Storage at instalación fotovoltaica existente OPDE Trévago 1
A battery installation of 30 MW in Fuentestrún, Soria, authorised to build. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 30 MW |
| Promoter | Planta Solar OPDE 42, SLU |
| Configuration | Added to a plant |
| Plant it is added to | instalación fotovoltaica existente OPDE Trévago 1, 34.8 MW |
| Municipality | Fuentestrún |
| Province | Soria |
| Substation | Trévago 220 kV |
| Step reached | Authorised to build |
Planta Solar OPDE 42, SLU belongs to Bruc Energy, traced through Spain’s companies gazette, the GLEIF register and the regulator’s reports; the State gazette itself names only the promoter.
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 9 Nov 2026 | First authorisation (autorización administrativa previa), authorisation to build (autorización administrativa de construcción); 30 MW | · | BOE-A-2026-23498* |
The acts marked with an asterisk have so far been read only by our parser, which can mistake a plant’s power for the battery’s; the full reading, with every figure checked against the act’s words, follows within a week. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.