation; 10 MW, 45.1 MWhDEPARTAMENTO DE ECONOMÍA, COMPETITIVIDAD Y EMPLEOBOA-007961681

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Aragón, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.

All installations  ·  On the map