Vitreous LabsEnergy transparency

Rhea

A battery installation of 20 MW and 40 MWh in Budia, Guadalajara, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power20 MW
Storage40 MWh
Hours at full power2.0
PromoterPlanta FV 146 SL, Planta FV 148 SL, Planta FV 149 SL, Planta FV 147 SL, Planta FV 145 SL y Planta FV 144 SL
ConfigurationAdded to a plant
Plant it is added toRhea, solar
MunicipalityBudia
ProvinceGuadalajara
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
16 Mar 2026Environmental decision; 20 MW, 40 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2026-6209

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.

All installations  ·  On the map  ·  Planta FV 146 SL, Planta FV 148 SL, Planta FV 149 SL, Planta FV 147 SL, Planta FV 145 SL y Planta FV 144 SL