A battery installation of 21.4 MW in Badajoz, Badajoz, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power21.4 MW
PromoterNaturgy Renovables, SLU
ConfigurationAdded to a plant
Plant it is added toLos Naipes, 46.4 MW, solar
MunicipalityBadajoz
ProvinceBadajoz
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
11 May 2026Environmental decision; 21.4 MWMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2026-10216

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.