PB Navegantes 32

A battery installation of 65 MW and 210 MWh in Mieres, Asturias, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power65 MW
Storage210 MWh
Hours at full power3.2
PromoterArena Power Ren 34, SLU; Arena Power Ren 31, SLU
ConfigurationStand-alone
MunicipalityMieres
ProvinceAsturias
SubstationLa Pereda 220 kV
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
18 Apr 2026Environmental decision; 65 MW, 210 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2026-8573

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.