PB Babor 6

A battery installation of 28.6 MW in Ortuella, Bizkaia, first authorisation. Every fact below is taken from the latest act in the regional gazette of the Basque Country that states it, and every act is linked.

In the gazette

Battery power28.6 MW
PromoterArena Green Assets 5, S.L.U.
ConfigurationStand-alone
MunicipalityOrtuella, Santurtzi
ProvinceBizkaia
SubstationColectora Santurce 220/30 kV
Step reachedFirst authorisation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
22 Feb 2026Environmental decision; 28.6 MWIndustria, Transición Energética y SostenibilidadBOPV-2026-02-802
18 Oct 2026First authorisation (autorización administrativa previa); 28.6 MWIndustria, Transición Energética y SostenibilidadBOPV-2026-10-4363

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of the Basque Country, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.

All installations  ·  On the map