MHIA Águila II-III unificado

A battery installation of 33 MW and 66 MWh in Pedrola, Zaragoza, environmental decision. Every fact below is taken from the latest act in the regional gazette of Aragón that states it, and every act is linked.

In the gazette

Battery power33 MW
Storage66 MWh
Hours at full power2.0
PromoterDesarrollos Renovables del Ebro, SL
ConfigurationAdded to a plant
Plant it is added toPlanta fotovoltaica Águila II-III unificado (16 MW), solar
MunicipalityPedrola
ProvinceZaragoza
SubstationCoscojar II 220/30 kV
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
30 Aug 2024Public consultationDEPARTAMENTO DE MEDIO AMBIENTE Y TURISMOBOA-007943354
6 Sep 2024Public consultationDEPARTAMENTO DE MEDIO AMBIENTE Y TURISMOBOA-007943448
23 Jul 2025Environmental decision; 33 MW, 66 MWhDEPARTAMENTO DE MEDIO AMBIENTE Y TURISMOBOA-007950995

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Aragón, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.