PB Navegantes 32
A battery installation of 65 MW and 210 MWh in Mieres, Asturias, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 65 MW |
| Storage | 210 MWh |
| Hours at full power | 3.2 |
| Promoter | Arena Power Ren 34, SLU; Arena Power Ren 31, SLU |
| Configuration | Stand-alone |
| Municipality | Mieres |
| Province | Asturias |
| Substation | La Pereda 220 kV |
| Step reached | Environmental decision |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 18 Apr 2026 | Environmental decision; 65 MW, 210 MWh | Ministry for the Ecological Transition, Directorate-General for Environmental Quality and Assessment | BOE-A-2026-8573 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.
All installations · On the map · Arena Power Ren 34, SLU; Arena Power Ren 31, SLU