ALM Cimera Solar

A battery installation of 19.7 MW in Pinos Puente, Granada, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power19.7 MW
PromoterCimera Solar S.L.U.
ConfigurationAdded to a plant
Plant it is added toCimera Solar, solar
MunicipalityPinos Puente
ProvinceGranada
SubstationCaparacena 400 kV
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
6 Oct 2026Public consultation; 19.7 MWSubdelegación del Gobierno en GranadaBOE-B-2026-32445

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.