BESS CAMARREAL

A battery installation of 49.9 MW and 206 MWh in Camargo, Cantabria, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power49.9 MW
Storage206 MWh
Hours at full power4.1
PromoterFotowatio Renewable Ventures Servicios España, S.L.U.
ConfigurationStand-alone
MunicipalityCamargo
ProvinceCantabria
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
23 Jul 2026Public consultation; 49.9 MW, 206 MWhGobierno de Cantabria, Dirección General de Industria, Energía y MinasBOE-B-2026-24989

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.