BESS La Nava
A battery installation of 20.8 MW and 46.7 MWh in Almodóvar del Campo, Ciudad Real, authorised to build. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 20.8 MW |
| Storage | 46.7 MWh |
| Hours at full power | 2.2 |
| Promoter | Naturgy Renovables, SLU |
| Configuration | Added to a plant |
| Plant it is added to | La Nava, 46.2 MW, solar |
| Access capacity | 49.9 MW |
| Municipality | Almodóvar del Campo |
| Province | Ciudad Real |
| Step reached | Authorised to build |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 29 Mar 2023 | Public consultation; 19.8 MW, 46.7 MWh | Delegación del Gobierno en Castilla-La Mancha, Área de Industria y Energía | BOE-B-2023-9202 |
| 27 Mar 2025 | First authorisation (autorización administrativa previa), authorisation to build (autorización administrativa de construcción); 20.8 MW, 46.7 MWh | Ministry for the Ecological Transition, Directorate-General for Energy Policy and Mines | BOE-A-2025-6169 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.