A battery installation of 102 MW and 407 MWh in Sant Julià de Ramis, Girona, first authorisation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power102 MW
Storage407 MWh
Hours at full power4.0
PromoterA Green Message, SL
ConfigurationStand-alone
Access capacity97 MW
MunicipalitySant Julià de Ramis
ProvinceGirona
SubstationLa Farga 220 kV
Step reachedFirst authorisation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
14 Jul 2025Environmental decision; 102 MW, 407 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2025-14560
26 Sep 2025Public consultation; 102 MW, 407 MWhDelegación del Gobierno en CataluñaBOE-B-2025-34547
17 Jun 2026First authorisation (autorización administrativa previa); 102 MW, 407 MWhMinistry for the Ecological Transition, Directorate-General for Energy Policy and MinesBOE-A-2026-13198

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.