A battery installation of 20 MW and 80 MWh in Corral-Rubio, Albacete, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 20 MW |
| Storage | 80 MWh |
| Hours at full power | 4.0 |
| Promoter | ELAWAN EÓLICA FRONTONES, S.L. |
| Configuration | Added to a plant |
| Plant it is added to | Planta Frontones Híbrida, 60 MW, solar and wind |
| Municipality | Corral-Rubio |
| Province | Albacete |
| Substation | Campanario 400 kV |
| Step reached | In public consultation |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 31 Aug 2026 | Public consultation; 20 MW, 80 MWh | Subdelegación del Gobierno en Albacete | BOE-B-2026-28211 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.