A battery installation of 1.4 MW and 5 MWh in Santa Lucía de Tirajana, Las Palmas, authorised to build. Every fact below is taken from the latest act in the regional gazette of the Canary Islands that states it, and every act is linked.

In the gazette

Battery power1.4 MW
Storage5 MWh
Hours at full power3.6
PromoterAtlantic Generation, S.L.
ConfigurationAdded to a plant
Plant it is added toParque Fotovoltaico Balos, solar
MunicipalitySanta Lucía de Tirajana
ProvinceLas Palmas
Step reachedAuthorised to build

Every act, oldest first

PublishedWhat the act doesAuthorityAct
20 Oct 2025Public consultation; 1.4 MW, 5 MWhConsejería de Transición Ecológica y EnergíaBOC-A-2025-207-3602
30 Oct 2025Environmental decision; 1.4 MWConsejería de Transición Ecológica y EnergíaBOC-A-2025-215-3706
22 Dec 2025Authorisation to build (autorización administrativa de construcción); 1.4 MW, 5 MWhConsejería de Transición Ecológica y EnergíaBOC-A-2025-252-4352
3 Feb 2026First authorisation (autorización administrativa previa); 1.4 MWConsejería de Transición Ecológica y EnergíaBOC-A-2026-022-338

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of the Canary Islands, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.