Sistema de almacenamiento BESS hibridación parque eólico Jedey

A battery installation of 2 MW in San Sebastián de La Gomera, Santa Cruz de Tenerife, authorised to build. Every fact below is taken from the latest act in the regional gazette of the Canary Islands that states it, and every act is linked.

In the gazette

Battery power2 MW
PromoterSiempreviva Gigante, S.L.
ConfigurationAdded to a plant
Plant it is added toParque Eólico Jedey, wind
MunicipalitySan Sebastián de La Gomera
ProvinceSanta Cruz de Tenerife
Step reachedAuthorised to build

Every act, oldest first

PublishedWhat the act doesAuthorityAct
4 Dec 2024Public consultationConsejería de Transición Ecológica y EnergíaBOC-A-2024-242-4039
23 Jan 2025Public consultationConsejería de Transición Ecológica y EnergíaBOC-A-2025-015-302
27 Apr 2026Authorisation to build (autorización administrativa de construcción); 2 MWConsejería de Transición Ecológica y EnergíaBOC-A-2026-080-1346
18 May 2026First authorisation (autorización administrativa previa); 2 MWConsejería de Transición Ecológica y EnergíaBOC-A-2026-094-1632

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of the Canary Islands, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.