A battery installation of 5 MW and 10 MWh in Rueda de Jalón, Zaragoza, first authorisation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power5 MW
Storage10 MWh
Hours at full power2.0
PromoterMolinos del Ebro, SA
ConfigurationAdded to a plant
Plant it is added toValdejalón, 50 MW, wind
Access capacity50 MW
MunicipalityRueda de Jalón
ProvinceZaragoza
SubstationJalón 220 kV
Step reachedFirst authorisation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
27 Mar 2024Public consultation; 5 MW, 10 MWhSubdelegación del Gobierno en ZaragozaBOE-B-2024-11134
22 Dec 2025Environmental decision; 5 MW, 10 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2025-26330
4 May 2026First authorisation (autorización administrativa previa); 5 MW, 10 MWhMinistry for the Ecological Transition, Directorate-General for Energy Policy and MinesBOE-A-2026-9683

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.